FY 2023
Deliver full year 2023 production target of c. 2,090 boepd Details
14 Dec 2023
✓ Kept
2024
FY 2024
Net production of about 2,000 boepd in 2024 Details · +1
24 Apr 2024
✓ Kept
FY 2024
Cash capex in 2024 of £5.5m, later guided to £7.7m Details · +1
24 Apr 2024
✗ Missed · target changed
Q3 2024
Start formal farm-down process with potential partners in early Q3 2024 Details
12 Jun 2024
✗ Missed · target changed
Result
Not mentioned in the 4 results reports since the deadline (Q3 2024) – treated as dropped.
Q3 2024
Start Salisbury hospital seismic data acquisition and analysis in Q3 2024 Details
25 Jul 2024
✓ Kept
2025
30 Jun 2025
Repay Facility A (€6.7m) by end June 2025 Details
19 Jun 2025
✓ Kept
2025
Achieve G&A savings of about £1.5m a year from 2025 Details · +3
25 Jul 2024
✓ Kept
H1 2025
Complete Alton land sale for £6.3m in H1 2025 Details
12 Nov 2024
✓ Kept
FY 2025
Net production of about 2,000 boe/d in 2025 Details · +2
24 Feb 2025
✗ Missed
FY 2025
2025 capex of about £11m, later guided to £8.4m Details
24 Feb 2025
✗ Missed · target changed
Today · 20 Oct 2026
2026
early October 2026
Singleton gas-to-wire project online, adding about 74 boe/d, first expected mid-2025 then late 2025 Details · +4
18 Sep 2024
✗ Missed
Q3 2026
Reinstate Stockbridge production via water injector conversion in Q3 2026 Details
25 Feb 2026
✓ Kept
H2 2026
Complete sale of Croatian geothermal subsidiary IGeoPen in H2 2026 Details
24 Apr 2026
✓ Kept
FY 2026
Net production of about 2,000 boepd in 2026 Details · +2
29 Apr 2026
✗ Missed · target changed
FY 2026
Capital expenditure of about £6.6m in 2026 Details · +1
29 Apr 2026
… In progress
Status so far
Not yet due.