Star Energy Group Plc
STAR · AIM · Energy · mcap £39m · 20.5p 1 open situation →
Star Energy produces about 1,900 barrels of oil equivalent a day from UK oil and gas fields. It also has UK geothermal heat development projects.
Timeline · every situation
dots = announcementsOpen · 1
Project milestones
Singleton gas-to-wire project
Grid connection delayed; first production early October
Singleton gas-to-wire has been under way since February 2026, with £2.6m of capex to complete. The grid connection delay cut H1 production and is cited in the lowered full-year guidance. First production is now expected in early October 2026.
- Incremental output
- approximately 74 boepd
- Next milestone
- final grid connection and commissioning; first production early October 2026
- Other benefit
- materially reduces routine flaring at the site
- 16 Sep 2026 Grid connection delayed; first production early October
- 29 Apr 2026 Under way; £2.6m capex to complete
- 25 Feb 2026 Delayed; plant installed, awaiting grid connection