Synectics
SNX · AIM · Industrial Goods and Services · mcap £35m · 202.5p 2 open situations →
Synectics supplies Synergy security and surveillance software and related systems to gaming, energy, transport and critical infrastructure customers. Its Ocular Integration arm installs the systems, including CCTV on buses and security upgrades at utility sites.
| Target | Promise | Said | Status |
|---|---|---|---|
| 2024 | |||
| 30 Nov 2024 | Deliver three gaming contracts (Ontario, Omaha, Maryland) worth $2.0m during FY2024. | 24 Apr 2024 | ✓ Kept |
|
How it developed
Result
FY24 results showed revenue £55.8m, ahead of expectations; no delay to these contracts was reported. “Continued momentum in contract wins, including material Gaming awards announced in the US and South-East Asia worth an aggregate $4.9 million”4 Mar 2025 · Final Results |
|||
| 2025 | |||
| 30 Nov 2025 | Deliver US$10m South-East Asian gaming resort surveillance upgrade by 30 November 2025. | 18 Jun 2024 | ✓ Kept |
|
How it developed
Result
H1 2026 revenue fell on absence of prior-year gaming contract, indicating the work was largely completed in FY25. “As expected, trading in FY26 has returned towards the Group's more typical second-half weighting following the significant non-repeating gaming contract which benefited H1 last year.”18 Aug 2026 · Half-year Results |
|||
| 30 Nov 2025 | Board confident in FY2025 performance, underpinned by the £37.8m order book. | 9 Dec 2024 | ✓ Kept |
|
How it developed
Result
FY25 revenue £68.1m and adjusted EBITDA £8.5m, above the £65m revenue expectation. “Revenue increased by 22.0% to £68.1 million (FY24: £55.8 million) · Adjusted EBITDA1 increased by 36.1% to £8.5 million (FY24: £6.3 million)”3 Mar 2026 · Final Results and Strategic Update “FY25 has been an important year for Synectics. We delivered robust financial growth, supported by the successful execution of a major gaming project”3 Mar 2026 · Final Results and Strategic Update |
|||
| 30 Nov 2025 | Introduce subscription pricing for core Synergy technology by end of FY25. | 4 Mar 2025 | ✗ Missed · target changed |
|
How it developed
Result
Not mentioned in the 4 results reports since the deadline (2025-11-30) – treated as dropped. 17 Dec 2025 · Full Year Trading Update |
|||
| 2026 | |||
| 31 Mar 2026 | West Midlands Police first site live April 2025; remaining sites within twelve months. | 31 Mar 2025 | ✗ Missed · target changed |
|
How it developed
Result
Not mentioned in the 2 results reports since the deadline (2026-03-31) – treated as dropped. |
|||
| 12 May 2026 | Complete Stagecoach On-Board Hub pilot within twelve months. | 12 May 2025 | ◐ Partly kept |
|
Result
Stagecoach later extended its framework and placed £1.5m of orders; pilot completion not stated. 18 Jun 2026 · New Stagecoach Orders Totalling £1.5m |
|||
| Today · 20 Oct 2026 | |||
| FY26 | FY26 adjusted EBITDA in the range of £3.7m to £4.1m. | 18 Aug 2026 | … In progress |
|
Status so far
Not yet due. |
|||
| 2026 | Supply Qatar COEX camera stations in two phases, 2025 and 2026. | 25 Nov 2024 | … In progress |
|
Status so far
Not yet due. |
|||
| 2026 | Wider commercial launch of Synergy SEARCH later in 2026. | 11 Aug 2026 | … In progress |
|
Status so far
Not yet due. |
|||
| 2027 | |||
| 31 Mar 2027 | Deliver Kutei FPSO security and surveillance solution in Q1 2027. | 24 Aug 2026 | … In progress |
|
Status so far
Not yet due. |
|||
| FY27 | Double-digit revenue growth in FY27, EBITDA above normalised FY25 levels, and stronger performance from FY27. | 3 Mar 2026 | … In progress |
|
Also stated 18 Aug 2026
How it developed
Status so far
Not yet due. |
|||
| FY27 | Scalable growth: from FY27 by FY27 | 18 Aug 2026 | … In progress |
|
Status so far
Not yet due. |
|||