Sylvania Platinum Ltd

SLP · AIM · Basic Resources · mcap £251m · 93.0p

Sylvania retrieves platinum group metals (PGMs) and chrome from old mine tailings and current mine arisings in South Africa's Bushveld Complex. It also holds early-stage mining projects, Volspruit and Aurora.

TargetPromiseSaidStatus
2024
Q2 FY2024 Commence Thaba JV civil construction by Q2 FY2024 25 Oct 2023 ✓ Kept
2024-08 Deliver Volspruit PEA/scoping study and metallurgical results by August 2024 25 Oct 2023 ✓ Kept
2025
2025-06 Thaba JV first production by HY2 FY2025 (chrome May, PGMs June 2025) 22 Feb 2024 ✓ Kept
2026
FY2026 Achieve or exceed top of 90,000-93,000 ounce FY2026 guidance 29 Apr 2026 ✓ Kept