2024
Q3 FY2024
Commission Lannex fine grinding circuit by end of Q2 FY2024, optimisation in Q3 Details · +1
25 Oct 2023
◐ Partly kept
Q2 FY2024
Commence Thaba JV civil construction by Q2 FY2024 Details
25 Oct 2023
✓ Kept
FY2024
FY2024 production of 74,000-75,000 4E ounces Details · +1
22 Feb 2024
✗ Missed
Result
FY2024 production was 72,704 ounces, below the range.
“SDO produced 72,704 4E (92,4276E) PGM ounces for FY2024 (FY2023 75,469 4E PGM ounces; 95,965 6E PGM ounces)” 31 Jul 2024 · Fourth Quarter Report to 30 June 2024
“resulted in a lower than anticipated quarterly production and ultimate annual production of 72,704 4E PGM ounces for FY2024, marginally below our target of between 74,000 to 75,000 4E PGM ounces for the year” 31 Jul 2024 · Fourth Quarter Report to 30 June 2024
2024-08
Deliver Volspruit PEA/scoping study and metallurgical results by August 2024 Details · +2
25 Oct 2023
✓ Kept
2025
FY2025
Decide on Volspruit pre-feasibility study during FY2025 Details · +1
16 Feb 2024
◐ Partly kept
FY2025
FY2025 production of 73,000-76,000 4E ounces Details · +2
10 Sep 2024
✗ Missed · target changed
Q3 FY2025
Aurora geophysical survey results in Q3 FY2025 Details
29 Oct 2024
… In progress
Status so far
Not yet due.
Q3 FY2025
Submit Volspruit Water Use Licence Application in Q3 FY2025 Details
28 Jan 2025
… In progress
Status so far
Not yet due.
2025-06
Thaba JV first production by HY2 FY2025 (chrome May, PGMs June 2025) Details · +3
22 Feb 2024
✓ Kept
2026
Q3 FY2026
Thaba JV steady state production Details · +2
10 Sep 2024
✗ Missed
Q2 FY2026
Complete centralised PGM filtration plant at Lesedi in Q2 FY2026 Details · +1
28 Jan 2025
… In progress
Status so far
Not yet due.
Q2 FY2026
Lesedi ROM plant/crushing plant at steady state by Q2 FY2026 Details · +1
28 Jan 2025
✗ Missed · target changed
FY2026
FY2026 production of 83,000-86,000 4E ounces and 100,000-130,000 tons chromite Details · +2
9 Sep 2025
✗ Missed · target changed
Q4 FY2026
Thaba JV nameplate throughput by end of Q4 FY2026 Details
24 Feb 2026
✗ Missed
FY2026
Achieve or exceed top of 90,000-93,000 ounce FY2026 guidance Details
29 Apr 2026
✓ Kept
Today · 11 Oct 2026
2027
31 Mar 2027
Share buyback up to US$1.5m, ending by 31 March 2027 Details · +1
4 Mar 2024
… In progress
Status so far
Not yet due.
mid-FY2027
Build Lannex and Tweefontein tailings storage facilities, complete mid-FY2027 Details
24 Feb 2026
… In progress
Status so far
Not yet due.
FY2027
FY2027 production of 85,000-95,000 4E ounces and 110,000-140,000 tons chrome concentrate Details
15 Sep 2026
… In progress
Status so far
Not yet due.