05 Oct 26 3rd FlexGen Asset Build Completed & Other Updates
Bordesley 5 MW flexible generation project achieved substantial completion milestone and grid energisation; commercial operations expected Q4 2026.
−5.0%
24 Sep 26 Board change Business Update and QDE CEO Interview
CEO Pieter Krügel interviewed by Vox Markets on business progress and outlook.
+179.2%
24 Sep 26 Restoration of Listing
Temporary suspension of listing lifted; shares resume trading on LSE Main Market.
+179.2%
14 Sep 26 Hindlip Enters Commercial Operations
Hindlip 7.5 MW flexible generation asset enters commercial operations and begins trading electricity.
+0.0%
04 Sep 26 Results Half-year Results
H1 2026 revenue £792k, up 9% YoY; record 4.7 GWh generation; two projects advancing toward operations.
+0.0%
02 Sep 26 Results of Reconvened AGM
Reconvened AGM held with all resolutions carried; 1.47% of shares represented by proxy.
+0.0%
01 Sep 26 Hindlip 7.5 MW FlexGen - Construction Completion
Hindlip 7.5 MW flexible generation project completed construction and achieved grid energisation, delivered below budget.
+0.0%
11 Aug 26 Notice of Reconvened AGM
Reconvened Annual General Meeting scheduled for 2 September 2026 at registered office in London.
+0.0%
05 Aug 26 Update on Restoration of Listing and Share Trading
Company applies to restore listing and resume trading following publication of audited 2025 annual report.
+0.0%
05 Aug 26 Results Annual Report
London, UK - Quantum Data Energy PLC (LSE: QDE) is pleased to announce its annual audited results for the financial year ended 31 December 2025.
+0.0%
14 Jul 26 Warrant Expiry and Cancellation of Block Listings
Expiry of Warrants and Cancellation of Block Listings
+0.0%
06 Jul 26 Fundraise Audit Timeline & Fundraise Update
Audited accounts expected early August; Stage 2 equity fundraise cancelled as audit completion delayed.
+0.0%
30 Jun 26 Result of AGM
London, UK - Quantum Data Energy PLC (LSE: QDE) ("Quantum", "QDE" or the "Company") announces that the 2026 Annual General Meeting of the Company (the "AGM"), held at 1:00 p.m. on Tuesday, 30 June 2026 at the Company's r
+0.0%
18 Jun 26 Company’s Response to Former Auditor Resignation
Former auditor Crowe resigned unexpectedly two days before reporting deadline; company disputes reasons and considers legal action.
+0.0%
02 Jun 26 Appointment of New Auditor Finalised
Parker Russell UK LLP formally appointed as statutory auditor following previous announcement.
+0.0%
21 May 26 Appointment of New Auditor
Board progressing appointment of new auditor following casual vacancy; expects to announce shortly.
+0.0%
29 Apr 26 Temporary Suspension and Amendment to Equity Raise
Company requests temporary suspension of listing and amends equity fundraise structure to two-stage subscription.
−40.4%
29 Apr 26 Resignation of Auditor
Auditor Crowe UK LLP resigned unexpectedly; company will miss 30 April 2026 deadline for publishing audited accounts.
−40.4%
28 Apr 26 Bordesley Construction Commenced and on Schedule
Construction commenced on Bordesley 5 MW flexible generation asset, on schedule and budget targeting Q4 2026 commercial operations.
+0.0%
23 Apr 26 Business Update & Acceleration Capital Funding
Quantum Data Energy raises £1m via 38.5m shares at 2.6p to fund flexible generation project capex.
−25.4%
15 Apr 26 Board change Q2 2026 Update and CEO Interviewed on Vox Markets
CEO interviewed by Vox Markets on Q2 2026 business update and outlook.
+17.3%
31 Mar 26 Revenue Surge; Iran Conflict No Impact
Pyebridge generation up 61% to 3.3 GWh in Q1 2026; Iran conflict has no material impact on business.
+1.7%
25 Mar 26 AI Datacentre Power Supply Strategy Explainer Vid.
Company publishes video explainer on AI datacentre power supply strategy.
+4.0%
18 Mar 26 Hindlip Enters Final Phase; Pyebridge CM Award
Hindlip 7.5 MW project enters final construction phase on schedule and below budget; Pyebridge secures additional Capacity Market contract.
−1.1%
09 Mar 26 FlexGen Project Financial Close and Construction
Third FlexGen project reaches financial close with PBS investment; construction commenced.
−6.5%
26 Feb 26 Change of Share Ticker (TIDM)
Share ticker changed from MAST to QDE effective 27 February 2026 to complete rebranding.
−5.2%
19 Feb 26 Third FlexGen Funding & 7 MW Site Update
Third FlexGen project advances to near-final investment agreement with PBS; 7 MW brownfield acquisition progresses toward completion.
+16.8%
09 Feb 26 Business Growth Update and Capital Funding
Quantum Data Energy raises £1.165m via placing of 46.6m shares at 2.5p to fund Bordesley 5MW project.
−24.3%
03 Feb 26 New Record High Generation and Revenues
Pyebridge achieved record monthly generation of 1.8 GWh in January; third flexgen project progressing to financial close.
+13.8%
30 Jan 26 Board change Q1 2026 Business Update & CEO Interview
QDE rebranded to Quantum Data Energy and progresses datacentre power supply and development pipeline expansion.
+8.4%
13 Jan 26 Hindlip Makes Significant Construction Progress
Hindlip 7.5 MW power project on track for Q2 2026 completion with major construction milestones achieved.
−2.1%
06 Jan 26 Record Generation and Revenues For 2025
Pyebridge asset achieved record 10.8 GWh generation and £1.6m revenues in 2025, up 71% and 136% respectively.
−6.6%
18 Dec 25 Board change QDE CEO Interview & Publication of Business Video
CEO interview released on Vox Markets and business video published.
+3.0%
16 Dec 25 2025 A Remarkable Year in Review
Company raised £5m, achieved 10x enterprise value growth, and advanced flexible generation and AI datacentre power projects.
+0.0%
09 Dec 25 Electricity Generation and Revenues Surge
Pyebridge 8.1 MW asset generated 9.2 GWh in first 11 months 2025, up 71%, with revenues of £1.45m, up 136%.
+6.4%
02 Dec 25 Significant Progress with Funding at Project Level
QDE appoints funding adviser SIS to secure non-dilutive project-level financing for flexgen portfolio growth to 300+ MW.
+16.9%
25 Nov 25 10 MW CHP Project Significant Progress
Submitted 10 MW CHP proposal to major UK holiday park; appointed Levercor as EPC partner for holiday-park rollout strategy.
−13.4%
18 Nov 25 Record High Electricity Sales
Pyebridge 8.1 MW asset achieves record monthly electricity sales of 1.3 GWh; qualifies for 15-year Capacity Market contract from 2029-2044.
+14.7%
11 Nov 25 1GW AI Datacentre Power Strategy Update
Quantum signs partnership with Navon World to develop AI datacentre power campuses; approaches one of UK's largest residential property developers.
+10.1%
06 Nov 25 Hindlip breaks ground and update on 7 MW purchase
Hindlip 7.5 MW project breaks ground with construction on schedule for Q2 2026 COD; 7 MW acquisition nearing completion in Q4 2025.
−19.0%
21 Oct 25 25 MW Portfolio Makes Signif. Development Progress
25 MW flexible generation portfolio advances with planning pre-applications completed and grid connections confirmed.
−23.7%
14 Oct 25 Pyebridge FlexGen Power Asset Revenues Surge
Pyebridge 8.1 MW asset generated 2.5 GWh in Q3 2025, up 24% quarter-on-quarter; 9-month revenues reached £1.1m, up 300% year-on-year.
+2.2%
07 Oct 25 Hindlip Project Significant Construction Progress
Rolls-Royce engines arrived at Hindlip 7.5 MW power project; construction on track for Q2 2026 completion.
+15.6%

Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note