Pensana
PRE · Main Market · Basic Resources · mcap £145m · 41.0p
| Date | Type | Announcement | Day |
|---|---|---|---|
| 25 Sep 26 | Update on Longonjo Financing and Coola Farm Out
Longonjo mine construction 30% complete; financing discussions ongoing with potential delays to late 2028 completion. |
−24.0% | |
| 17 Aug 26 | Board change | Update on Strategic Investor Board Appointment
Board appointment of Sheikh Dr Badr bin Dalhim Al-Faheid Al-Hajri to Cascade still in progress, not yet filed. |
−9.5% |
| 10 Aug 26 | Trump announces US$3 billion support for U.S. critical minerals supply chains
Trump administration announces US$3 billion support for U.S. critical minerals; Pensana CEO invited to briefing on rare earths strategy. |
−4.5% | |
| 06 Aug 26 | Update on Cascade financing
Cascade financing of US$165 million progressing; US$15 million received, US$150 million outstanding, backed by State of Qatar. |
+17.7% | |
| 22 Jul 26 | Holding | Holding(s) in Company | |
| 18 Jun 26 | Board change | Strategic Investor Board Appointment
Sheikh Dr Badr Al-Hajri joins Cascade board to support its US$165m investment in Pensana. |
−11.2% |
| 08 Jun 26 | Update on Longonjo Mine Development, Downstream and Offtake
Longonjo mine development 22% complete, on target for 2027 commissioning with downstream strategy and offtake partnerships confirmed. |
−0.3% | |
| 28 Apr 26 | Holding | Holding(s) in Company | |
| 17 Apr 26 | US$165 million Strategic Investment to support U.S. Mine to Magnet strategy
Cascade Natural Resources to invest US$165 million to fund Longonjo rare earth mine development and US magnet supply chain. |
+6.8% | |
| 27 Mar 26 | Results | Unaudited Interim results for the six months ended 31 December 2025
H1 FY26 loss US$4.5m; Cascade invests US$165m; Longonjo construction progressing towards 2027 commissioning. |
−1.7% |
| 09 Mar 26 | Adjournment of General Meeting and Corporate Presentation
General Meeting scheduled for 9 March adjourned until further notice without resolutions being put. |
−0.2% | |
| 04 Mar 26 | Increased US$165 million Strategic Investment to support U.S. Mine to Magnet strategy - Proposed adjournment of General Meeting
Cascade Natural Resources to invest US$165 million in Pensana to support US Mine-to-Magnet strategy. |
−1.4% | |
| 03 Mar 26 | Construction on track for 2027 first production
Longonjo rare earth project main construction on track with commissioning scheduled for 2027. |
−7.1% | |
| 10 Feb 26 | US$ 160 million Strategic Equity Investment
General Meeting scheduled for 9 March 2026 to vote on US$160 million strategic equity investment. |
+7.5% | |
| 04 Feb 26 | Update on US$25 million Longonjo mine finance
Final tranche of US$25 million Longonjo mine financing received and deployed towards construction. |
−0.5% | |
| 21 Jan 26 | Routine | Issue of Equity | |
| 21 Jan 26 | Update on Longonjo infill and resource expansion drill programme
Commencing 7,000 metre infill drill programme at Longonjo ahead of mining start in early 2027. |
+9.5% | |
| 14 Jan 26 | Director dealing | Director/PDMR Shareholding | |
| 14 Jan 26 | Longonjo Main Construction well underway
Longonjo rare earths mine main construction underway on budget, first production targeted for 2027. |
+2.0% | |
| 23 Dec 25 | Holding | Holding(s) in Company | |
| 19 Dec 25 | Routine | Issue of Equity - Updated Admission Date and number of shares to be issued | |
| 18 Dec 25 | Routine | Issue of Equity | |
| 18 Dec 25 | Routine | Issue of Equity | |
| 18 Dec 25 | Major shareholder support for US Strategy
FSDEA to stage conversion of US$15m bridging loan to equity; M&G invests further £5m ahead of Nasdaq listing mid-2026. |
−1.3% | |
| 16 Dec 25 | Routine | Issue of Equity | |
| 15 Dec 25 | Routine | Issue of Equity/Total Voting Rights | |
| 09 Dec 25 | US$100 million Strategic Equity Investment
US$100m strategic equity investment and US$3m institutional placing to fund Longonjo mine development. |
−3.7% | |
| 03 Dec 25 | Board change | Annual General Meeting - Chairman's Presentation
Pensana is pleased to advise that the presentation slides from the Chairman's Presentation at the Company's Annual General Meeting, held earlier today, have been published on the Company's website: www.pensana.co.uk |
+5.5% |
| 03 Dec 25 | Routine | Result of AGM | |
| 27 Nov 25 | Longonjo study lifts HREE production fivefold
Pensana increases planned heavy rare earth production from Longonjo by more than five times through circuit upgrade. |
+8.0% | |
| 17 Nov 25 | Major drill programme to increase Longonjo resource to over one billion tonnes
Pensana announces US$11m drilling programme targeting expansion of Longonjo resource to over one billion tonnes. |
−2.3% | |
| 10 Nov 25 | Routine | Notice of Annual General Meeting and Form of Proxy | |
| 31 Oct 25 | New Corporate Presentation
Pensana uploads new corporate presentation on Longonjo project and rare earth value chain strategy. |
+14.1% | |
| 28 Oct 25 | U.S. EXIM debt funding to accelerate U.S. mine-to-magnet supply chain
EXIM provides Letter of Interest for up to US$160m debt funding of Longonjo rare earth mine to establish U.S. mine-to-magnet supply chain. |
+7.1% | |
| 22 Oct 25 | Partnership with Vacuumschmelze GmbH to establish mine-to-magnet supply chain in the US
Pensana signs MOU with Vacuumschmelze to supply rare earth materials to US magnet manufacturer from 2027 |
−2.3% | |
| 15 Oct 25 | Routine | Publication of Annual Report 2025 and Notice of Annual General Meeting | |
| 09 Oct 25 | Routine | Issue of Equity |
Company filings. Not investment advice.