Summary:

Project Update

During the quarter, Berkeley Energia (Berkeley or Company) received formal notifications from the High Court of Justice of Castilla y León (TSJ) which upheld the appeals submitted by a non-governmental organisation, Plataforma Stop Uranio, and the city council of Villavieja de Yeltes (the appellants) to revoke the first instance judgements related to the Authorization of Exceptional Use of the Land (AEUL) and the Urbanism Licence (UL), and annules both the AEUL and UL.

The Company strongly disagrees with the fundamentals of the TSJ's judgement and it will submit appeals against the TSJ judgements before the Supreme Court under Spanish law to defend its position and take all necessary actions to preserve its rights.

The Company has also previously submitted a contentious-administrative appeal before the Spanish National Court following notification from the Ministry for Ecological Transition and the Demographic Challenge (MITECO) in relation to the rejection of the administrative appeal filed by the Company against MITECO's rejection of the Authorisation for Construction for the uranium concentrate plant as a radioactive facility (NSC II) at the Salamanca project.

Whilst the Company's focus is on resolving the current permitting situation, and ultimately advancing the Salamanca project towards production, the Company will continue to strongly defend its position and take all necessary actions to preserve its rights.

Global Nuclear Power and Uranium Market:

Spot uranium prices continued to demonstrate extreme upside as the near-term price indicator increased by 27% during the quarter and ended December at US$91 per pound. In January 2024 the uranium price surpassed US$100 per pound and is currently ~US$100 per pound.

Price indicators reflecting the longer-term uranium market strengthened over the quarter as the 3-year forward price increased to US$96 per pound with the 5-year forward price increasing to US$101 per pound by the end of December. The Long-Term Price continued to rise incrementally reaching US$68 per pound at the end of December.

European Union

o The European Parliament adopted its official position on the proposed Net-Zero Industry Act (NZIA), which is designed to support Europe's manufacturing output in technologies needed for decarbonization. The Members of the European Parliament included nuclear fission and fusion amongst the list of 17 technologies addressed by the legislation.

o The NZIA sets a target for Europe to produce 40% of its annual deployment needs in net zero technologies by 2030 and to capture 25% of the global market value for these technologies.

COP28

o During the World Climate Action Summit of the 28th Conference of the Parties to the U.N. Framework Convention (COP28), more than 20 countries lead by the United States, France, Japan Republic of Korea, United Arab Emirates and the United Kingdom, launched the Declaration to Triple Nuclear Energy. The Declaration "recognizes the key role of nuclear energy in achieving global net-zero greenhouse gas emissions by 2050 and keeping the 1.5-degree goal within reach."

Sweden

o The Swedish government presented its climate policy action plan to meet net zero by 2045. The climate action plan contains some 70 "concrete proposals" to achieve emission reductions in all sectors and says "expanded nuclear power is the single most important measure" to reduce emissions through electrification, with the government's recently published roadmap for new nuclear "one crucial piece of the puzzle.

The government also tabled a proposed amendment to the country's nuclear energy regulations (Environmental Code) which would remove the current stipulation that any new nuclear reactor can only be authorized if it replace a permanently closed reactor and must be built on a site where one of the existing reactors is located. The recently-elected government is also pursuing legislation which would address the potential development of small modular reactors.

Finland

o Finnish utility, TVO, initiated an environmental impact assessment for the possible operating license extension and potential power uprating of reactors which currently supply 15% of Finland's annual electricity needs. The reactors can operate until the end of 2038 and TVO is considering applying for a further 10-year extension.

Balance Sheet

The Company is in a strong financial position with A$75 million in cash reserves and no debt.

In 2021, the Company received formal notification from MITECO that it had rejected the NSC II application at Salamanca. This decision followed the unfavourable NSC II report issued by the NSC in July 2021.

In this regard, the Company believes that MITECO have infringed regulations on administrative procedures in Spain but also under protection afforded to Berkeley under the Energy Charter Treaty (ECT), which would imply that the decision on the rejection of the Company's NSC II Application is not legal.

In April 2023, the Company's wholly owned Spanish subsidiary, Berkeley Minera España (BME) submitted a contentious-administrative appeal before the Spanish National Court in an attempt to overturn the MITECO decision denying NSC II.

Initiation of the contentious-administrative appeal is necessary to preserve BME's rights however, the Company reiterates that it is prepared to collaborate with the relevant authorities and remains hopeful that the permitting situation can be resolved amicably.

Salamanca Project Update

Following the annual Internal Audit (IA) of the Environmental and Sustainable Mining Management Systems completed in the September quarter, AENOR, an independent Spanish institution, completed the External Audit (EA) during November.

The EA successfully verified that the Company's management system complies with the requirements of ISO Standards 14001:2015 "Environmental Management" and UNE 22480/70:2019 "Sustainable Mining Management", and remains implemented in an adequate and effective manner.

The conclusions of the EA highlighted the significant progress made towards achievement of the Company's 2023 Sustainability Goals including involvement in the management system at all levels of the organisation and the integration of Sustainable Development Goals (SDGs) into the Company's strategy.

The certification process to obtain ISO 45001 certification for Health and Safety Management is ongoing, with the internal audit and the integration of the SDGs into the Company's strategy being successfully completed.

Solar Power System Study

As previously reported, Berkeley initiated a study evaluating the design, permitting, construction and operation of a solar power system at the Project. This study has been finalised, a formal application submitted to the relevant authorities in Salamanca, and the permitting process continued during the quarter.

The proposed facility will have an installed power of 20.1MW and will be able to supply up to 75% of the power requirements at the Project. There is flexibility with regard to storage capacity versus capital and operational costs to ensure the optimal outcome for the Project.

The engineering, design, and cost estimation workstreams were completed and the overall project was delivered during the prior quarter. The environmental studies are well advanced, and once the scope of the environmental document is confirmed by the Administration, the Environmental Assessment will be formally submitted.

Exploration

During the quarter, the Company continued with its initial exploration program focusing on battery and critical metals in Spain. The exploration initiative is targeting lithium, cobalt, tin, tungsten, rare earths, and other battery and critical metals, within the Company's existing tenements in western Spain that do not form part of Berkeley's main undertaking being the development of the Salamanca uranium project. Further analysis of the mineral and metal endowment across the entire mineral rich province and other prospective regions in Spain is also being undertaken, with a view to identifying additional targets and regional consolidation opportunities.

Investigation Permit Conchas

Based on the results of the soil sampling programs and information gleaned from a review of the available historical data, a small initial drilling program was implemented to test the tin-lithium anomaly. The drill program comprised five broad spaced reverse circulation (RC) holes for a total of 282m. Anomalous results for lithium (Li), tin (Sn), rubidium (Rb), cesium (Cs), niobium (Nb) and tantalum (Ta) obtained from multi-element analysis of drill samples were reported in the March 2023 quarter.

Mineralogical studies have been undertaken on 25 samples from the drilling at ALS Laboratories (Perth, Australia) and the University of Oviedo (Oviedo, Spain), to determine the mineral species present and understand their characteristics and properties.

The results of the mineralogical study carried out by ALS Laboratories on the samples of mineralised muscovitic leucogranite indicate they are composed mainly of plagioclase (average content of 55%) and quartz (average content of 25%), with potassium feldspar, muscovite mica, and Li-mica making up remainder of the rock. The samples have an average Li-mica content of 3%.

Based on the conclusions of the studies carried out at the University of Oviedo, IP Conchas demonstrates exploration potential for several critical and strategic raw materials included in the European Commission's Critical Raw Materials Act1, particularly Li, Nb and Ta. Results from the mineralogical study report conclude that the Li-bearing minerals in the mineralised leucogranite are mainly Li-rich muscovites.

The Department of Geology at the Universidad del País Vasco (Spain) has also undertaken an optical mineralogy and petrography study on thin sections from six samples collected from surface outcrops of the Conchas mineralisation. Four of the collected samples are representative of the main muscovitic leucogranite and two are the same leucogranite but completely greisenized. The study concludes that among the mineral phases identified within the leucogranite and greisen samples, the micas can be considered as aluminum-rich micas and they are the only minerals to contain Li. The micas also hosting the highest contents of Rb and Cs.

The Company is currently advancing plans for a second drilling campaign at IP Conchas focused on improving confidence in the geology, continuity, and grade distribution of the zone of multi-element mineralisation.

Figure 1: IP Conchas Location Plans and Geology / Drill Hole Location Plan

Figure 2: IP Conchas Cross Section A-A1

Oliva and La Majada Projects

The Company has designed exploration programs for both projects and communicated with the relevant authorities to progress the pending grant of the Investigation Permits for two of tenements.

Permitting

During the quarter, the Company received formal notifications from the TSJ which upheld the appeals submitted by a non-governmental organisation, Plataforma Stop Uranio, and the city council of Villavieja de Yeltes (the appellants) to revoke the first instance judgements related to the AEUL and the UL, and annules both the AEUL and UL.

The appellants subsequently filed administrative appeals against the AEUL and the UL at the first instance courts in Salamanca. The administrative appeals against the AEUL and UL were dismissed in September 2022 and January 2023 respectively. One of the appellants subsequently lodged appeals before the TSJ, with the TSJ delivering judgements to revoke the first instance judgements and declare the AEUL and the UL null.

The Company strongly disagrees with the fundamentals of the TSJ's judgement and it will submit cassation appeals against the TSJ judgements before the Supreme Court under Spanish law to defend its position and take all necessary actions to preserve its rights.

Given the current permitting situation at the Salamanca Project, and following the recommendation of the regional mining authorities, the Company has applied for a temporary suspension of activity work at the C.E Retortillo-Santidad ('Retortillo mining licence') whilst the NSC II related and abovementioned appeals processes are ongoing. All environmental, health and safety measures will continue to maintained by the Company. The application is pending resolution by the regional mining authorities.

Spanish Politics

Following a failed vote in Congress for the Partido Popular (PP) leader, Alberto Núñez Feijóo, to become Prime Minister in September 2023, the Spanish Socialist Workers' Party (PSOE) leader, Pedro Sánchez, won parliamentary support during the quarter to be re-elected as Spain's Prime Minister, after striking a controversial agreement with Catalan separatists.

In exchange for supporting Sanchez's PSOE, nationalists from the Spanish region of Catalonia secured a commitment from the PSOE to pass an amnesty law that would pardon those linked to a failed Catalan bid for independence six years ago. PSOE also struck controversial agreements with other nationalist parties, including from the Basque Country, to secure their support.

Additional Information on the Global Nuclear Power and Uranium Market

  • The International Atomic Energy Agency (IAEA) released its latest nuclear power forecast up to 2050. The international nuclear regulatory agency now foresees a high case installed nuclear generating capacity in 2050 of 890GWe (compared with today's 369GWe), an increase over the 2020 forecast of 24%.

Large-scale reactors remain the dominant form of nuclear power in all scenarios, including advanced reactor designs, but the development of and growing interest in small modular reactors increases the potential for nuclear power.

  • In response to calls from the nuclear industry, research community and nuclear safety regulators, the European Commission will establish an Industrial Alliance dedicated to small modular reactors in early 2024, the European Commissioner for Energy announced.
  • The Swedish government unveiled a roadmap which envisages the construction of new nuclear generating capacity equivalent to at least two large-scale reactors by 2035, with up to ten new large-scale reactors coming online by 2045.

The parliament subsequently approved a bill that will clear the way for new nuclear power in the country by removing the current limit on the number of nuclear reactors in operation, as well as allowing reactors to be built on new sites. The amendment entered into force on 1 January 2024.

Sweden and France also signed a declaration of intent to develop long-term cooperation in the field of nuclear energy.

  • Norsk Kjernkraft, submitted a proposal to Norway's Ministry of Oil and Energy for an assessment into the construction of a power plant based on multiple small modular reactors in the municipalities of Aure and Heim. The company said it marks the first formal step towards the possible construction of the country's first nuclear power plant. Once approved by the government agency, the environmental impact assessment phase could begin.
  • Slovenia's Ministry of the Environment, Climate and Energy presented a draft resolution on the long-term peaceful use of nuclear energy in the country, which envisages long-term use of nuclear energy, a second reactor at the Krško nuclear power plant and a secure electricity supply through a mix of nuclear and renewable energy sources, the Slovenian Press Agency reported.
  • The Estonian government's Nuclear Energy Working Group concluded that introducing nuclear energy to the country would help to meet climate goals and increase energy security, with small modular reactors deemed to be the most suitable for the country.
  • The Council of Ministers of Bulgaria have approved the construction of two additional reactors. The target date for commercial operation of the first reactor is set at 2033 while the second reactor would follow 2-3 years later. The planned capacity of the two reactors will total 2,300MWe.
  • The British government launched a roadmap for reaching its ambition for the UK to have 24GWe of nuclear generating capacity by 2050, representing about 25% of the country's projected electricity demand.
  • The EURATOM Supply Agency (ESA) distributed its Annual Report for 2022 which documents various aspects of the nuclear fuel cycle within the European Union.

According to the ESA's survey of the 103 reactors operating in 13 Member Countries as of the end of 2022, future uncovered uranium requirements through 2031 range from a minimum of 51.9 million pounds (assuming all current supply agreements are honoured) and a maximum of 87.5 million pounds (assuming Russian-sourced agreements are not completed as scheduled).

Total uranium inventories held by EU utilities at the end of 2022 approximated 92.8 million pounds, a decrease from the aggregate inventories held at the end of 2021 (95.7 million pounds).

During 2022, the purchases of Russian-origin uranium declined by 16% to 5.2 million pounds as compared to 2021 buying levels.

  • Kazatomprom released its September 2023 quarter Operations and Trading Update, which reported a slight decline in Kazakh uranium production for the first nine months of the year (2023 - 39.8 million pounds. compared to 2022 - 40.2 million pounds), but reconfirming the 2023 guidance at 53.3 - 55.9 million pounds. However, the world's largest producer of uranium cautioned that "issues associated with limited access to certain key materials, such as sulfuric acid, remain persistent, and might potentially have a negative impact on 2024 production."
  • Orano took the decision to expand uranium enrichment capacity at the Georges Besse 2 Uranium Enrichment Plant, located at Tricastin, France. The facility entered operation in 2011 reaching its current full production capacity of 7.5 million Separative Work Units (SWU) in 2016, based on centrifuge technology. The Orano Board approved the planned expansion of 2.5 million SWU at a cost of €1.7 billion.

References

1 Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL establishing a framework for ensuring a secure and sustainable supply of critical raw materials and amending Regulations (EU) 168/2013, (EU) 2018/858, 2018/1724 and (EU) 2019/1020

This announcement has been authorised for release by Mr Robert Behets, Director.

Appendix 1: Mineral Resource at Salamanca

Deposit NameResource CategoryTonnes (Mt)U 3 O 8 (ppm)U 3 O 8 (Mlbs)
RetortilloMeasured4.14984.5
Indicated11.33959.8
Inferred0.23680.2
Total15.642214.5
Zona 7Measured Indicated5.2 10.5674 7617.8 17.6
Inferred6.03644.8
Total21.763130.2
AlamedaIndicated20.045520.1
Inferred0.76571.0
Total20.746221.1
Las CarbasInferred0.64430.6
CristinaInferred0.84600.8
CaridadInferred0.43820.4
VillaresInferred0.76721.1
Villares NorthInferred0.33880.2
Total Retortillo SatellitesTotal2.84923.0
VillarInferred5.04464.9
Alameda Nth Zone 2Inferred1.24721.3
Alameda Nth Zone 19Inferred1.14921.2
Alameda Nth Zone 21Inferred1.85312.1
Total Alameda SatellitesTotal9.14729.5
GambutaInferred12.739411.1
Salamanca Project TotalMeasured9.359712.3
Indicated41.851647.5
Inferred31.539529.6
Total (*)82.651489.3

Appendix 2: Summary of Mining Tenements

As at 31 December 2023, the Company had an interest in the following tenements:

LocationTenement NamePercentage InterestStatus
Spain
SalamancaD.S.R Salamanca 28 (Alameda)100%Granted
D.S.R Salamanca 29 (Villar)100%Granted
I.P. Abedules100%Granted
I.P. Abetos100%Granted
I.P. Alcornoques100%Granted
I.P. Alisos100%Granted
I.P. Bardal100%Granted
I.P. Barquilla100%Granted
I.P. Berzosa100%Granted
I.P. Campillo100%Granted
I.P. Casta ñ os 2100%Granted
I.P. Ciervo100%Granted
I.P. Conchas100%Granted
I.P. Dehesa100%Granted
I.P. El Á guila100%Granted
I.P. El Vaqueril100%Granted
I.P. Espinera100%Granted
I.P. Horcajada100%Granted
I.P. Lis100%Granted
I.P. Mailleras100%Granted
I.P. Mimbre100%Granted
I.P. Pedreras100%Granted
C á ceresI.P. Almendro E.C. Gambuta100% 100%Granted Pending^
I.P. Ibor100%Granted
I.P. Olmos100%Granted
BadajozI.P. Los Bélicos100%Granted**
I.P.A. Ampliación Los Bélicos100%Pending**
Ciudad RealI.P.A. La Majada100%Pending**

^During quarter, the Company applied for an Exploitation Concession from the existing IP Almendro.

**In the March 2023 quarter, Exploracion de Recuros Minerales S.L.U (ERM), a wholly owned subsidiary of the Company, entered into a Tenement Sale and Purchase Agreement and Royalty Deed with COPROMI, to acquire IP Los Bélicos, IPA Ampliación Los Bélicos, and IPA La Majada.

Appendix 3: Related Party Payments

During the quarter ended 31 December 2023, the Company made payments of $186,000 to related parties and their associates. These payments relate to existing remuneration arrangements (director and consulting fees plus statutory superannuation).

Appendix 4: Exploration and Mining Expenditure

During the quarter ended 31 December 2023, the Company made the following payments in relation to exploration and development activities:

ActivityA$000
Radiological protection, monitoring and other assays20
Permitting related expenditure (including legal dispute expenses)476
Consultants and other expenditure54
Payment/(return) of VAT and other social taxes in Spain144
Total as reported in the Appendix 5B694

Appendix 5B

Mining exploration entity or oil and gas exploration entity

quarterly cash flow report

Name of entity

Berkeley Energia Limited

ABNQuarter ended ("current quarter")
40 052 468 56931 December 2023
Consolidated statement of cash flowsCurrent quarter $A'000Year to date (6 months) $A'000
1.Cash flows from operating activities--
1.1Receipts from customers
1.2Payments for(694)(1,601)
(a) exploration & evaluation
(b) development--
(c) production--
(d) staff costs(346)(599)
(e) administration and corporate costs(305)(692)
1.3Dividends received (see note 3)--
1.4Interest received8751,668
1.5Interest and other costs of finance paid--
1.6Income taxes paid--
1.7Government grants and tax incentives--
1.8Other (provide details if material) (a) Business Development(92)(117)
1.9Net cash from / (used in) operating activities(562)(1,341)
2.Cash flows from investing activities--
2.1Payments to acquire or for:
(a) entities
(b) tenements--
(c) property, plant and equipment--
(d) exploration & evaluation--
(e) investments--
(f) other non-current assets--
2.2Proceeds from the disposal of:--
(a) entities
(b) tenements--
(c) property, plant and equipment--
(d) investments--
(e) other non-current assets--
2.3Cash flows from loans to other entities--
2.4Dividends received (see note 3)--
2.5Other (provide details if material)--
2.6Net cash from / (used in) investing activities--
3.Cash flows from financing activities--
3.1Proceeds from issues of equity securities (excluding convertible debt securities)
3.2Proceeds from issue of convertible debt securities--
3.3Proceeds from exercise of options--
3.4Transaction costs related to issues of equity securities or convertible debt securities--
3.5Proceeds from borrowings--
3.6Repayment of borrowings--
3.7Transaction costs related to loans and borrowings--
3.8Dividends paid--
3.9Other (provide details if material)--
3.10Net cash from / (used in) financing activities--
4.Net increase / (decrease) in cash and cash equivalents for the period
4.1Cash and cash equivalents at beginning of period80,03978,776
4.2Net cash from / (used in) operating activities (item 1.9 above)(562)(1,341)
4.3Net cash from / (used in) investing activities (item 2.6 above)--
4.4Net cash from / (used in) financing activities (item 3.10 above)--
4.5Effect of movement in exchange rates on cash held(4,343)(2,301)
4.6Cash and cash equivalents at end of period75,13475,134
5.Reconciliation of cash and cash equivalents at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accountsCurrent quarter $A'000Previous quarter $A'000
5.1Bank balances75,08479,989
5.2Call deposits5050
5.3Bank overdrafts--
5.4Other (provide details)--
5.5Cash and cash equivalents at end of quarter (should equal item 4.6 above)75,13480,039
6.Payments to related parties of the entity and their associatesCurrent quarter $A'000
6.1Aggregate amount of payments to related parties and their associates included in item 1(186)
6.2Aggregate amount of payments to related parties and their associates included in item 2-
7.Financing facilities Note: the term "facility' includes all forms of financing arrangements available to the entity. Add notes as necessary for an understanding of the sources of finance available to the entity.Total facility amount at quarter end $A'000Amount drawn at quarter end $A'000
7.1Loan facilities--
7.2Credit standby arrangements--
7.3Other (please specify)--
7.4Total financing facilities--
7.5Unused financing facilities available at quarter end-
Not applicable
8.Estimated cash available for future operating activities$A'000
8.1Net cash from / (used in) operating activities (item 1.9)(562)
8.2(Payments for exploration & evaluation classified as investing activities) (item 2.1(d))-
8.3Total relevant outgoings (item 8.1 + item 8.2)(562)
8.4Cash and cash equivalents at quarter end (item 4.6)75,134
8.5Unused finance facilities available at quarter end (item 7.5)-
8.6Total available funding (item 8.4 + item 8.5)75,134
8.7Estimated quarters of funding available (item 8.6 divided by item 8.3)>10
8.8If item 8.7 is less than 2 quarters, please provide answers to the following questions:

Answer: Not applicable

Answer: Not applicable

Answer: Not applicable

Compliance statement

2 This statement gives a true and fair view of the matters disclosed.

Date: 30 January 2024

Authorised by: Company Secretary

(Name of body or officer authorising release - see note 4)

Notes

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note