Project milestones

Lithium Ridge exploration with SQM

Drilling complete; fifth batch of assays reported

Lithium Ridge is explored under an SQM earn-in (SQM may earn 30%). Drilling finished in May 2026 at about 16,500m across 143 holes. On 6 Oct 2026 the fifth batch of assays reported 23 mineralised holes, with grades up to 2.04% Li2O, tin and tantalum by-products, and a newly identified pegmatite outside the main trend.

Next milestone
Assay analysis to be completed Q3 FY2027; no exact date stated 29 Jun 2026 ↗
Drilling
Completed May 2026: about 16 500m across 143 holes 29 Jun 2026 ↗
Assays
22 holes (15% of programme) reported; 85% still to come 27 May 2026 ↗
Partner
SQM earn-in; SQM may earn 30% interest in the Project 6 Oct 2026 ↗
Assays reported
34 holes released to date (22 holes at 27 May 2026); remainder pending 29 Jun 2026 ↗
Fifth batch
23 holes intersected mineralisation; 6 holes did not meet reporting thresholds (reported 6 Oct 2026) 6 Oct 2026 ↗

Next: Assay analysis to be completed

  1. 6 Oct 2026 Drilling complete; fifth batch of assays reported
  2. 28 Sep 2026 Funded; long-lead crushing equipment ordered
  3. 17 Aug 2026 Loans executed; project in execution
  4. 29 Jun 2026 Loans still conditional; construction said funded
Open the full view – chart and every step →
Disposal of a part (break-up)

Brandberg West earn-in partnership

Workplan under way; ore sorting results positive

ACAM LP, through BWCAM, is funding a USD51m phased investment in Brandberg West; the first USD10m was received earlier in 2026. The 29 June 2026 update reports initial XRT ore sorting test work (released 13 April 2026) showing over 90% mass reduction with tin and tungsten recoveries above 80% in multiple instances. An extensive drilling and metallurgical programme has started. The company calls this a potential low-capex route to production.

Size
USD51 million phased investment by ACAM LP via BWCAM 29 Jun 2026 ↗
Received
First USD10 million (£7.3 million) received in the Quarter
Initial work
Tailings recovery, feasibility study preparation, pit optimisation
Conditions
Conditions precedent completed
Next milestone
Remaining phased funding; no date stated 29 Jun 2026 ↗
Ore sorting
Over 90% mass reduction; recoveries above 80% in multiple instances; test work on historical grab samples 29 Jun 2026 ↗

Next: Drilling and metallurgical programme; remaining phased funding

  1. 29 Jun 2026 Workplan under way; ore sorting results positive
  2. 26 Mar 2026 First USD10m received; workplan under way
  3. 4 Feb 2026 Initial conditions met; funds imminent; competition approval pending
  4. 21 Jan 2026 Agreed; initial investment conditions pending
Open the full view – chart and every step →

Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note