Activities Update For The South Crofty Tin Project

In brief · summary, not quotable

South Crofty tin project progressing with surface redevelopment started, first production delayed to H1 2028.

  • Mine dewatering capacity 25,000m3 per day
  • Water level below surface approximately 340 metres
  • Shaft refurbishment depth approximately 330 metres below surface
  • Expected mid-shaft pump station depth approximately 360 metres below surface
  • Expected lower pump station depth approximately 730 metres below surface
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your TIN notes

Cornish Metals Inc. (AIM/TSX-V: CUSN) ("Cornish Metals" or the "Company"), a mineral exploration and development company focused on advancing its wholly owned and permitted South Crofty tin project in Cornwall, United Kingdom, is pleased to provide an update on the progress of activities at South Crofty.

Highlights

  • The first major phase of surface redevelopment at South Crofty started in early July with refurbishment of the Mine Dry building and demolition of the old Bartles Foundry buildings. The latter will provide space for construction of new stores and workshop facilities, in part funded by the UK Government through the UK Shared Prosperity Fund (see press release dated 11 June 2025);
  • The placing of orders with UK-based Qualter Hall & Company Limited ("Qualter Hall") for the production and service winders to be used at New Cook's Kitchen ("NCK") shaft was an important milestone representing the start of one of South Crofty's critical path projects (see press release dated 3 June 2025). Design and fabrication work for the winders are currently underway in-line with the schedule contracted with Qualter Hall;
  • Excavation and earthworks for the processing plant are expected to commence in August 2025;
  • Detailed engineering has commenced on critical path activities, in-line with the execution schedule. Front-End Engineering Design ("FEED"), along with further detailed engineering for the process plant and non-critical surface infrastructure, is expected to begin in the coming weeks;
  • The recent addition of two Epiroc Boomer T1D drill rigs to South Crofty's fleet will enable the start of underground development of the No. 1 level of the mine;
  • A jumbo drill operator training programme will soon begin at the No. 1 level;
  • As the water drops further down NCK shaft, providing access to lower levels of the mine, additional work can commence alongside continued mine dewatering and shaft refurbishment;
  • The Company has partnered with Tomahee Consulting Services, an experienced mining consulting firm, to support the management and operational teams in developing a fully integrated mining technology platform prioritising health & safety, operational excellence, social responsibility and sound financial management;
  • Mine dewatering progress in recent months has been slower than planned reflecting reduced pump availability during staged maintenance of the submersible pumps, particularly with delays in the servicing one of the pump motors. This maintenance work is now complete and dewatering has resumed near full capacity of 25,000m3 per day in mid-July with the water level currently at approximately 340 metres below surface;
  • Refurbishment of NCK shaft is progressing well, but the pace of advance down the shaft has been held back by the rate of dewatering in recent months. Refurbishment depth is currently down to approximately 330 metres below surface with increased advance rates now back in-line with plan;
  • Shaft refurbishment and mine dewatering are anticipated to reach the mid-shaft pump station at approximately 360 metres below surface in August 2025. Refurbishment of the pump station, including installation of permanent pumps, will commence at that point. Shaft refurbishment and dewatering will continue below the level of the pump station, in parallel with this work;
  • Mine dewatering and NCK shaft refurbishment to the lower pump station level (approximately 730 metres below surface) are now expected in mid-2026, from Q4-2025 previously;
  • First tin production from South Crofty is now expected in the first half of 2028, from 2027 previously;
  • The Company is progressing a review of South Crofty, supported by Technical Management Group and Worley, testing key assumptions, optimising project parameters and further refining estimates. The review and an updated project Technical Report are expected to be completed in September 2025.

Don Turvey, CEO and Director of Cornish Metals, stated: "Activities at South Crofty have ramped up meaningfully following the financing in Q1 2025 with works underway across the site on-surface and underground. With the work completed this year, newly appointed technical advisers and the strengthened senior management, operations and projects leadership, we are now better positioned to build and deliver a world class project at South Crofty. We are fully engaged and focused on advancing and derisking the project towards a restart of tin production."

ON BEHALF OF THE BOARD OF DIRECTORS

"Don Turvey"

Don Turvey

CEO and Director

Engage with us directly at our investor hub. Sign up at: https://investors.cornishmetals.com/link/rAkgjy

Caution regarding forward looking statements

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note