Tharisa

THS · Main Market · Basic Resources · mcap £364m · 111.0p 1 open situation →

Beta Briefing, track record and signals & risks are not ready for Tharisa yet.

We follow 960 UK small caps and every one of their announcements – often hundreds per company. 101 companies are already wired into a briefing: browse them.

Timeline · every situation
dots = announcements

Open · 1

Project milestones◷ in 37 days

Karo Platinum Project build-out

Construction; awaiting bond drawdown

Karo build-out continued after the 25-year Special Mining Lease (24 Aug 2026), Valterra offtake (27 Aug 2026) and US$300m bond (escrow confirmed 25 Sep 2026). The 13 Oct 2026 report shows US$240m of US$516m capex spent, pre-stripping at 1.91m BCM and construction moving to steel erection. Drawdowns are expected from Nov 2026 and first ore to the mill is still targeted for Q4 CY2027.

Output ambition
CEO says Karo will more than double PGM output and add a second Tier 1 asset 11 Sep 2026 ↗
Key agreements
SMLA and Valterra offtake agreement concluded 11 Sep 2026 ↗
Conditions
Remaining release conditions must be met before project drawdown 25 Sep 2026 ↗
Capex to date
US$240m of US$516m: US$204m Tharisa equity, US$36m KMH bond 13 Oct 2026 ↗
Next milestone
Ore mining from October 2026; mechanical installation Q1 2027 13 Oct 2026 ↗
Commissioning
July to October 2027; first ore to mill Q4 CY2027 13 Oct 2026 ↗

Next: Drawdowns from Nov 2026; ore mining Oct 2026; first ore to mill Q4 CY2027 · 30 Nov 2026

  1. 13 Oct 2026 US$288.2m in escrow; conditions pending
  2. 25 Sep 2026 Proceeds in escrow; release conditions pending
  3. 11 Sep 2026 Bond priced; settlement pending
  4. 27 Aug 2026 Offtake signed; refinancing still not mentioned
Open the full view – chart and every step →

Company filings. Not investment advice.