Tharisa
THS · Main Market · Basic Resources · mcap £364m · 111.0p 1 open situation →
Timeline · every situation
dots = announcementsOpen · 1
Project milestones◷ in 37 days
Karo Platinum Project build-out
Construction; awaiting bond drawdown
Karo build-out continued after the 25-year Special Mining Lease (24 Aug 2026), Valterra offtake (27 Aug 2026) and US$300m bond (escrow confirmed 25 Sep 2026). The 13 Oct 2026 report shows US$240m of US$516m capex spent, pre-stripping at 1.91m BCM and construction moving to steel erection. Drawdowns are expected from Nov 2026 and first ore to the mill is still targeted for Q4 CY2027.
- Output ambition
- CEO says Karo will more than double PGM output and add a second Tier 1 asset 11 Sep 2026 ↗
- Key agreements
- SMLA and Valterra offtake agreement concluded 11 Sep 2026 ↗
- Conditions
- Remaining release conditions must be met before project drawdown 25 Sep 2026 ↗
- Capex to date
- US$240m of US$516m: US$204m Tharisa equity, US$36m KMH bond 13 Oct 2026 ↗
- Next milestone
- Ore mining from October 2026; mechanical installation Q1 2027 13 Oct 2026 ↗
- Commissioning
- July to October 2027; first ore to mill Q4 CY2027 13 Oct 2026 ↗
Next: Drawdowns from Nov 2026; ore mining Oct 2026; first ore to mill Q4 CY2027 · 30 Nov 2026
- 13 Oct 2026 US$288.2m in escrow; conditions pending
- 25 Sep 2026 Proceeds in escrow; release conditions pending
- 11 Sep 2026 Bond priced; settlement pending
- 27 Aug 2026 Offtake signed; refinancing still not mentioned
Company filings. Not investment advice.