Savannah Resources
SAV · AIM · Basic Resources · mcap £156m · 5.0p 1 open situation →
- EV
- £144m
- EV / EBIT
- –
- Net cash
- £12.2m
- FCF yield
- -5.6%
- Revenue
- £0k
- Share price 1y
- +22%
- Insiders 12m
- no deals
- Next report
- around 15 Apr
Timeline · every situation
dots = announcementsOpen · 1
Project milestones
Boticas bypass road permitting
Positive conditional DIA received; moving to RECAPE
Savannah received a positive conditional DIA from APA on 19 Oct 2026 for the c.16.5km Boticas bypass road, a key condition of the Barroso Lithium Project's own DIA. The July 2026 Phase 1 DFS put construction cost at US$61m. The process now moves to RECAPE; the Project can be commissioned before the road is completed.
- Decision
- Positive conditional DIA from APA, announced 2026-10-19 19 Oct 2026 ↗
- Route
- Northern option selected by APA and nine other Evaluation Committee bodies 19 Oct 2026 ↗
- Cost estimate
- US$61m per July 2026 Phase 1 DFS 19 Oct 2026 ↗
- Conditions
- Northern design; 50m from groundwater abstraction points; Declaration of Essential Public Utility if cork or holm oaks cut 19 Oct 2026 ↗
- Next milestone
- RECAPE stage: monitoring, studies and final designs; no date stated 19 Oct 2026 ↗
- Dependency
- Project can be commissioned and operated before the road is completed 19 Oct 2026 ↗
Next: RECAPE stage studies and final designs for northern route
- 19 Oct 2026 Positive conditional DIA received; moving to RECAPE