Project milestones
New-build surgical hub
Under construction; opening early 2027/28
One Health's first surgical hub, in Scunthorpe, got planning approval in February 2026 with an estimated cost of £8m-£9m. The 6 July 2026 results say construction began in March 2026 and the hub should open early in the 2027/28 financial year. Year-end cash was £11.1m after £1.6m spent on hub land and development in the year. Second and third sites are being explored.
- Cost estimate
- £8m-£9m, as previously stated; not restated in the results 6 Jul 2026 ↗
- Build period
- One-year construction period
- Contract backing
- Sheffield Teaching Hospital, Lincolnshire ICB and South Yorkshire ICB contracts, c.80% of activity, on longer terms
- Location
- Scunthorpe, Lincolnshire
- Cash
- £11.1m at 31 March 2026 (FY 25: £11.4m) 6 Jul 2026 ↗
- Next milestone
- Opening early in 2027/28 financial year; no exact date 6 Jul 2026 ↗
Next: Hub completion and opening; second and third sites being explored
- 6 Jul 2026 Under construction; opening early 2027/28
- 27 Apr 2026 Under construction, on track and on budget
- 7 Apr 2026 Under construction
- 1 Apr 2026 Construction imminent; CFO hired for build phase