Castillo Copper Limited (LSE and ASX: CCZ), a base metal explorer primarily focused on copper across Australia and Zambia, is pleased to present shareholders its latest quarterly report for the period 1 October 2023 to 31 December 2023.

HIGHLIGHTS:

STRATEGIC ASSET PORTFOLIO REVIEW

  • A wholesale asset portfolio review was completed to support the definition of next steps and optimal pathways to create shareholder value.
  • The review identified which assets remain core and highly prospective to prioritise exploration capital and leverage future opportunities with strategic development partners.

NWQ COPPER PROJECT, QUEENSLAND

  • The Board collectively endorsed the geology team's motion to earmark the NWQ Copper Project as a core asset.
  • Growing geological understanding of the 20+ prospects is now a Board focus, in readiness of engaging potential strategic partners.
  • Field trips commenced to map and fully assess future exploration targets across the asset.

CORPORATE

  • Former Managing Director Dr Dennis Jensen tendered his resignation during the Quarter.
  • Mr Jack Sedgwick (BEng BCom MBA - Distinction) GAICD transitioned from interim Executive Director to Non-Executive Director.
  • Cash on hand at the end of quarter totalled $1,747,000.
  • Rehabilitation Security Bonds which will convert to cash within 12 months totalled $311,000 at quarter end.

STRATEGIC ASSET PORTFOLIO REVIEW

Identification of Core and Non-Core Assets

During the quarter, a strategic asset review was completed to assess the location, timing and sequence of planned exploration activities across Castillo's existing portfolio.

Assets deemed to be core will be developed, potentially with the support of a strategic partner, while assets deemed non-core will be divested.

NWQ COPPER PROJECT

Core Asset Identification

During the quarter as part of the strategic asset portfolio review, the Company's NWQ Copper Project - situated in Mount Isa's copper-belt - was identified as a core asset.

This classification acknowledges the NWQ Copper Project (see Figure 1) as an asset that aligns with Castillo's future development plans.

Next Steps

The Board will be embarking on a campaign to deepen its understanding of the 20+ prospects across the tenure (excluding the Big One Deposit) ahead of engaging with potential strategic partners.

As part of the review process, members of the geology team visited the Boomerang and Josephine Prospects to assess their exploration potential. Both have been interpreted as prospective for structurally controlled copper mineralisation.

Historical Highlights

The historical highlights of these prospects are as follows:

Boomerang Prospect(1-4)

Mineralisation is hosted in the Surprise Creek Formation and is through to be associated with secondary faulting related to the Mt Gordon Fault, a regional NE trending structure.

In 1975, Dampier Mining conducted an exploration campaign that included geological mapping, rock sampling and drilling of nine RAB holes, to delineate a sandstone hosted copper oxide mineralisation over an 800m strike length. Secondary copper staining was observed along the strike length.

Josephine Prospect(1-4)

Occurs within a fault-bounded block of middle-lower Surprise Creek Formation. The host rock consists of buff, brown and grey thin bedded fine feldspathic and labile sandstone, ferruginous sandstone and micaceous siltstone.

Figure 1: NWQ Project Prospect Map

Field Trip and Rock Chip Sampling

The field trip was undertaken to complete a small program of rock chip sampling (refer ASX Announcement dated 24 October 2023) taken across various geological formations.

This preliminary work was undertaken to determine the prospectivity for copper mineralisation and facilitate the next phase of a more systematic exploration campaign if suitable targets are determined.

CORPORATE

Board changes: On 10 October 2023 Managing Director Dr Dennis Jensen resigned from the Castillo Copper Board.

Rehabilitation Security Bonds

Rehabilitation Security and Bonds which will convert to cash within 12 months totalled $311,000 at quarter end.

During the quarter $225,000 was paid to related parties of the Company relating to executive and non-executive director fees and exploration consulting fees paid to an entity controlled by a related party.

A summary of the exploration expenditure incurred during the quarter is set out below:

Table 1: Summary of Exploration Expenditure

AssetConsulting feesRates and mines departments feesOther
Cangai$37,000--
Broken Hill$58,000--
Mt Isa$56,000--
Zambia$17,000$6,000-
Total$168,000$6,000-

Castillo Copper is listed on the LSE and ASX under the ticker "CCZ".

References

  • CCZ London Listing Prospectus - 28 July 2020
  • CCZ ASX Announcement - 17 October 2023
  • CCZ ASZ Announcement - 23 January 2023
  • Nowland, M. L. (2020-22). EPM 26462 Big Oxide North Annual Report for period 29th August 2021 to 28th August 2022. Prepared by ROM Resources for Castillo Copper Limited.

APPENDIX A: Key PROJECTS

Figure 2: West and East Zone - BHA Project, Broken Hill Region (Source: CCZ Geology Team)

Figure 3: Zambia Copper-Belt Projects (Source: CCZ Geology Team)

Figure 4: NWQ Copper Project, Mt Isa Region (Source: CCZ Geology Team)

APPENDIX B: Interest in mining tenements held

Table 2: Jackaderry (Cangai), New England Orogen in NSW

Tenement IDOwnership at start of QuarterOwnership at end of QuarterChange during the Quarter
EL8635100%100%-
EL8625100%100%-
EL8601100%100%-

Table 3: Broken Hill, located within a 20km radius of Broken Hill in NSW

Tenement IDOwnership at start of QuarterOwnership at end of QuarterChange during the Quarter
EL8599100%100%-
EL8572100%100%-
EL 8434100%100%-
EL 8435100%100%-

Table 4: Mt Oxide, Mt Isa region in North West Queensland

Tenement IDOwnership at start of QuarterOwnership at end of QuarterChange during the Quarter
EPM 26513100%100%-
EPM 26525100%100%-
EPM 26574100%100%-
EPM 26462100%100%-
EPM 27440100%100%-
Table 5: Zambia
Tenement IDOwnership at start of QuarterOwnership at end of QuarterChange during the Quarter
24659-HQ-LEL (Mkushi)100%100%-
25195-HQ-LEL (Luanshya)55%55%-
25273-HQ-LEL (Luanshya)55%55%-
25261-HQ-LEL (Mwansa)100%100%-

Appendix 5B

Mining exploration entity or oil and gas exploration entity

quarterly cash flow report

Name of entity

Castillo Copper Ltd

ABNQuarter ended ("current quarter")
52 137 606 47631 December 2023
Consolidated statement of cash flowsCurrent quarter $A'000Year to date (6 months) $A'000
1.Cash flows from operating activities
1.1Receipts from customers
1.2Payments for
(a) exploration & evaluation
(b) development
(c) production
(d) staff costs
(e) administration and corporate costs(381)(663)
1.3Dividends received (see note 3)
1.4Interest received1523
1.5Interest and other costs of finance paid
1.6Income taxes paid
1.7Government grants and tax incentives
1.8Other (provide details if material)
1.9Net cash from / (used in) operating activities(366)(640)
2.Cash flows from investing activities
2.1Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation(174)(501)
(e) investments
(f) other non-current assets
2.2Proceeds from the disposal of:
  • entities
  • tenements
  • property, plant and equipment
  • investments
  • other non-current assets
2.3Cash flows from loans to other entities
2.4Dividends received (see note 3)
2.5Other (provide details if material)
2.6Net cash from / (used in) investing activities(174)(501)
3.Cash flows from financing activities
3.1Proceeds from issues of equity securities (excluding convertible debt securities)
3.2Proceeds from issue of convertible debt securities
3.3Proceeds from exercise of options
3.4Transaction costs related to issues of equity securities or convertible debt securities
3.5Proceeds from borrowings
3.6Repayment of borrowings
3.7Transaction costs related to loans and borrowings
3.8Dividends paid
3.9Other (provide details if material)
3.10Net cash from / (used in) financing activities--
4.Net increase / (decrease) in cash and cash equivalents for the period
4.1Cash and cash equivalents at beginning of period2,2942,897
4.2Net cash from / (used in) operating activities (item 1.9 above)(366)(640)
4.3Net cash from / (used in) investing activities (item 2.6 above)(174)(501)
4.4Net cash from / (used in) financing activities (item 3.10 above)--
4.5Effect of movement in exchange rates on cash held(7)(9)
4.6Cash and cash equivalents at end of period1,7471,747
5.Reconciliation of cash and cash equivalents at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accountsCurrent quarter $A'000Previous quarter $A'000
5.1Bank balances1,7471,354
5.2Call deposits-940
5.3Bank overdrafts
5.4Other (provide details)
5.5Cash and cash equivalents at end of quarter (should equal item 4.6 above)1,7472,294
6.Payments to related parties of the entity and their associatesCurrent quarter $A'000
6.1Aggregate amount of payments to related parties and their associates included in item 1100 1
6.2Aggregate amount of payments to related parties and their associates included in item 2125 2

1 Comprises director's fees for the quarter. 2 Comprises consulting fees paid to the Managing Director and exploration expenditure paid to Field Crew Pty Ltd, a related entity of director David Drakeley.

7.Financing facilities Note: the term "facility' includes all forms of financing arrangements available to the entity. Add notes as necessary for an understanding of the sources of finance available to the entity.Total facility amount at quarter end $A'000Amount drawn at quarter end $A'000
7.1Loan facilities
7.2Credit standby arrangements
7.3Other (please specify)
7.4Total financing facilities
7.5Unused financing facilities available at quarter end
8.Estimated cash available for future operating activities$A'000
8.1Net cash from / (used in) operating activities (item 1.9)(366)
8.2(Payments for exploration & evaluation classified as investing activities) (item 2.1(d))(174)
8.3Total relevant outgoings (item 8.1 + item 8.2)(540)
8.4Cash and cash equivalents at quarter end (item 4.6)1,747
8.5Unused finance facilities available at quarter end (item 7.5)
8.6Total available funding (item 8.4 + item 8.5)1,747
8.7Estimated quarters of funding available (item 8.6 divided by item 8.3)3.2
8.8If item 8.7 is less than 2 quarters, please provide answers to the following questions:

Answer: N/A

Answer: N/A

Answer: N/A

Compliance statement

2 This statement gives a true and fair view of the matters disclosed.

Date: 30 January 2024

Authorised by: The Board of Directors

(Name of body or officer authorising release - see note 4)

Notes

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note