KEFI Gold and Copper
KEFI · AIM · Basic Resources · mcap £95m · 0.7p 2 open situations →
Timeline · every situation
dots = announcementsOpen · 2
Project milestones
Tulu Kapi project financing and construction
Suspension lifted; phased restart under way
Tulu Kapi's funding package was assembled from Oct 2025 (US$240m loan, c.£35.6m placing in March 2026, BCM contract 18 Jun 2026). A fatal security incident on 4 Sep 2026 led to suspension on 7 Sep and deferred drawdown. On 12 Oct 2026 KEFI lifted the suspension and restarted development in phases; lenders remain supportive but drawdown sequencing is still being updated.
- Cash
- Cash £18.25m at 30 June 2026 (31 Dec 2025: £8.8m) 29 Sep 2026 ↗
- Production target
- Not restated in this announcement; the earlier plan was 2028, so any delay is not yet quantified 12 Oct 2026 ↗
- Capex spend
- Project exploration and evaluation costs of £14.5m in H1 2026 29 Sep 2026 ↗
- Suspension
- Imposed 7 September 2026 after the 4 September Genji Incident; lifted 12 October 2026 after reviews and consultations 12 Oct 2026 ↗
- Restart order
- Electricity connections and new access roads first, then replacement housing and lands for resettlement 12 Oct 2026 ↗
- Then on site
- Security infrastructure, bulk earthworks for the processing plant, permanent workforce accommodation 12 Oct 2026 ↗
Next: Further announcements as restart details are finalised; drawdown sequencing update
- 12 Oct 2026 Suspension lifted; phased restart under way
- 29 Sep 2026 Suspended; stakeholders support careful resumption
- 22 Sep 2026 Suspended; development plan and schedule under review
- 11 Sep 2026 Suspended; stakeholder support reaffirmed; no resumption date
Legal & regulatory
Ethiopian exploration licence legal action
Legal action to be pursued over several years
- 20 Oct 2025 Legal action to be pursued over several years