Cadence Minerals
KDNC · AIM · Basic Resources · mcap £22m · 4.6p 2 open situations →
Open · 2
Azteca Plant restart
Azteca restart is funded by a US$4.6m prepayment facility from Dec 2025, with the Installation Licence granted in May 2026. Mechanical completion came on 4 Sep 2026, and DEV began hot commissioning at 25%-50% of capacity under SEMA/AP consent, announced 28 Sep 2026. The half-year results of 29 Sep 2026 confirm that concentrate cannot be sold until the Operating Licence is granted. DEV is preparing the supporting maintenance and environmental monitoring documentation for SEMA/AP. Bridge repairs have started.
- Funding gap
- Bridge, road works and extra Tailings Storage Facility are outside the refurbishment programme; no change in position 10 Aug 2026 ↗
- Operating Licence
- Pending; required before any concentrate is sold or dispatched 29 Sep 2026 ↗
- Stage
- Cold and wet commissioning done; hot commissioning at 25%-50% of capacity 29 Sep 2026 ↗
- Consent limit
- SEMA/AP technical consent allows tests for a maximum of 45 days from start of feeding 28 Sep 2026 ↗
- Funding
- Restart capital advanced; operating working capital subject to Operating Licence 29 Sep 2026 ↗
- Bridge
- Repairs commenced; completion targeted before first shipment 29 Sep 2026 ↗
Next: Complete hot commissioning, secure Operating Licence, finish bridge repairs before first shipment
- 29 Sep 2026 Hot commissioning underway; licence pending
- 28 Sep 2026 Hot commissioning underway; Operating Licence pending
- 10 Aug 2026 Refurbishment 87%, on plan; commissioning next
- 27 Jul 2026 Refurbishment 77% complete, ahead of plan
Sonora concession cancellation arbitration
Cadence and REM Mexico are pursuing Mexico over the August 2023 cancellation of the Sonora lithium concessions. LCM non-recourse funding was secured in March 2026. On 29 July 2026 ICSID registered the claim as Case No. ARB/26/36 under the UK-Mexico BIT. The tribunal is yet to be formed, and the company says there is no certainty on outcome, duration or recovery.
- Forum
- ICSID Case No. ARB/26/36 under the UK-Mexico BIT
- Respondent
- United Mexican States
- Claims
- Unlawful expropriation, fair and equitable treatment, full protection and security, and national and most-favoured-nation treatment
- Funding
- LCM non-recourse funding of legal fees and disbursements, announced 24 March 2026
- Next milestone
- Appointment of three-member tribunal; each party appoints one arbitrator, then the chair is agreed
- Amount at stake
- Not stated; the company says there is no certainty of outcome, duration or level of recovery
Next: Constitute three-member tribunal, then set procedural timetable
- 29 Jul 2026 ICSID case registered; tribunal being constituted
- 29 Jun 2026 Non-recourse litigation funding secured post-period