CatalystWireBeta

Jadestone Energy

JSE · AIM · Energy · mcap £223m · 44.3p 3 open situations →

Beta Briefing, track record and signals & risks are not ready for Jadestone Energy yet.

We follow 960 UK small caps and every one of their announcements – often hundreds per company. 101 companies are already wired into a briefing: browse them.

Timeline · every situation
dots = announcements

Open · 3

Stake building towards control

PT Prima Petroleum Energi towards control

28.2779% (from 0%)

On 2 Sep 2026 Prima Energy, an Indonesian oil and gas operator, agreed to buy c.28.3% of Jadestone from Tyrus Capital funds, its largest shareholder, under a private share purchase agreement. Prima said it has no intention of making an offer and is bound by Rule 2.8. Jadestone responded the same day, noting it has not yet received independent confirmation of the Sale.

Buyer
PT Prima Petroleum Energi (Prima Energy), Indonesian independent oil and gas company 2 Sep 2026 ↗
Seller
Tyrus Capital S.A.M. funds 2 Sep 2026 ↗
Stake
c.28.3% of issued share capital, agreed 2 Sep 2026 2 Sep 2026 ↗
Offer intention
No intention to make an offer; bound by Rule 2.8 of the UK Takeover Code 2 Sep 2026 ↗
Rule 2.8 set-aside
With board agreement, a third-party offer or possible offer, a Rule 9 waiver or reverse takeover, or a material change of circumstances 2 Sep 2026 ↗
Advisers
Standard Chartered (financial); Herbert Smith Freehills Kramer (legal) 2 Sep 2026 ↗

Next: independent confirmation of the Sale received by Jadestone

  1. 3 Sep 2026 28.2779%
Open the full view – chart and every step →
Takeover target

Possible offer

approach
  1. 2 Sep 2026 approach
  2. 2 Sep 2026 approach
Open the full view – chart and every step →
Project milestones

Nam Du/U Minh Vietnam development

Restart still targeted around end Q3 2026

The Okha FPSO returned to the CWLH fields in May after dry-dock, but a riser J-tube issue needed repair. On 29 July 2026 restart was targeted for around end Q3 2026. The 27 Aug 2026 results keep that target, subject to the remedial works. The delay drove much of the H1 production decline and higher costs.

Restart
Still targeted around end Q3 2026 27 Aug 2026 ↗
2026 YTD production
~16,300 boe/d to end-April 19 May 2026 ↗
Operator
Woodside has developed detailed repair plans 29 Jul 2026 ↗
Cause
Repair of one subsea riser J-tube 27 Aug 2026 ↗
H1 impact
Dry dock and subsea dive campaign raised CWLH costs 27 Aug 2026 ↗
  1. 27 Aug 2026 Farm-out in final negotiations; FPSO contractor approved
  2. 29 Jul 2026 Campaign complete; all three wells online
  3. 19 May 2026 Drilling commenced April 2026
  4. 20 Apr 2026 GSPA signed; moving to execution phase
Open the full view – chart and every step →

Closed · 4

OverhangTyrus Capital, S.A.M selling down holder sold out · 3 Sep 2026 – 3 Sep 2026 Balance-sheet stress / refinancingRBL facility refinancing Refinancing complete; RBL repaid · 26 Feb 2026 – 29 Jul 2026 Upgrade / downgrade cycle2026 guidance and reserves update Guidance and reserves published; FCF guidance cut · 3 Feb 2026 – 26 Feb 2026 Insider conviction1 director buying £257k in 2 buys · 3 Oct 2024 – 11 Feb 2025 −20%

Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note