Amitsoq Phase III Drilling and AAM Pilot Plant

In brief · summary, not quotable

Phase III drilling completed at Amitsoq with eight holes showing significant graphite intersections; purification line arrived at pilot plant.

  • Thickest graphite intersection (true thickness) ca. 23.70m
  • Mineralised zone extension 100-150m N-NW
  • Global JORC Mineral Resource Estimate 23.05Mt grading 20.41% graphite
  • PEA mining plan 8.26Mt over 22 years at 21.3% graphite grade
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your GROC notes

GreenRoc Strategic Materials Plc (AIM: GROC), a company focused on developing critical mineral projects in Greenland, is pleased to announce the completion of its Phase III diamond drilling at Amitsoq and the arrival of the purification line for the Company's pilot plant in Denmark.

Key highlights

  • Eight holes drilled in total, with drilling from all three platforms showing significant intersections of graphite ore.
  • Thickest intersection (true thickness) was ca. 23.70m in drill hole AM_DD_041, similar to the thickest encountered during drilling in 2022.
  • Key objectives of the Phase III drilling have been achieved:

o Drilling has successfully extended the mineralised zone 100-150m N-NW.

o Drill core and associated geotechnical and hydrogeological information obtained are considered sufficient to proceed to the planned Pre-Feasibility Study ("PFS") on the mine.

  • GreenRoc is in the process of completing its review of PFS proposals from selected contractors.
  • Purification line received at GreenRoc's pilot plant in Denmark. Once fully operational, this will allow for the production of spherical purified graphite ("SPG") and commencement of the qualification process with offtake customers.

Overview

Phase III drilling at Amitsoq has now concluded and demobilisation has been successfully completed. In total, eight holes were drilled from three platforms, out of ten originally planned holes (see Fig

ure 1). The revised number of completed holes and the associated geotechnical and hydrogeological information obtained, are considered to be sufficient to enable GreenRoc to start the Pre-Feasibility Study ("PFS"), which is planned to begin in Q1 2027.

The Phase III drilling was designed to serve several purposes. First, it aimed to provide the basis for increasing the confidence level of the coming revised Resource Estimate. The global JORC-compliant Mineral Resource Estimate, announced on 23 January 2023, contained 23.05Mt grading 20.41% graphite across the Inferred, Indicated and Measured categories. The Preliminary Economic Assessment ("PEA"), announced on 31 October 2023, envisaged mining 8.26Mt of the Lower Graphite Layer orebody at a combined graphite grade of 21.3% over an initial 22 years of production at Amitsoq. Of this, 6.17Mt would be in the Measured and Indicated categories, and 2.1Mt in the Inferred category, which has the lowest confidence level. The Upper Graphite Layer was not considered for mining in the 2023 PEA model.

To plan the mining operation at the confidence level required for the planned PFS, the Estimated Mineral Resource should be in the Indicated or Measured categories, so one objective of Phase III was to convert the 2.1Mt of Inferred resource into the higher classification category.

Second, the potential northern extension of the orebodies, indicated by surface expressions, warranted drilling to confirm whether parts of the orebodies at higher elevations would be available for future mining. The Phase III drilling from drill Platform 3 has successfully extended the intersected graphite mineralisation approximately 100-150m north-northwest of the previous drilling, so this objective has been achieved (see Figure 1).

Any Mineral Resource upgrade or inclusion of the northern extension remains subject to assay results and assessment by the independent Competent Person.

Third, mine planning for the PFS requires hydrological, hydrogeological and rock strength data to be obtained from the drill holes and drill core. This data has been successfully obtained by specialist contractors during the drilling programme.

Figure 1, showing the planned and executed drill holes of the Phase III programme. Note also surface expressions of UGL in orange and LGL in red, as well as projection of the historical underground mine workings in dark grey.

Drilling at Amitsoq in 2026 was conducted from three platforms (Figure 1), with two holes from the southernmost Platform 1 (AM_DD_039 and _040), one hole from Platform 2 (AM_DD_041) and five holes from the northernmost Platform 3 (AM_DD_043, _044, _045, _046, and _047). The details of the drilling intersections with graphite are shown in Table 1.

Drillhole IDGraphite LayerFrom (m)To (m)Apparent Thickness (m)Estimated True Thickness (m)
AM_DD_039LGL107.09119.5112.4210.17
AM_DD_040UGL35.9540.864.914.61
AM_DD_040LGL93.04102.489.449.12
AM_DD_041LGL115.95142.7626.1523.70
AM_DD_043LGL137.30162.4825.1823.66
AM_DD_044LGL118.34123.314.973.19
AM_DD_046MGL139.40142.302.901.45
AM_DD_046LGL161.28165.454.173.19
AM_DD_047MGL113.42114.811.390.80
AM_DD_047LGL182.12204.9522.8311.42

Table 1. Substantial graphite intersections and estimated true thickness values in Phase III drillholes. Drill hole AM_DD_045 is not listed in the Table as no graphite orebodies were encountered here. True thickness calculation is based on measured angles of ore contact with wall rock. UGL = Upper Graphite Layer, MGL = Middle Graphite Layer, LGL = Lower Graphite Layer.

A second drill hole from Platform 2 was planned (AM_DD_042), but, as for the four planned holes from Platform 4, because of time constraints, this has been postponed until Drill Phase IV. All holes other than AM_DD_045 intersected significant thicknesses of what from visual inspection of drill core appears to be high-grade graphite ore. The northern section of the Amitsoq deposit, addressed by Phase III drilling, is dominated by the LGL and UGL only occurs in drill hole AM_DD_040 from the southernmost drill Platform 1. The occasional appearance of MGL is typical for this orebody which appears much less consistent than LGL.

All drill cores and the drill rig have now been moved to Nanortalik, where the remaining unsampled core will be cut and shipped for analysis. The first batch of drill core samples is on its way to ALS in Ireland for analysis. Drill rods, various other equipment and structures have been packed and winterised for the planned Phase IV drilling, which is due to commence in spring or summer 2027. Storing the equipment will reduce costs for both demobilisation this year and mobilisation in 2027, and greatly simplify the start of the next stage of the project.

Graphite purification line

GreenRoc has now received the main components of the purification line ordered from Sepor in Florida, USA (see RNS of 13 August 2026), including pumps, a filter press, reactor tanks, ovens and rinse tanks. Preparations are being made for installation. Earlier in the month, a Grundfos water purification plant capable of producing all the required process water to an ultra-pure standard was installed at GreenRoc's pilot plant. The purification line is planned to be ready for commissioning in January 2027 following an internal safety audit.

In conjunction with this, a 20-tonne bulk sample from Amitsoq is currently with GTK in Finland where it will be processed into graphite concentrate. This will mean that, once the purification line is fully commissioned and operational, the Company will be able to produce SPG from Amitsoq graphite concentrate and commence the qualification process with potential offtake customers.

GreenRoc attending Li-ion Battery Europe 2026 Conference in Barcelona

George Frangeskides, Chairman of GreenRoc is attending the 4th Li-Europe conference on 2-3 November 2026 and will be moderating a panel discussion "Strategic Repositioning of Investments Across the European Battery Value Chain and Capital Flows".

GreenRoc's CEO, Stefan Bernstein, commented:

"I'm very pleased with the results of this year's drilling at Amitsoq. We have confirmed the extent and thickness of the graphite orebodies, and have intersected the targeted mineralisation well beyond the current resource drilling and into the previously untested northern extension of the deposit.

"At the pilot plant in Hørsholm, Denmark, we have received the main components of the purification line and begun preparations for its installation. Subject to successful commissioning, we expect to be able to use graphite concentrate produced from our 20-tonne bulk sample to begin producing spherical purified graphite during 2027."

Investor questions on this announcement We encourage all investors to share questions on this announcement via our investor hubhttps://greenrocplc.com/link/PqaW8P
GreenRoc Strategic Materials Plc Stefan Bernstein, CEOinfo@greenrocplc.com +44 20 3950 0724
Cairn Financial Advisers LLP (Nomad) Sandy Jamieson / Louise O'Driscoll+44 20 7213 0880
Oberon (Broker) Nick Lovering / Adam Pollock+44 20 3179 5300

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note