Capital Limited
CAPD · Main Market · Basic Resources · mcap £275m · 117.5p 1 open situation →
Timeline · every situation
dots = announcementsOpen · 1
Project milestones
Reko Diq mining ramp-up
Performing in line with contract; Barrick review continues
Reko Diq mining began with both fleets double shifting, but Barrick slowed development from January 2026 and on 2 April 2026 said it will review the project until mid-2027. On 20 Aug 2026 Capital said operations were in line with contract. The 15 Oct Q3 update repeats this and says more equipment is en route, due in Q4.
- Barrick action
- Slowed development; review to mid-2027; reduced capital spend (2 April 2026) 15 Oct 2026 ↗
- Capital position
- Operations in line with contract; key contractor supporting development 15 Oct 2026 ↗
- Next milestone
- Additional equipment en route to Reko Diq, expected Q4 2026 15 Oct 2026 ↗
Next: Additional equipment arrives at Reko Diq in Q4 2026
- 15 Oct 2026 Performing in line with contract; Barrick review continues
- 20 Aug 2026 Slowed by Barrick; Capital supporting
- 16 Jul 2026 Slowed development; Capital's site position unchanged
- 21 Apr 2026 Both fleets double shifting; Barrick slowing development
Closed · 2