Aminex (CDI)
AEX · Main Market · Energy · mcap £83m · 1.7p 1 open situation →
Timeline · every situation
dots = announcementsOpen · 1
Project milestones
Ntorya gas field development
Revised programme agreed; execution pending
Ntorya development has been in dispute since Ndovu's notice over APT not implementing the approved 2026 budget. A government-backed schedule on 26 August kept first gas in December 2026 and preserved CH-1. The half-year report confirms the programme, with the pipeline about 95% laid and up to US$75m gross budgeted. The 2027 programme still needs TPDC and PURA approval, and the interim report says the programme must be judged on delivery.
- Budget approved
- Up to US$75 million gross across remainder of 2026 and 2027
- Next milestone
- NT-1 wellhead and slickline work from October 2026; NT-2 testing in November 2026
- First gas
- NT-2 gas into the pipeline by end December 2026
- NT-3 well
- Spud before end December 2026; gas from the well scheduled September 2027
- Pipeline
- About 95% of pipelaying and infilling complete; connection and metering finish December 2026
- CH-1
- Obligation well, to be drilled at the end of the programme
- 25 Sep 2026 Revised programme agreed; execution pending
- 23 Sep 2026 JV approved revised 2026 and provisional 2027 budgets
- 2 Sep 2026 Government-backed schedule agreed; dispute notice still open
- 21 Aug 2026 Formal dispute notice issued against operator APT
Company filings. Not investment advice.