Project milestones

Ntorya gas field development

Revised programme agreed; execution pending

Ntorya development has been in dispute since Ndovu's notice over APT not implementing the approved 2026 budget. A government-backed schedule on 26 August kept first gas in December 2026 and preserved CH-1. The half-year report confirms the programme, with the pipeline about 95% laid and up to US$75m gross budgeted. The 2027 programme still needs TPDC and PURA approval, and the interim report says the programme must be judged on delivery.

Budget approved
Up to US$75 million gross across remainder of 2026 and 2027
Next milestone
NT-1 wellhead and slickline work from October 2026; NT-2 testing in November 2026
First gas
NT-2 gas into the pipeline by end December 2026
NT-3 well
Spud before end December 2026; gas from the well scheduled September 2027
Pipeline
About 95% of pipelaying and infilling complete; connection and metering finish December 2026
CH-1
Obligation well, to be drilled at the end of the programme
  1. 25 Sep 2026 Revised programme agreed; execution pending
  2. 23 Sep 2026 JV approved revised 2026 and provisional 2027 budgets
  3. 2 Sep 2026 Government-backed schedule agreed; dispute notice still open
  4. 21 Aug 2026 Formal dispute notice issued against operator APT
Open the full view – chart and every step →

Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note