Gediktepe enriched ore treatment project
Gediktepe produced first copper concentrate on 31 August 2026 and is ramping up. The 2026 CPR, published 20 October 2026 and following the 17 September 2026 resource and reserve update, adds an enriched ore treatment project of about 83kt CuEq to life of mine production, with production expected in Q3 2027.
- Next milestone
- Enriched ore treatment production expected to come online in Q3 2027 20 Oct 2026 ↗
- Size
- Approximately 83kt CuEq added to life of mine production profile 20 Oct 2026 ↗
- Report
- 2026 CPR by SRK, JORC 2012, effective 31 July 2026, published 20 October 2026 20 Oct 2026 ↗
- Asset value
- Total asset post-tax NPV8 of approximately US$1.2 billion 20 Oct 2026 ↗
Next: Enriched ore treatment production comes online
- 20 Oct 2026 Included in 2026 CPR mine plan
Profit upgrade
Acg Acquisition Company Limited Cls A said it is trading ahead of expectations on 17 Sep 2026; the shares moved −4% on the day. It is the fourth such statement in 12 months.
- 17 Sep 2026 ahead of expectations · -4% on the day
- 14 Jul 2026 ahead of expectations · -0% on the day
- 14 Apr 2026 ahead of expectations · +4% on the day
- 19 Jan 2026 guidance raised · +6% on the day
AOF Trading LLC towards control
AOF Trading LLC raised its stake in Acg Acquisition Company Limited Cls A from 29.48% to 30.11% on 2 Dec 2025, crossing 29.9%.
Next: over 30% a holder normally has to make an offer (Rule 9)
- 2 Dec 2025 30.11%