Vast Resources (VAST): Zimbabwe diamond parcel sale

This situation live

VAST Vast Resources

£62m · 3.8p · −23% since the first step
8.4p 2.2p Now 3.8p · 23 Oct −31% −14% +0% +0% +0% +0% +0% Oct ’25NovDecJan ’26FebMarAprMayJunJulAugSepOct
1 Dec 2025 · Initial tender mostly low-grade; gem stones unsold · +26% until the next step The Company will provide further updates to the market as and when appropriate.
22 Dec 2025 · Further diamond sales expected · +0% until the next step The Company intends to use the revenue from upcoming diamond sales
15 Jul 2026 · Update promised shortly; no results given · +0% until the next step The Company intends to provide a further update regarding the progress of diamond processing and sales shortly.
Disposal of a part (break-up)
Zimbabwe diamond parcel sale
Polished sales deferred; retail channels started
Next: Dubai rough tender of c.5,000 ct, timing market-dependent
Every step · 10
  1. 31 Oct 2025 Parcel released; sale process begun – The Company has begun the process of selling the diamonds and this will significantly improve the financial position of the Company. ↗
  2. 17 Nov 2025 Initial parcel tender defined; higher-quality balance held back – The balance of the higher quality stones will be sold in a phased manner in due course to seek to maximise revenues and the total value of the diamonds for... ↗
  3. 25 Nov 2025 Initial parcel 98% sold; higher-grade balance remains – This first auction process paves the way for future tenders for the higher quality stones, and we look forward to providing further updates regarding those... ↗
  4. 1 Dec 2025 Initial tender mostly low-grade; gem stones unsold – The Company will provide further updates to the market as and when appropriate. ↗
  5. 22 Dec 2025 Further diamond sales expected – The Company intends to use the revenue from upcoming diamond sales ↗
  6. 30 Jan 2026 Phased sales of higher-quality stones continue – The balance of the higher quality stones is being sold in a phased manner to maximise returns to Shareholders and are expected to improve the financial... ↗
  7. 31 Mar 2026 Dubai sales delayed; Antwerp channel in talks – The Company is in advanced discussions regarding alternative sales channels in Antwerp and expects to conclude these arrangements in the coming weeks. ↗
  8. 5 May 2026 Antwerp channel set up; sales due to start – the Company has established an alternative sales channel in Antwerp and expects to commence the sales process during the week commencing 4 May 2026 ↗
  9. 15 Jul 2026 Update promised shortly; no results given – The Company intends to provide a further update regarding the progress of diamond processing and sales shortly. ↗
  10. 27 Jul 2026 Polished sales deferred; retail channels started – However, the Company, via its polished goods associate, has commenced selling via retail channels, which generate higher realised values per carat ("ct")... ↗

What is happening

Vast Resources: Zimbabwe diamond parcel sale – Polished sales deferred; retail channels started. ['Polished sales deferred; retail channels started']

In short
The first tender in November 2025 sold 98% of the parcel for about US$1.09m net, with higher-quality stones to be sold in phases. Dubai sales were delayed by Middle East conflict. On 27 July 2026 Vast said wholesale polished sales are deferred as Dubai and Antwerp are depressed, and it has begun retail sales of polished stones, only 19.51 ct sold so far.
Announced
31 Oct 2025 · Parcel released; sale process begun
Latest
27 Jul 2026 · Polished sales deferred; retail channels started
New channel
Antwerp, sales expected to start week commencing 4 May 2026
Next milestone
Further update on processing and sales shortly
Channel
Antwerp, sales expected from week commencing 4 May 2026
Rough sold
c.123,000 ct at c.US$8.50 per ct, revenue c.US$1.05m
Polished sold
19.51 ct at average US$3,295 per ct, US$0.064m
Polished remaining
c.1,674.39 ct, estimated average US$2,750 per ct
Polishing loss
Estimated 50-75% of initial weight
Next rough tender
c.5,000 ct in Dubai, timing set by market strength and stability

What comes next

Dubai rough tender of c.5,000 ct, timing market-dependent.

Briefing Pro

New to Vast Resources? Get up to speed in 2 minutes.

What it does, how it got here, what management promised and delivered – written from its own announcements.

Get the VAST briefing →
Ask VAST Beta
Ask anything about Vast Resources

Answered from its own announcements and reported figures, every statement linked to its source.

From the company's own announcements. Not investment advice.

Also at Vast Resources 4 open
Project milestonesSoviet Tailings reprocessing project – Drilling complete; plant build and assays pending Balance-sheet stress / refinancingAlpha and Mercuria loan default – Funding in place; settlement of loans pending Takeover targetOffer for the company – offer Project milestonesBPPM review and operations suspension – Suspended; geology and mine plan review under way Large acquisition / reverse takeoverGulf International Minerals reverse takeover – Completed; shares re-admitted to AIM on 19 Aug · closed Vast Resources – company page →