Touchstone Exploration Inc (TXP): Carapal Ridge-3 completion and tie-in
This situation live
TXP Touchstone Exploration Inc
5 Jan 2026 · Drilled; completion underway, tie-in targeted Q1 2026 · −8% until the next step
Completion operations are underway at CR-3. The Company intends to initially produce the undeveloped Herrera sands from the horizontal section of the well below the shale marker, while the uphole deve
25 Feb 2026 · Completed and perforated; shut-in awaiting tie-in · +33% until the next step
The well is currently shut-in and is scheduled to be tied into the Central block facility for production in late March 2026.
30 Mar 2026 · Onstream 28 March; cleaning up · −34% until the next step
The CR-3 well commenced production on March 28, 2026, and is currently flowing natural gas, 58-degree API condensate, and drilling and completion fluids.
14 May 2026 · Producing at low rate; inflow restriction · +0% until the next step
Based on current well performance and flowing parameters, the well appears to be experiencing an inflow restriction.
28 May 2026 · Awaiting coiled tubing unit; may defer · +28% until the next step
Given the favourable gas pricing associated with the Train 4 diversion, Touchstone is evaluating whether it is commercially advantageous to defer the CR-3 shut-in and optimization program until the At
14 Aug 2026 · Coiled tubing unit repaired; workover scheduled · −11% until the next step
The CR-3 workover is scheduled for execution by late August 2026.
14 Sep 2026 · Cleanout failed; Karamat completion planned October · +24% since
Execution of the Karamat completion program is targeted for October 2026.
Carapal Ridge-3 completion and tie-in
Cleanout failed; Karamat completion planned October
OCT31
Next: Karamat sands completion program at CR-3 in 7 days
Every step · 7
- 5 Jan 2026 Drilled; completion underway, tie-in targeted Q1 2026 – Completion operations are underway at CR-3. The Company intends to initially produce the undeveloped Herrera sands from the horizontal section of the well... ↗
- 25 Feb 2026 Completed and perforated; shut-in awaiting tie-in – The well is currently shut-in and is scheduled to be tied into the Central block facility for production in late March 2026. ↗
- 30 Mar 2026 Onstream 28 March; cleaning up – The CR-3 well commenced production on March 28, 2026, and is currently flowing natural gas, 58-degree API condensate, and drilling and completion fluids. ↗
- 14 May 2026 Producing at low rate; inflow restriction – Based on current well performance and flowing parameters, the well appears to be experiencing an inflow restriction. ↗
- 28 May 2026 Awaiting coiled tubing unit; may defer – Given the favourable gas pricing associated with the Train 4 diversion, Touchstone is evaluating whether it is commercially advantageous to defer the CR-3... ↗
- 14 Aug 2026 Coiled tubing unit repaired; workover scheduled – The CR-3 workover is scheduled for execution by late August 2026. ↗
- 14 Sep 2026 Cleanout failed; Karamat completion planned October – Execution of the Karamat completion program is targeted for October 2026. ↗
What is happening
Touchstone Exploration Inc: Carapal Ridge-3 completion and tie-in – Cleanout failed; Karamat completion planned October. ['Cleanout failed; Karamat completion planned October']
- In short
- CR-3 went onstream on 28 March at about 2.2 MMcf/d with an inflow restriction. The coiled tubing cleanout and acid stimulation was completed in August and early September (update of 14 Sep 2026) but gave only a limited response and did not cure the drilling damage. The company now plans an uphole Karamat completion in October 2026.
- Announced
- 5 Jan 2026 · Drilled; completion underway, tie-in targeted Q1 2026
- Latest
- 14 Sep 2026 · Cleanout failed; Karamat completion planned October
- Constraint
- Sole local coiled tubing provider fixing mechanical issues and sourcing parts
- Possible deferral
- Until the Atlantic LNG maintenance window ends, 19 July 2026
- Next milestone
- Karamat sands completion program targeted for October 2026
- Equipment
- Local provider resolved mechanical issues; unit is function testing
- Train 4 outage
- Planned maintenance ran 26 May to 3 August 2026
- Cleanout result
- Coiled tubing cleanout and acid stimulation completed Aug/early Sep 2026; limited production response
- Karamat pay
- About 82 feet net pay between 6,530 and 6,760 feet
- Other wells
- Karamat sands also present in Carapal Ridge-1 and Carapal Ridge-2
What comes next
Karamat sands completion program at CR-3 (31 Oct 2026).
From the company's own announcements. Not investment advice.
Briefing Pro
New to Touchstone Exploration Inc? Get up to speed in 2 minutes.
What it does, how it got here, what management promised and delivered – written from its own announcements.
Get the TXP briefing →Also at Touchstone Exploration Inc 3 open
Project milestonesCascadura development and compression – Cleanout failed; Karamat completion planned October
Dilutive fundraiseEquity raise and loan covenant – Debenture converted to equity; going-concern doubt remains
Stake building towards controlPurebond Limited towards control – 36.27% (from 19.99%)
Insider conviction1 director buying – £45k in 1 buy · closed
Touchstone Exploration Inc – company page →