Tharisa (THS): Karo Platinum Project build-out
This situation live
THS Tharisa
10 Nov 2025 · Bondholders approved extension; effective 1 December 2025 · +32% until the next step
approved by the requisite majority, with effect from the maturity date of the existing bonds, being 1 December 2025
13 Jan 2026 · Extension effective; Tharisa funding Karo further · −8% until the next step
At Karo, development remains aligned with capital availability, with Tharisa providing additional funding support to maintain momentum on the project timeline.
14 Apr 2026 · Karo funding progressing; fiscal agreements nearing conclusion · +3% until the next step
The funding is subject to final agreement with the Government of Zimbabwe on the fiscal stability agreements which are nearing conclusion.
7 May 2026 · Contractor appointed; first portal under development · −7% until the next step
The signing follows on from the successful first blast on 31 March 2026 marking the commencement of the development of the first portal at the Tharisa Mine.
14 Jul 2026 · Portal development on time and on budget · +8% until the next step
Tharisa underground project on time and in line with budget, portal development on track to deliver first ROM within Q4
24 Aug 2026 · Special Mining Lease signed; fiscal terms agreed · +2% until the next step
The parties have agreed to the fiscal terms, and the agreement was signed by Hon. Minister Dr Eng. Polite Kambamura of the Ministry of Mines and Mining Development and Hon. Minister Mthuli Ncube of th
27 Aug 2026 · Offtake signed; refinancing still not mentioned · +2% until the next step
This agreement underpins the bankability of Karo, reflects the quality of the asset and reinforces the partnership-led approach that has been central to Tharisa's development since inception.
11 Sep 2026 · Bond priced; settlement pending · −2% until the next step
successful pricing of a US$300 million five-year senior secured bond issued at 98% of principal, with a semi-annual coupon of 11.00% per annum
25 Sep 2026 · Proceeds in escrow; release conditions pending · −2% until the next step
will see proceeds released to the Group upon fulfilment of the remaining applicable release conditions
13 Oct 2026 · Construction; awaiting bond drawdown · −10% since
The US$300 million bond has been sized to fund the remaining construction programme, with proceeds held in escrow pending fulfilment of the customary conditions precedent.
Karo Platinum Project build-out
Construction; awaiting bond drawdown
NOV30
Next: Drawdowns from Nov 2026; ore mining Oct 2026; first ore to mill Q4 CY2027 in 37 days
Every step · 10
- 10 Nov 2025 Bondholders approved extension; effective 1 December 2025 – approved by the requisite majority, with effect from the maturity date of the existing bonds, being 1 December 2025 ↗
- 13 Jan 2026 Extension effective; Tharisa funding Karo further – At Karo, development remains aligned with capital availability, with Tharisa providing additional funding support to maintain momentum on the project timeline. ↗
- 14 Apr 2026 Karo funding progressing; fiscal agreements nearing conclusion – The funding is subject to final agreement with the Government of Zimbabwe on the fiscal stability agreements which are nearing conclusion. ↗
- 7 May 2026 Contractor appointed; first portal under development – The signing follows on from the successful first blast on 31 March 2026 marking the commencement of the development of the first portal at the Tharisa Mine. ↗
- 14 Jul 2026 Portal development on time and on budget – Tharisa underground project on time and in line with budget, portal development on track to deliver first ROM within Q4 ↗
- 24 Aug 2026 Special Mining Lease signed; fiscal terms agreed – The parties have agreed to the fiscal terms, and the agreement was signed by Hon. Minister Dr Eng. Polite Kambamura of the Ministry of Mines and Mining... ↗
- 27 Aug 2026 Offtake signed; refinancing still not mentioned – This agreement underpins the bankability of Karo, reflects the quality of the asset and reinforces the partnership-led approach that has been central to... ↗
- 11 Sep 2026 Bond priced; settlement pending – successful pricing of a US$300 million five-year senior secured bond issued at 98% of principal, with a semi-annual coupon of 11.00% per annum ↗
- 25 Sep 2026 Proceeds in escrow; release conditions pending – will see proceeds released to the Group upon fulfilment of the remaining applicable release conditions ↗
- 13 Oct 2026 Construction; awaiting bond drawdown – The US$300 million bond has been sized to fund the remaining construction programme, with proceeds held in escrow pending fulfilment of the customary... ↗
What is happening
Tharisa: Karo Platinum Project build-out – Construction; awaiting bond drawdown. ['Construction; awaiting bond drawdown']
- In short
- Karo build-out continued after the 25-year Special Mining Lease (24 Aug 2026), Valterra offtake (27 Aug 2026) and US$300m bond (escrow confirmed 25 Sep 2026). The 13 Oct 2026 report shows US$240m of US$516m capex spent, pre-stripping at 1.91m BCM and construction moving to steel erection. Drawdowns are expected from Nov 2026 and first ore to the mill is still targeted for Q4 CY2027.
- Announced
- 10 Nov 2025 · Bondholders approved extension; effective 1 December 2025
- Latest
- 13 Oct 2026 · US$288.2m in escrow; conditions pending
- Output ambition
- CEO says Karo will more than double PGM output and add a second Tier 1 asset
- Key agreements
- SMLA and Valterra offtake agreement concluded
- Conditions
- Remaining release conditions must be met before project drawdown
- Capex to date
- US$240m of US$516m: US$204m Tharisa equity, US$36m KMH bond
- Next milestone
- Ore mining from October 2026; mechanical installation Q1 2027
- Commissioning
- July to October 2027; first ore to mill Q4 CY2027
- Steady state
- 220-230 koz 6E per annum, about six months after first ore in mill
- Progress
- Pre-stripping 1.91m BCM; Chirundazi Dam 75% complete; cleaner flotation 73%
What comes next
Drawdowns from Nov 2026; ore mining Oct 2026; first ore to mill Q4 CY2027 (30 Nov 2026).
Briefing Pro
New to Tharisa? Get up to speed in 2 minutes.
What it does, how it got here, what management promised and delivered – written from its own announcements.
Get the THS briefing →From the company's own announcements. Not investment advice.