CatalystWireBeta

Prospex Energy (PXEN): Selva Malvezzi development wells and 3D

This situation live

PXEN Prospex Energy

£26m · 5.9p · +44% since the first step
6.8p 2.3p Now 5.9p · 23 Oct −6% +14% +2% +2% +83% +8% Oct ’25NovDecJan ’26FebMarAprMayJunJulAugSepOct
31 Oct 2025 · EIA revised; 3D survey permitting near complete · −21% until the next step The operator has progressed a new environmental study incorporating recommendations and amendments from the EIA technical commission
19 Jan 2026 · 3D survey completed; JV payments up to date · +2% until the next step The Company is now up to date with its obligations in the Selva Malvezzi Joint Venture.
30 Apr 2026 · 3D processing; EIA being updated · +2% until the next step Specialist studies requested by the EIA Commission are ongoing and are expected to be submitted in Q2 2026.
15 May 2026 · 3D seismic processing under way · −12% until the next step Development costs in Q1 2026 primarily relate to seismic processing on Selva Malvezzi.
Project milestones
Selva Malvezzi development wells and 3D
Licences held; Mniszow development planning
DEC31 Next: Independent review of Mniszow resource in 68 days
Every step · 12
  1. 20 Oct 2025 Awaiting reinterpretation of reprocessed 3D seismic – Once the newly reprocessed 3D seismic is reinterpreted it is the Operator's intention to update the reservoir model, gas in place and the reserves for the... ↗
  2. 31 Oct 2025 EIA revised; 3D survey permitting near complete – The operator has progressed a new environmental study incorporating recommendations and amendments from the EIA technical commission ↗
  3. 18 Nov 2025 3D acquisition underway since 13 November – The acquired data will undergo time-domain volume processing, anticipated to be completed by April 2026, producing a full three-dimensional subsurface model... ↗
  4. 20 Nov 2025 Operator working on reprocessed 3D seismic model – The operator is working on the reprocessed 3D seismic database with a view to optimising the structural model so that a reserve report can be commissioned... ↗
  5. 24 Nov 2025 3D underway; drilling permits advancing – The Selva Malvezzi production concession in northern Italy continues its steady production and cash generation with a new gas sales contract agreed with... ↗
  6. 19 Jan 2026 3D survey completed; JV payments up to date – The Company is now up to date with its obligations in the Selva Malvezzi Joint Venture. ↗
  7. 28 Jan 2026 3D acquired; processing; EIA under update – The specialist studies requested by the EIA commission are in progress and expected to be submitted to the Ministry in Q2 2026. ↗
  8. 30 Apr 2026 3D processing; EIA being updated – Specialist studies requested by the EIA Commission are ongoing and are expected to be submitted in Q2 2026. ↗
  9. 15 May 2026 3D seismic processing under way – Development costs in Q1 2026 primarily relate to seismic processing on Selva Malvezzi. ↗
  10. 3 Aug 2026 Dynamic model built; development scenarios defined – During the quarter, operator HEYCO Energy Iberia advanced the dynamic reservoir model and defined several development scenarios for further drilling... ↗
  11. 7 Sep 2026 2027 development planning continues – Field development planning has continued, and the core operational plan includes testing the water injection capability of the ST3 well (currently shut-in)... ↗
  12. 28 Sep 2026 Licences held; Mniszow development planning – Planning for a 2027 development programme is ongoing, including testing the water injection capability of the shut-in ST3 well starting in Q4 2026, and the... ↗

What is happening

Prospex Energy: Selva Malvezzi development wells and 3D – Licences held; Mniszow development planning. ['Licences held; Mniszow development planning']

In short
Prospex was awarded the San and Dunajec licences, which PXEN Tatra accepted. Work continued on historical data and well design for the Mniszow oil discovery. The 28 Sep 2026 H1 report says a mid-September site visit took place, a Mniszow development presentation was released and an independent resource review is planned for Q4 2026.
Announced
20 Oct 2025 · Awaiting reinterpretation of reprocessed 3D seismic
Latest
28 Sep 2026 · 2027 development planning continues
Funding
Cash on hand to fund licences and early prospectivity assessment
Next milestone
Independent resource review in Q4 2026
Permit fees
£177k of new permit fees paid in Q2 2026
Mniszów oil
Company view of 3.7 mmbbl recoverable
Focus
Well and completion design for Mniszów oil discovery on Dunajec licence
Site visit
San and Dunajec licence areas, mid-September 2026
Partnering
Evaluating advanced completion techniques to support partner talks
Mniszow resource
Company assessment of about 3.7 million barrels recoverable

What comes next

Independent review of Mniszow resource (31 Dec 2026).

Ask PXEN Beta
Ask anything about Prospex Energy

Answered from its own announcements and reported figures, every statement linked to its source.

From the company's own announcements. Not investment advice.

Briefing Pro

New to Prospex Energy? Get up to speed in 2 minutes.

What it does, how it got here, what management promised and delivered – written from its own announcements.

Get the PXEN briefing →
Also at Prospex Energy 1 open
New CEO / resetCEO succession – New CEO's strategy being implemented Insider conviction1 director buying – £41k in 2 buys · closed Prospex Energy – company page →

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note