Petrotal Corporation (PTAL): Bretana drilling restart and water handling
This situation live
PTAL Petrotal Corporation
13 Nov 2025 · Building breakwaters #1 and #3; on schedule · −23% until the next step
PetroTal continues to target completion date in Q3 2026, with total project cost estimates falling within a range of $65-75 million.
13 Nov 2025 · Delayed; water handling expansion needed · −23% until the next step
At this point, PetroTal believes the best-case timing to resume drilling at Bretana is mid-year 2026.
20 Jan 2026 · On plan; no material cost changes · +17% until the next step
There are no material changes to cost estimates or timelines for the erosion control project at this time; PetroTal expects to complete the project by Q4 2026, for a total investment of $65-75 million
25 Feb 2026 · Restart targeted for October 2026 · +32% until the next step
We look forward to the planned resumption of drilling in October 2026 and will continue to update the market on our progress as necessary.
26 Mar 2026 · Behind schedule; contractor being replaced, re-tender · −7% until the next step
The Company is currently soliciting bids and expects to award a new construction contract by the end of May 2026, at which time it will be in a better position to provide updated estimates on the tota
14 Apr 2026 · Contract in final stages; rig mobilizing · +11% until the next step
We are in the final stages of securing a contract with a third-party drilling contractor and expect to mobilize a rig to the field in the coming months, with drilling activities targeted to resume by
7 May 2026 · Re-tender underway; award slipped to end June · −14% until the next step
The tender process is underway and PetroTal expects to award a new contract by the end of June 2026.
15 Jul 2026 · Still in contractor discussions; no award announced · −1% until the next step
There are no material changes to the status of the erosion control project at this time. PetroTal remains in discussions with third-party contractors about restarting construction activities in a safe
6 Aug 2026 · Re-tender ongoing; construction largely suspended · +19% until the next step
That process remains ongoing, with updated bids now expected by the end of August.
7 Sep 2026 · Evaluating proposals; construction largely suspended · −1% until the next step
PetroTal continues to evaluate several proposals to reinitiate construction activities at the erosion control project.
23 Sep 2026 · Well 25H spud 21 Sept; drilling under way · +4% until the next step
Well 25H is expected to take approximately eight weeks to drill and complete, at a total cost of $15 million.
14 Oct 2026 · Well 25H drilling on schedule at 3,362m · +2% since
The well is currently drilling at a depth of 3,362 meters, in line with pre-drill prognosis.
Bretana drilling restart and water handling
Well 25H drilling on schedule at 3,362m
NOV9
Next: 25H well results and Q3 financial results webcast in 16 days
Every step · 12
- 13 Nov 2025 Building breakwaters #1 and #3; on schedule – PetroTal continues to target completion date in Q3 2026, with total project cost estimates falling within a range of $65-75 million. ↗
- 13 Nov 2025 Delayed; water handling expansion needed – At this point, PetroTal believes the best-case timing to resume drilling at Bretana is mid-year 2026. ↗
- 20 Jan 2026 On plan; no material cost changes – There are no material changes to cost estimates or timelines for the erosion control project at this time; PetroTal expects to complete the project by Q4... ↗
- 25 Feb 2026 Restart targeted for October 2026 – We look forward to the planned resumption of drilling in October 2026 and will continue to update the market on our progress as necessary. ↗
- 26 Mar 2026 Behind schedule; contractor being replaced, re-tender – The Company is currently soliciting bids and expects to award a new construction contract by the end of May 2026, at which time it will be in a better... ↗
- 14 Apr 2026 Contract in final stages; rig mobilizing – We are in the final stages of securing a contract with a third-party drilling contractor and expect to mobilize a rig to the field in the coming months,... ↗
- 7 May 2026 Re-tender underway; award slipped to end June – The tender process is underway and PetroTal expects to award a new contract by the end of June 2026. ↗
- 15 Jul 2026 Still in contractor discussions; no award announced – There are no material changes to the status of the erosion control project at this time. PetroTal remains in discussions with third-party contractors about... ↗
- 6 Aug 2026 Re-tender ongoing; construction largely suspended – That process remains ongoing, with updated bids now expected by the end of August. ↗
- 7 Sep 2026 Evaluating proposals; construction largely suspended – PetroTal continues to evaluate several proposals to reinitiate construction activities at the erosion control project. ↗
- 23 Sep 2026 Well 25H spud 21 Sept; drilling under way – Well 25H is expected to take approximately eight weeks to drill and complete, at a total cost of $15 million. ↗
- 14 Oct 2026 Well 25H drilling on schedule at 3,362m – The well is currently drilling at a depth of 3,362 meters, in line with pre-drill prognosis. ↗
What is happening
Petrotal Corporation: Bretana drilling restart and water handling – Well 25H drilling on schedule at 3,362m. ['Well 25H drilling on schedule at 3,362m']
- In short
- Drilling restarted at Bretana with well 25H spud on 21 Sept 2026, the first new well since January 2025. On 14 Oct 2026 the company said drilling was on schedule at 3,362m. Injection capacity rose after stimulations. It now targets about 20,000 bopd by end of Q1 2027.
- Announced
- 13 Nov 2025 · Building breakwaters #1 and #3; on schedule
- Latest
- 14 Oct 2026 · Well 25H drilling on schedule at 3,362m
- Injection capacity
- Just over 190,000 bwpd since 3 Sept, up 9% on August; target 320,000 bwpd by end-2028
- September output
- Group 12,286 bopd; Bretana 11,960 bopd; both up about 600 bopd on August
- Inventory
- 22 drilling locations remaining; target plateau of approximately 20,000 bopd
- Progress
- At 3,362 meters on 14 October 2026, in line with pre-drill prognosis
- Target
- Bretana production about 20,000 bopd by end of Q1 2027
- Water injection
- Averaged 187,000 bwpd in September 2026, up 6% on August
- Q3 production
- Group 11,797 bopd; Bretana 11,465 bopd
- Next milestone
- Q3 results and 25H update webcast on 9 November 2026
What comes next
25H well results and Q3 financial results webcast (9 Nov 2026).
Briefing Pro
New to Petrotal Corporation? Get up to speed in 2 minutes.
What it does, how it got here, what management promised and delivered – written from its own announcements.
Get the PTAL briefing →From the company's own announcements. Not investment advice.
Also at Petrotal Corporation 2 open
Insider conviction1 director buying – £160k in 3 buys
Turnaround plan with targets2026 budget and development plan – Development plan revised; more wells and water disposal
Insider conviction2 directors buying – £101k in 2 buys · closed
OverhangBlue Harbour Capital Fund I Open-ended Fund Company, acting on behalf of Blue Harbour Capital Securities Fund I selling down – 22.52% → 2.63% in 1 notice · closed
Capital returnSpecial dividend and buyback programme – proposed · closed
Petrotal Corporation – company page →