Metals Exploration (MTL): La India construction
This situation live
MTL Metals Exploration
14 Nov 2025 · Construction progressing · +6% until the next step
as well as progressing the construction at La India in Nicaragua.
9 Dec 2025 · 24% complete, ahead of schedule; first gold Q4 2026 · +32% until the next step
The on-site laboratory building is nearing completion and is scheduled to be operative from February 2026, with Interteck having been selected as the preferred supplier to manage the on-site laborator
28 Jan 2026 · 33% complete, ahead of schedule, within revised budget · −27% until the next step
Overall construction continues to be within the revised budget and ahead of schedule at 33% complete.
30 Mar 2026 · 40% complete, ahead of schedule, budget raised · +11% until the next step
First gold production at La India remains on track for December 2026.
23 Apr 2026 · 40% complete, ahead of schedule, mining concession renewed · −2% until the next step
Overall construction continues to be within the revised budget and ahead of schedule at 40% complete.
22 May 2026 · About 50% complete, ahead of schedule · −1% until the next step
Development of the La India project has continued to progress post-Period end, with construction now approximately 50% complete and tracking ahead of schedule.
15 Jun 2026 · Agreements signed; exploration starting · +2% until the next step
Initial exploration work to begin immediately, followed by a drill programme anticipated to commence in H2 2026.
16 Jul 2026 · 56% complete, on track; budget raised to US$177m · +12% until the next step
Overall construction is 56% complete, with first gold pour remaining on track for December 2026.
21 Aug 2026 · Construction advancing; equipment loan drawn · +8% until the next step
First gold – first gold production at La India remains on track for December 2026.
28 Sep 2026 · Plant installation advancing; loan fully drawn · +0% until the next step
First gold – first gold production at La India remains on track for December 2026.
30 Sep 2026 · Pre-drilling underway; drilling expected Q4 2026 · −2% since
The total Project budget has marginally increased to c.US$180 million due to unforeseen logistics costs and new import duties imposed on certain imported goods. The first gold pour at La India remains
La India construction
Pre-drilling underway; drilling expected Q4 2026
Next: Drilling campaign expected to commence
Every step · 11
- 14 Nov 2025 Construction progressing – as well as progressing the construction at La India in Nicaragua. ↗
- 9 Dec 2025 24% complete, ahead of schedule; first gold Q4 2026 – The on-site laboratory building is nearing completion and is scheduled to be operative from February 2026, with Interteck having been selected as the... ↗
- 28 Jan 2026 33% complete, ahead of schedule, within revised budget – Overall construction continues to be within the revised budget and ahead of schedule at 33% complete. ↗
- 30 Mar 2026 40% complete, ahead of schedule, budget raised – First gold production at La India remains on track for December 2026. ↗
- 23 Apr 2026 40% complete, ahead of schedule, mining concession renewed – Overall construction continues to be within the revised budget and ahead of schedule at 40% complete. ↗
- 22 May 2026 About 50% complete, ahead of schedule – Development of the La India project has continued to progress post-Period end, with construction now approximately 50% complete and tracking ahead of schedule. ↗
- 15 Jun 2026 Agreements signed; exploration starting – Initial exploration work to begin immediately, followed by a drill programme anticipated to commence in H2 2026. ↗
- 16 Jul 2026 56% complete, on track; budget raised to US$177m – Overall construction is 56% complete, with first gold pour remaining on track for December 2026. ↗
- 21 Aug 2026 Construction advancing; equipment loan drawn – First gold – first gold production at La India remains on track for December 2026. ↗
- 28 Sep 2026 Plant installation advancing; loan fully drawn – First gold – first gold production at La India remains on track for December 2026. ↗
- 30 Sep 2026 Pre-drilling underway; drilling expected Q4 2026 – The total Project budget has marginally increased to c.US$180 million due to unforeseen logistics costs and new import duties imposed on certain imported... ↗
What is happening
Metals Exploration: La India construction – Pre-drilling underway; drilling expected Q4 2026. ['Pre-drilling underway; drilling expected Q4 2026']
- In short
- On 15 June 2026 MTL announced agreements giving it exclusive rights to explore Batong Buhay, a porphyry copper-gold project in the Philippines, as a possible successor to Runruno. Pre-drilling began by 16 July 2026. The 30 Sep 2026 interims narrow the drilling start to Q4 2026 from H2 2026.
- Announced
- 14 Nov 2025 · Construction progressing
- Latest
- 30 Sep 2026 · 74.4% complete; first gold on track December 2026
- Next milestone
- Drilling campaign expected to commence Q4 2026
- Ownership
- MTL subsidiary 80% of FEMC; Balatoc (Kalinga) Tribe 20% free carried
- Minimum spend
- Year 1 PHP 30m (~US$0.5m); Year 2 PHP 60m (~US$1m); five-year total PHP 1bn (~US$16m)
- Government payments
- PMDC: PHP 50m (~US$0.8m) signing fee, annual PHP 10m commitment fee, 2% NSR rising to 3% after 10 years
- Historical resource
- Dickson non-JORC 86.9Mt at 0.83% CuEq from surface
- Pending
- PMDC to finalise Exploration Permit EXPA-079 with the MGB
- Location
- c. 200km north of Runruno
What comes next
Drilling campaign expected to commence.
From the company's own announcements. Not investment advice.
Briefing Pro
New to Metals Exploration? Get up to speed in 2 minutes.
What it does, how it got here, what management promised and delivered – written from its own announcements.
Get the MTL briefing →Also at Metals Exploration 2 open
Upgrade / downgrade cycleRunruno end of mine life – H1 output halved; mining to cease Q4 2026
Insider conviction1 director buying – £8,158k in 2 buys
Insider conviction4 directors buying – £297k in 6 buys · closed
Metals Exploration – company page →