Jubilee Metals Group (JLP): Large Waste Project
This situation live
JLP Jubilee Metals Group
21 Nov 2025 · Resource review and design underway · +37% until the next step
Discussions with potential project partners are progressing with internal target date remaining the end of the current quarter
19 Feb 2026 · Resource review drafts issued; two partners shortlisted · −23% until the next step
The results from the resource review have confirmed the scale of the project and details of the results from the review will be provided to shareholders once the final report is issued, expected withi
31 Mar 2026 · Stage payment made; partner talks ongoing · −11% until the next step
Settled the next stage payment towards the acquisition of the Large Waste Project of US$2.6 million leaving a balance of US$5.4 million (total acquisition value of US$18 million)
10 Aug 2026 · Two binding offers received; sale to be agreed · −10% until the next step
Jubilee will provide further detail on the transaction once the preferred Purchaser has been selected and definitive transaction agreements are concluded which are expected within the next two weeks.
26 Aug 2026 · Preferred purchaser selected; due diligence under way · −11% until the next step
The transaction will proceed through a two-stage due diligence process.
8 Oct 2026 · Legal DD complete; 45-day technical DD begins · −3% since
Based on the terms of the binding heads of terms, a further 45-day period is offered to complete the further due diligence mainly focussing on the technical aspects of the material as well as the conc
Large Waste Project
Legal DD complete; 45-day technical DD begins
Next: Complete technical DD and definitive documents within 45 days
Every step · 6
- 21 Nov 2025 Resource review and design underway – Discussions with potential project partners are progressing with internal target date remaining the end of the current quarter ↗
- 19 Feb 2026 Resource review drafts issued; two partners shortlisted – The results from the resource review have confirmed the scale of the project and details of the results from the review will be provided to shareholders... ↗
- 31 Mar 2026 Stage payment made; partner talks ongoing – Settled the next stage payment towards the acquisition of the Large Waste Project of US$2.6 million leaving a balance of US$5.4 million (total acquisition... ↗
- 10 Aug 2026 Two binding offers received; sale to be agreed – Jubilee will provide further detail on the transaction once the preferred Purchaser has been selected and definitive transaction agreements are concluded... ↗
- 26 Aug 2026 Preferred purchaser selected; due diligence under way – The transaction will proceed through a two-stage due diligence process. ↗
- 8 Oct 2026 Legal DD complete; 45-day technical DD begins – Based on the terms of the binding heads of terms, a further 45-day period is offered to complete the further due diligence mainly focussing on the technical... ↗
What is happening
Jubilee Metals Group: Large Waste Project – Legal DD complete; 45-day technical DD begins. ['Legal DD complete; 45-day technical DD begins']
- In short
- Jubilee has been shortlisting partners for the Large Waste Project since late 2025. On 10 Aug 2026 it announced two binding offers; on 26 Aug 2026 it chose a preferred purchaser at US$35.0m. On 8 Oct 2026 it said legal due diligence is complete, with a US$2.25m deposit due within days and a 45-day technical DD and documentation period starting.
- Announced
- 21 Nov 2025 · Resource review and design underway
- Latest
- 8 Oct 2026 · Legal DD complete; 45-day technical DD begins
- Payment
- Settled over 3 years, first instalment due December 2026 if completed
- Seller settlement
- US$5.0m final payment in 150 489 090 new shares at 2.5p, 4.5% of enlarged capital; admission around 14 August 2026
- Use of money
- Accelerated investment in existing Zambian copper operations, including Molefe Mine
- Price
- approximately US$35 million total consideration; US$30.0m if settled within two years
- Next milestone
- 45-day period for technical due diligence and final documentation
- Replaces
- Previous 10Mt waste sale for US$6.75m; about 550 000t collected, about US$0.6m paid
- Deposit
- US$2.25 million expected within the next few days
- Conditions
- Final due diligence, definitive documentation and customary conditions precedent
What comes next
Complete technical DD and definitive documents within 45 days.
Briefing Pro
New to Jubilee Metals Group? Get up to speed in 2 minutes.
What it does, how it got here, what management promised and delivered – written from its own announcements.
Get the JLP briefing →From the company's own announcements. Not investment advice.
Also at Jubilee Metals Group 3 open
Project milestonesMolefe mine ramp-up – Commissioning complete; fine-tuning for stable operation
Upgrade / downgrade cycleFY2026 copper guidance – Still under review
Capital returnCapital reduction and shareholder distributions – Shareholder consultation; legal process being scoped
Disposal of a part (break-up)Sale of SA Chrome and PGM – Completed; second instalment due shortly · closed