ITM Power (ITM): Lingen and Refhyne II 100 MW plants
This situation live
ITM ITM Power
4 Dec 2025 · Lingen 1 delivered; Lingen 2 and Refhyne II on plan · −11% until the next step
The world's first 100 MW PEM plant for RWE in Lingen has progressed well, with our scope now fully delivered and installed.
29 Jan 2026 · Lingen 1 installed and tested; Lingen 2 progressing · +66% until the next step
For the second 100 MW, Lingen 2, all TRIDENT skids and already 40% of the stacks have been installed.
4 Aug 2026 · First hydrogen delivered to customer during commissioning · −18% until the next step
we look forward to supporting the project's continued ramp-up towards full 200 MW commercial operation.
19 Oct 2026 · Lingen 1 operational; Lingen 2 on track · −6% since
Second 100 MW, Lingen 2, on track for completion in this financial year
Lingen and Refhyne II 100 MW plants
Lingen 1 operational; Lingen 2 on track
Next: Lingen 2 completion in FY27; ramp-up of both plants
Every step · 4
- 4 Dec 2025 Lingen 1 delivered; Lingen 2 and Refhyne II on plan – The world's first 100 MW PEM plant for RWE in Lingen has progressed well, with our scope now fully delivered and installed. ↗
- 29 Jan 2026 Lingen 1 installed and tested; Lingen 2 progressing – For the second 100 MW, Lingen 2, all TRIDENT skids and already 40% of the stacks have been installed. ↗
- 4 Aug 2026 First hydrogen delivered to customer during commissioning – we look forward to supporting the project's continued ramp-up towards full 200 MW commercial operation. ↗
- 19 Oct 2026 Lingen 1 operational; Lingen 2 on track – Second 100 MW, Lingen 2, on track for completion in this financial year ↗
What is happening
ITM Power: Lingen and Refhyne II 100 MW plants – Lingen 1 operational; Lingen 2 on track. ['Lingen 1 operational; Lingen 2 on track']
- In short
- ITM and Linde Engineering are delivering two 100 MW plants to RWE at Lingen. First hydrogen went to Evonik's Marl park, announced 4 Aug 2026. In the 19 Oct 2026 results ITM says Lingen 1, the world's largest PEM electrolyser plant, is now operational, and Lingen 2 is on track for completion in the current financial year.
- Announced
- 4 Dec 2025 · Lingen 1 delivered; Lingen 2 and Refhyne II on plan
- Latest
- 19 Oct 2026 · Lingen 1 operational; Lingen 2 on track
- Milestone
- First hydrogen produced and delivered to Evonik's Marl chemical park, announced 4 Aug 2026
- Size
- Two 100 MW plants, 200 MW in total, for RWE
- Pipeline
- Approximately 120 km of hydrogen pipeline to Marl
- Project
- GET H2 Nukleus
- Next milestone
- Lingen 2 completion; full 200 MW commercial operation, no date stated
- Status
- Commissioning ongoing
- Lingen 1
- 100 MW, now operational; world's largest PEM electrolyser plant (results, 19 Oct 2026)
- Lingen 2
- Second 100 MW, on track for completion in FY27
What comes next
Lingen 2 completion in FY27; ramp-up of both plants.
Briefing Pro
New to ITM Power? Get up to speed in 2 minutes.
What it does, how it got here, what management promised and delivered – written from its own announcements.
Get the ITM briefing →From the company's own announcements. Not investment advice.
Also at ITM Power 3 open
Project milestonesHydropulse 150 MW refinery project – Heads of Terms signed; FEED study under way
Project milestonesChronos 1 GW manufacturing line – DESNZ grant formally awarded; funding secured
Project milestonesMorGen West Wales Hydrogen project – FID reached; equipment and 10-year LTSA signed
Insider conviction1 director buying – £197k in 1 buy · closed
Insider conviction1 director buying – £30k in 1 buy · closed
ITM Power – company page →