First Tin (1SN): Taronga permitting and development approval

This situation live

1SN First Tin

£73m · 13.4p · +70% since the first step
18.0p 6.0p Now 13.4p · 23 Oct −2% +77% −20% +0% −4% +10% Oct ’25NovDecJan ’26FebMarAprMayJunJulAugSepOct
18 Dec 2025 · Final assays in; independent consultant updating resource · +77% until the next step All assay data has been provided to an independent consultant for an updated Mineral Resource Estimate, expected by early 2026.
1 Jun 2026 · RTS lodged with DPHI; awaiting assessment · −4% until the next step Final NSW Government departments and agency consultation on the RTS, coordinated by DPHI;
Project milestones
Taronga permitting and development approval
Final approval stages; RTS under assessment
Next: Development Approval from DPHI after RTS assessment
Every step · 8
  1. 27 Oct 2025 EIS submitted September 2025 – Submitted the Environmental Impact Statement (EIS) in September 2025, a significant step forward for Taronga, and the anticipated receipt of developmental... ↗
  2. 4 Nov 2025 Drilling complete; 36 assays outstanding; DFS mid-2026 – Once the remaining assay are received later this month, we will move swiftly to update our resource and reserve estimate ahead of the optimised DFS to be... ↗
  3. 12 Nov 2025 EIS exhibition closed; IPC referral avoided – the project will now proceed through the standard departmental approval process rather than referral to the Independent Planning Commission (IPC) ↗
  4. 18 Dec 2025 Final assays in; independent consultant updating resource – All assay data has been provided to an independent consultant for an updated Mineral Resource Estimate, expected by early 2026. ↗
  5. 25 Feb 2026 Updated MRE underway ahead of DFS update – Updated Mineral Resource Estimate ("MRE") underway, expected to convert inferred resources to measured and indicated categories, support an extended mine... ↗
  6. 30 Apr 2026 Updated MRE delivered; DFS update pending – We look forward to incorporating updated pit designs and an extended life of mine, based on the new MRE, in our forthcoming DFS update. ↗
  7. 1 Jun 2026 RTS lodged with DPHI; awaiting assessment – Final NSW Government departments and agency consultation on the RTS, coordinated by DPHI; ↗
  8. 17 Aug 2026 Final approval stages; RTS under assessment – has completed an updated Definitive Feasibility Study ("DFS") for its 100%-owned Taronga Tin Project in New South Wales, Australia. ↗

What is happening

First Tin: Taronga permitting and development approval – Final approval stages; RTS under assessment. ['Final approval stages; RTS under assessment']

In short
The Response to Submissions was lodged with DPHI on 1 June 2026 after only four objections, so there is no IPC referral. The DFS update repeats that permitting is in final approval stages. Phase 1 sits within the existing pit limits in the permit application. Phase 2 will need later permitting. No approval date is given.
Announced
27 Oct 2025 · EIS submitted September 2025
Latest
17 Aug 2026 · Updated DFS completed
Next milestone
Agency consultation on the RTS, coordinated by DPHI, then departmental assessment and draft approval conditions
Approval pathway
Standard departmental route; no IPC referral after four objections
Regulator
Department of Planning, Housing and Infrastructure (DPHI)
Timetable
Development Approval date not stated
Phase 1 scope
Contained entirely within existing pit limits in current permitting envelope
Phase 2
Requires permitting in later years; described as low-risk continuation of mining
Existing support
Non-binding US EXIM Letter of Interest for up to US$120m
Status
Financing and offtake discussions progressing and well advanced

What comes next

Development Approval from DPHI after RTS assessment.

Briefing Pro

New to First Tin? Get up to speed in 2 minutes.

What it does, how it got here, what management promised and delivered – written from its own announcements.

Get the 1SN briefing →
Ask 1SN Beta
Ask anything about First Tin

Answered from its own announcements and reported figures, every statement linked to its source.

From the company's own announcements. Not investment advice.

Also at First Tin 1 open
Takeover targetOffer for the company – offer OverhangArlington Group Asset Management Ltd. selling down – 11.21% → 0% in 2 notices · closed Stake building towards controlMetals X Limited towards control – 29.91% (from 23.07%) · closed First Tin – company page →