Energean (ENOG): Israel production disruptions
This situation live
ENOG Energean
27 Oct 2025 · Output recovered in Q3 after June suspension · −3% until the next step
Production for the period was down year-on-year due to the temporary suspension of production in Israel in June 2025.
26 Nov 2025 · Q3 output recovered; 9M still down 3% · −1% until the next step
Production increased in the third quarter, rising 35% quarter-on-quarter to average 176 kboed, reflecting operational excellence and robust summer gas demand in Israel following the temporary suspensi
26 Nov 2025 · Suspension ended 25 June; ceasefire announced October · −1% until the next step
On June 25, 2025, the Ministry of Energy and Infrastructure instructed the safe restart and resumption of production and operations of the Energean Power FPSO, and Energean acted in accordance with th
2 Mar 2026 · New FPSO suspension ordered 28 February 2026 · +2% until the next step
confirms that it received notice from the Ministry of Energy and Infrastructure on 28 February 2026 ordering the temporary suspension of production and activities of the Energean Power FPSO
19 Mar 2026 · Production still suspended at 19 March 2026 · −7% until the next step
As of the time of writing, production in Israel remains suspended.
9 Apr 2026 · Restart permitted 9 April; ramp-up under way · +2% until the next step
Energean is working to safely restart production and resume normal operations in line with its operating procedures.
13 Apr 2026 · FPSO fully operational; guidance update pending · +1% until the next step
Energean will provide an update to its 2026 guidance in due course.
20 May 2026 · FPSO restarted; guidance cut to 130-140 kboed · −2% until the next step
Production in Israel was temporarily suspended for 41 days between 28 February and 9 April 2026, following a directive from the Ministry of Energy and Infrastructure due to geopolitical escalations.
20 May 2026 · FPSO restarted; Q1 accounts show impact · −2% until the next step
On 28 February 2026, the Ministry of Energy and Infrastructure ordered the temporary suspension of production and activities of the Energean Power FPSO following further escalation of geopolitical ten
9 Sep 2026 · Production recovered; FY guidance reiterated · −15% since
Production has subsequently recovered strongly, with 8-months 2026 production averaging 135 Kboe/d, in line with full-year guidance of 130-140 Kboe/d[11]
9 Sep 2026 · Recovered; H1 Israel accounts show resilience · −15% since
Production of the Energean Power FPSO was resumed and the FPSO became fully operational on 10 April 2026.
Israel production disruptions
Recovered; H1 Israel accounts show resilience
Every step · 11
- 27 Oct 2025 Output recovered in Q3 after June suspension – Production for the period was down year-on-year due to the temporary suspension of production in Israel in June 2025. ↗
- 26 Nov 2025 Q3 output recovered; 9M still down 3% – Production increased in the third quarter, rising 35% quarter-on-quarter to average 176 kboed, reflecting operational excellence and robust summer gas... ↗
- 26 Nov 2025 Suspension ended 25 June; ceasefire announced October – On June 25, 2025, the Ministry of Energy and Infrastructure instructed the safe restart and resumption of production and operations of the Energean Power... ↗
- 2 Mar 2026 New FPSO suspension ordered 28 February 2026 – confirms that it received notice from the Ministry of Energy and Infrastructure on 28 February 2026 ordering the temporary suspension of production and... ↗
- 19 Mar 2026 Production still suspended at 19 March 2026 – As of the time of writing, production in Israel remains suspended. ↗
- 9 Apr 2026 Restart permitted 9 April; ramp-up under way – Energean is working to safely restart production and resume normal operations in line with its operating procedures. ↗
- 13 Apr 2026 FPSO fully operational; guidance update pending – Energean will provide an update to its 2026 guidance in due course. ↗
- 20 May 2026 FPSO restarted; guidance cut to 130-140 kboed – Production in Israel was temporarily suspended for 41 days between 28 February and 9 April 2026, following a directive from the Ministry of Energy and... ↗
- 20 May 2026 FPSO restarted; Q1 accounts show impact – On 28 February 2026, the Ministry of Energy and Infrastructure ordered the temporary suspension of production and activities of the Energean Power FPSO... ↗
- 9 Sep 2026 Production recovered; FY guidance reiterated – Production has subsequently recovered strongly, with 8-months 2026 production averaging 135 Kboe/d, in line with full-year guidance of 130-140 Kboe/d[11] ↗
- 9 Sep 2026 Recovered; H1 Israel accounts show resilience – Production of the Energean Power FPSO was resumed and the FPSO became fully operational on 10 April 2026. ↗
What is happening
Energean: Israel production disruptions – Recovered; H1 Israel accounts show resilience. ['Recovered; H1 Israel accounts show resilience']
- In short
- The ministry shut the Energean Power FPSO from 28 February to 9 April 2026 (41 days). The 20 May update cut 2026 Group guidance to 130-140 kboed. The 9 September results showed recovery and reiterated guidance. The Israel H1 accounts show revenue of $481m and net profit of $101m, both flat year on year, with the going concern basis kept.
- Announced
- 27 Oct 2025 · Output recovered in Q3 after June suspension
- Latest
- 9 Sep 2026 · Recovered; H1 Israel accounts show resilience
- Restart
- FPSO fully operational on 10 April 2026
- Risk
- Any event affecting Karish and Karish North production could have a material adverse impact
- Production
- 8-month 2026 average 135 kboed; August above 180 kboed
- H1 production
- 124 kboed versus 138 kboed in H1 2025
- Guidance
- Group 130-140 kboed reiterated
- H1 revenue
- $481.3m versus $482.6m in H1 2025
- H1 net profit
- $101.0m versus $100.5m
- Going concern
- Basis adopted; liquidity sufficient to 31 December 2027, including prolonged suspension scenario
From the company's own announcements. Not investment advice.
Briefing Pro
New to Energean? Get up to speed in 2 minutes.
What it does, how it got here, what management promised and delivered – written from its own announcements.
Get the ENOG briefing →Also at Energean 4 open
Project milestonesKatlan and Irena developments – Principal terms agreed with EGPC
Large acquisition / reverse takeoverAngola Block 14 acquisition – Etu signed SPA under pre-emption; Energean SPA still in effect
Insider conviction4 directors buying – £1,117k in 6 buys
Legal & regulatoryCassiopea arbitration and impairment – Impairment booked in FY2025 results
Insider conviction5 directors buying – £3,846k in 7 buys · closed
Energean – company page →