New 5 MWp PV Development Project in Puglia
Zenith acquires 5 MWp solar development project in Puglia, Italy, increasing pipeline to 238 MWp.
- New project capacity 5 MWp
- Total solar development pipeline 238 MWp
- Land purchase consideration EUR 560,000
Select text to share a quote on X · sign in to keep highlights & notes in your ZEN notes
Zenith Energy Ltd. (LSE: ZEN; OSE: ZENA; XSAT: ZENA SDR), the international energy production and development company, is pleased to announce the addition of a new ground-mounted photovoltaic development project with an anticipated installed capacity of approximately 5 MWp, located in the Province of Foggia, in the Puglia region of Italy (the "Project").
The Project increases the Company's total solar development pipeline to approximately 238 MWp, bringing it close to its target of 240 MWp by the end of 2026.
Overview of the Project
- The Project is expected to proceed under the Simplified Authorisation Procedure (Procedura Abilitativa Semplificata, or PAS), subject to the applicable eligibility requirements. This route may allow a significantly more efficient permitting process than ordinary authorisation procedures.
- The Company estimates that the Project could reach Ready-to-Build status in approximately 8 to 10 months including grid connection, final design and the PAS procedure.
- Based on preliminary assessments, the Company anticipates a comparatively straightforward grid connection with relatively limited associated infrastructure costs, compared with projects requiring much longer connection routes.
- The Project is classified as being in the development stage.
- The land purchase comprises approximately 8 hectares at EUR 70,000 per hectare, for a total consideration of approximately EUR 560,000. The consideration becomes payable only once the Project achieves Ready-to-Build status, limiting the Company's financial exposure until the Project is fully authorised.
.
Andrea Cattaneo, Chief Executive Officer, commented:
"This new 5 MWp project strengthens our position in Puglia, where our first plants are already under construction.
With our pipeline now at approximately 238 MWp, we are within reach of our 240 MWp targets for the end of 2026. Our focus remains on projects that can move quickly towards Ready-to-Build, and negotiations on the sale of selected development assets are continuing."