Cascadura-5 Well Drilling Results
Cascadura-5 well drilled to 7,020 feet with hydrocarbon-bearing sands observed throughout primary interval.
- Cascadura-5 well total depth 7,020 feet
- Gross sand encountered approximately 620 feet
- Drilling duration 22 days
- Field-estimated drilling costs approximately US$5 million
Select text to share a quote on X · sign in to keep highlights & notes in your TXP notes
CALGARY, ALBERTA (July 7, 2025) - Touchstone Exploration Inc. ("Touchstone" or the "Company") (TSX, LSE: TXP) provides an operational update on the Cascadura-5 development well ("Cas-5"), located on the Ortoire block onshore in the Republic of Trinidad and Tobago. Touchstone has an 80 percent operating working interest in the well, with Heritage Petroleum Company Limited holding the remaining 20 percent.
The Cas-5 well was spud on June 4, 2025, using Star Valley Drilling Rig #205 and was drilled to a total depth of 7,020 feet over 22 days. Following open-hole logging operations, the well was cased for future production.
The primary target of the Cas-5 well was the Herrera Gr7bc sands, which are prevalent in the Cascadura structure. Cas-5 is the second well drilled into the B block of the Cascadura structure and encountered approximately 620 feet of gross sand. The targeted reservoir intervals were observed approximately 300 feet updip of the Cascadura-2 well, which was drilled in the first quarter of 2024.
The original planned total depth of the well was 6,654 feet. Based on encouraging drill cuttings and mud logging data indicating continued hydrocarbon presence, drilling was extended to 7,020 feet. Wireline logging, mud logging, and drill cuttings data collectively suggest that hydrocarbon-bearing sands are present throughout the primary Gr7bc interval.
When funding is available, the drilling rig is expected to be mobilized to complete operations at the nearby Cascadura-4 well ("Cas-4"), which is currently cased to a depth of 3,200 feet. Cas-4 is also targeting the Herrera sands, with a planned total depth of approximately 6,500 feet.
Upon drilling Cas-4, the Company intends to complete and tie-in Cas-4 and Cas-5 into the Cascadura natural gas facility. All required tie-in equipment is currently on location.
Paul R. Baay, President and Chief Executive Officer, commented:
"Cas-5 was drilled on schedule and on budget, with field-estimated costs of approximately US$5 million, despite extending the target depth. The performance of our new drilling team, along with the use of synthetic oil-based mud and managed pressure drilling, was instrumental in delivering a successful operation. We encountered no material issues during drilling, which we attribute to improvements implemented following previous challenges. The hydrocarbon intervals observed align with or exceed our pre-drill expectations and continue to enhance our understanding of the Cascadura structure as we integrate ongoing seismic interpretation."
Placing update
The Company continues to evaluate its options regarding the unfunded placing commitments and will issue a further announcement as soon as practicable.
Touchstone Exploration Inc.
Touchstone Exploration Inc.
Paul Baay, President and Chief Executive Officer Tel: +1 (403) 750-4405
James Shipka, EVP Asset Development and HSE
Shore Capital (Nominated Advisor and Joint Broker)
Daniel Bush / Toby Gibbs / Tom Knibbs Tel: +44 (0) 207 408 4090
Canaccord Genuity (Joint Broker)
Adam James / Charlie Hammond Tel: +44 (0) 207 523 8000
FTI Consulting (Financial PR)
Nick Hennis / Ben Brewerton / Lucy Wigney Tel: +44 (0) 203 727 1000
Advisories
Working Interest
Touchstone holds an 80 percent operating working interest in the Cascadura field, which forms part of the Ortoire block, onshore in the Republic of Trinidad and Tobago. The remaining 20 percent participating interest is held by Heritage Petroleum Company Limited.
Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.