This release should be read with the Company’s Financial Statements and Management Discussion & Analysis ("MD&A"), available at www.tasekomines.com and filed on www.sedarplus.com . Except where otherwise noted, all currency amounts are stated in Canadian dollars. Taseko owns 100% of the Gibraltar Mine, which is located north of the City of Williams Lake in south-central British Columbia.

VANCOUVER, British Columbia, May 01, 2025 (GLOBE NEWSWIRE) -- Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) ("Taseko" or the "Company") reports first quarter 2025 Adjusted EBITDA* of $34 million and Earnings from mining operations before depletion and amortization and non-recurring items* of $39 million. Revenues for the first quarter were $139 million from the sale of 22 million pounds of copper and 364 thousand pounds of molybdenum. The Company recorded a Net loss of $29 million ($0.09 loss per share) and an Adjusted net loss* of $7 million ($0.02 loss per share).

Gibraltar produced 20 million pounds of copper and 336 thousand pounds of molybdenum in the first quarter at Total operating costs (C1) of US$2.26 per pound of copper produced. Mill throughput averaged 87,800 tons per day, which was above design capacity. Copper grades in the quarter averaged 0.19% and copper recoveries were 68%.

At Florence Copper, construction remains on schedule and as of the end of March the overall project completion was at 78%. Construction of the SX/EW plant, surface infrastructure and the wellfield drilling are tracking to plan. In the wellfield, drilling is nearly complete and the last two wells will be constructed in May. The electrowinning crane has been installed in the plant, allowing the building structure to be completed. Construction of surface infrastructure is also advancing on schedule, including work on the pipe corridor, electrical substation, tank farm, and office and dry buildings.

Stuart McDonald, President and CEO of Taseko, commented, “Through the first 15 months of construction at Florence Copper, all critical aspects of the project remain on schedule and our operating plans are well developed. In the coming months, site construction activities will begin to slow down and in the fall we expect to commence wellfield operations as we advance towards first copper cathode production later in the year. Our project team remains focussed on continued execution of the remaining construction activities, and our growing operations team is planning for the production ramp up in 2026.”

“At our Gibraltar mine, mill throughput exceeded design capacity in the first quarter and head grades were in line with plan. But copper production in the quarter was impacted by lower than expected metallurgical recoveries from oxidized ore. Also, challenging ground conditions at the top of the current Connector pit pushback have led to lower mining productivities in recent months which will delay the release of higher-grade ore from the second quarter to the third quarter. As a result, copper production for 2025 is expected to be about 10 million pounds (~8%) lower than our previous guidance. Significantly higher grades and recoveries are expected in the second half of this year and into 2026”, continued Mr. McDonald.

  • McDonald concluded, “With less than nine months until the startup of Florence Copper, America’s next copper mine, Taseko is approaching a period of significant production and cashflow growth. We are uniquely positioned as the North American copper producer with both near-term production growth and a longer-term growth pipeline.”

*Non-GAAP performance measure. See

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note