Operations Update For The South Crofty Tin Project

In brief · summary, not quotable

Cornish Metals Inc. provided an operational update for its South Crofty tin project, reporting progress on underground refurbishment at the New Cook's Kitchen mid-shaft pump station, with installation of new pumps well advanced and expected completion before year-end, after which dewatering will resume aiming for the lower pump station level by mid-2026. Underground development has commenced at the No. 1 level for rock-hoisting facilities, also serving as training for mining crews. Surface activities include excavation for a new pre-concentration plant and construction of a workshop and stores facility, with major works anticipated by the end of Q1 2026, alongside refurbishment of mine dry facilities.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your TIN notes

Cornish Metals Inc. (AIM/TSXV: CUSN) ("Cornish Metals" or the "Company"), a mineral exploration and development company focused on advancing its wholly owned and permitted South Crofty tin project in Cornwall, United Kingdom, is pleased to provide an update on the progress of activities at South Crofty.

Underground activities

Refurbishment work on the New Cook's Kitchen ("NCK") mid-shaft pump station (at approximately 360 metres below surface) is progressing to plan with removal of the old pumps, pipes and steelwork complete and installation of the new permanent pumps well advanced (see images 1 and 2). Work on the pump station is expected to be completed before the end of the year after which the submersible pumps will be lowered to below the lower pump station level (approximately 730 metres below surface). Mine dewatering will resume at that point and is expected to reach the lower pump station level in mid-2026.

Underground development at the No. 1 level (approximately 50 metres below surface) has now started, consisting of approximately 600 metres of lateral development, which is required to establish the skip discharge and rock handling facilities for the NCK Shaft rock-hoisting system. This development programme is also being used to facilitate training of the Company's mining crews in modern, mechanised development mining methods, utilising the recently purchased single-boom jumbo drill rigs and other trackless equipment Cornish Metals is acquiring as it builds its Life of Mine mobile fleet (see image 3).

Surface activities

The second phase of excavation for the new pre-concentration plant commenced in late November, as planned. Following the initial phase of topsoil removal which has been underway since August 2025, the second phase of work is focused on the removal of the overburden and rock across the footprint of the building (see image 4).

Construction activities for the new workshop and stores facility located at the old Bartles Foundry site are progressing well with the bulk excavation, foundations, and steelwork complete and the building cladding now underway. Major works are expected to be completed by the end of Q1 2026, in-line with the schedule (see images 5 and 6).

Additionally, Phase 1 of the Mine Dry refurbishment, which includes the changing room facilities and canteen, was completed in October 2025. Phase 2 of the Mine Dry, which includes additional changing facilities and office space is currently underway, and it expected to be completed in Q1 2026.

Don Turvey, CEO of Cornish Metals, commented: "The work programme at South Crofty has continued this year following the successful fundraise completed in Q1, and is progressing in line with our latest guidance. On surface, excavation and construction activities continue to advance across the site. Underground, significant progress has been made at the New Cook's Kitchen mid-shaft pump station, with the area cleared, installation of new permanent pumps well underway, and the start of development at the No. 1 level serving as an important step that will provide a training platform for newly recruited miners."

Image 1: New Cook's Kitchen shaft pump station - installation of pump bases.

Image 2: New Cook's Kitchen shaft pump station - mounting of the new permanent pumps.

Image 3: No. 1 level underground development - test run of Epiroc MT2010 haul truck down Tuckingmill decline.

Image 4: Pre-concentration plant excavation work.

Image 5: Workshop and stores building steel frame.

Image 6: Workshop and stores building cladding underway.

ON BEHALF OF THE BOARD OF DIRECTORS

"Don Turvey"

Don Turvey

CEO and Director

Engage with us directly at our investor hub. Sign up at: https://investors.cornishmetals.com/link/eNmOly

Caution regarding forward looking statements

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note