Update on production at Triton FPSO

In brief · summary, not quotable

Triton FPSO production ramp-up delayed; now expected to reach stable levels in August rather than July.

vs expectations: below

  • 2025 production guidance 33,000-35,000 boepd (prior 33,000-37,000 boepd)
  • Production from other assets almost 30,000 boepd
  • Portfolio potential once all Triton fields online over 55,000 boepd
  • Triton FPSO net production to Serica in January 25,000 boepd
  • BE01 well flow test rate 7,500 boepd constrained
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your SQZ notes

Serica Energy plc (AIM: SQZ) announces that, having successfully restarted production operations at the Triton FPSO in July, the ramp up to steady-state production has been slower than the timetable provided by the operator, Dana Petroleum ('Dana'). Production is now expected to reach a stable level in August.

Following the initial resumption of production from the Bittern field (which flows first due to associated gas from the field being used to provide gas lift for other wells and fuel gas for the FPSO), a problem with the gas lift system prevented other Triton fields being restarted. Additionally, other minor work was identified, which required a short cessation of production to repair. This remedial work now being complete, the restart of the Triton fields including new wells should proceed to an expedited timeline.

Production from the Bittern field (Serica 64.6%) will be followed rapidly by the Evelyn (Serica 100%) and Gannet (Serica 100%) fields. Once existing wells resume production, the new wells drilled on the Guillemot North West (Serica: 10%) and Evelyn (Serica: 100%) fields will be brought onstream for the first time, promising an increase to the 25,000 boepd the Triton FPSO was producing net to Serica in January.

The BE01 well on the Belinda field (Serica 100%), which flow tested at constrained rates of 7,500 boepd, is expected to enter production at the start of 2026 following work to tie the well into the Triton FPSO.

2025 Production Guidance

Given the delayed ramp up of production at Triton, Serica now expects production for 2025 to be 33,000-35,000 boepd (previously 33,000-37,000 boepd).

Chris Cox, Serica's CEO, stated:

"While teething issues with the resumption of production are not entirely unexpected after such a prolonged period of downtime, it doesn't make it any less frustrating to once again see things at the Triton FPSO progressing more slowly than we would expect. Our production from other assets is currently robust at almost 30,000 boepd and our portfolio has the potential to produce over 55,000 boepd once all Triton fields are back online, levels that we now expect in August rather than July. We are continuing to drive discussions with senior management at Dana regarding the optimal way to run the FPSO going forward."

Serica will issue 2025 half-year results at 0700 BST on Tuesday 5 August 2025, and will host a live presentation on the Investor Meet Company platform at 0900 BST on the day. Questions can be submitted pre-event via the Investor Meet Company dashboard up until 4 August, 0900 BST, or at any time during the live presentation. Investors can sign up and add to meet Serica Energy plc via:

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note