Update on Triton FPSO

In brief · summary, not quotable

Triton FPSO production suspended due to compressor seal issue; repairs expected to take two to four weeks.

  • 2024 production forecast approximately 35,000 to 36,000 boepd
  • Current Serica production ex-Triton around 28,000 boepd
  • Gas production from Bruce Hub and other assets around 22,000 boepd
  • Current gas price around 115-120p/therm
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your SQZ notes

Serica Energy plc (AIM: SQZ) announces that, after a limited resumption of production at the Triton FPSO last week, an issue with one of the compressor seals has been discovered which has resulted in production being suspended. The FPSO operator, Dana Petroleum, is working to identify and execute the necessary repairs, which are expected to take two to four weeks to complete. Production for 2024 is now forecast to be approximately 35,000 to 36,000 boepd.

As previously stated, the operational vulnerability will remain until the ongoing works to restore two-compressor operations are completed, expected in Q1 2025.

With production at Triton suspended, current Serica production from the Bruce Hub and other assets totals around 28,000 boepd. Of this, around 22,000 boepd of production is gas, benefitting from the current gas price of around 115-120p/therm.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note