Hindlip Construction Progress Update
Hindlip 7.5 MW power site construction progressing on schedule with COD expected Q2 2026.
- Hindlip capacity 7.5 MW
- Capacity Market T-4 contract cumulative guaranteed gross profit income c. £6.3m before inflation increases
- Expected Commercial Operations Date Q2 2026
Select text to share a quote on X · sign in to keep highlights & notes in your QDE notes
(Registration Number: 12886458)
Share code on the LSE: MAST
("MED" or "the Company")
Dated: 20 August 2025
Mast Energy Developments PLC
("MED" or the "Company")
Hindlip Construction Progress Update
Mast Energy Developments PLC is pleased to announce, further to its RNS announcement dated 6 May 2025, a construction progress update regarding its Hindlip 7.5 MW flexible generation power site which is fully funded in partnership with Powertree, the highlights and details of which are outlined below.
Hindlip Construction Progress Highlights:
- Site property's long-term leasehold option exercised and the long-term leasehold agreement exchanged and completed;
- Grid connection >5 MW Gate 2 protection application submitted and approved;
- Grid connection for c. 7.5 MW secured and majority of construction costs already paid;
- RFP submitted to industry-leading EPC firms, and following careful review of associated EPC proposals, MTU (Rolls Royce) engines selected as the best option for this site;
- Contract for new engines executed and order placed; and
- Site full construction works (including inter alia civils, LV and HV electricals, and grid- and gas connection) planned to commence in September 2025, with Commercial Operations Date ("COD") expected in Q2 2026.
Pieter Krügel, MED CEO, commented: "We are very pleased with the construction progress at Hindlip, with construction on track to be completed and COD expected in Q2 2026. It is a pleasure working with a partner of the calibre of Powertree, which not only brings investment capital to the table, but also a wealth of industry experience."
"The Hindlip site's already secured Capacity Market T-4 15-year contract with a cumulative guaranteed gross profit income value of c. £6.3m (before inflation increases) as previously announced, plus Embedded Benefits income, and PPA merchant trading income following COD make the site a very attractive investment. This along with other key elements including inter alia these types of flexgen sites being a critical part of the UK's energy security policy, fits perfectly into MED's business model and strategy to build a portfolio of 300+ MW."
"We are looking forward to updating the market with further positive progress and developments over the coming weeks."
MED general enquiries - https://www.med.energy/contact
MED email alerts - https://www.med.energy/rnsannoucements-1
MED LinkedIn page - https://uk.linkedin.com/company/mast-energy-developments-plc
MED X (formerly Twitter) handle - @mastplc
Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.