TSXV Final Acceptance for Helium & CO2 Plant

In brief · summary, not quotable

TSXV approves helium liquefaction and CO2 plant proposal with Chart Energy; first payment of US$5.025m made.

  • Helium Plant capacity 861 litres per hour (approximately 7.5 million litres annually)
  • CO2 Plant capacity 300-tonne-per-day capture capacity (over 100,000 tonnes annually)
  • Total equipment supply price US$85.5 million
  • First payment made US$5,025,000
  • Milestone 2 payment due US$8.55 million on January 31, 2027
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your PLSR notes

NEWS RELEASENOVEMBER 17, 2026DULUTH, USA

PULSAR HELIUM RECEIVES TSX VENTURE EXCHANGE FINAL ACCEPTANCE FOR COMMERCIAL-SCALE HELIUM LIQUEFACTION AND CO2 PLANT

Pulsar Helium Inc. (AIM: PLSR) (TSXV: PLSR) (OTCQB: PSRHF) (“Pulsar” or the “Company”), a primary helium company, is pleased to announce that, further to its announcements dated June 30, 2026, August 3, 2026, and October 1, 2026, it has received final acceptance from the TSX Venture Exchange (the “TSXV”) of the commercial proposal (the “Proposal”) entered into by the Company, through its wholly-owned subsidiary, Pulsar Helium MN Inc., with Chart Energy & Chemicals, Inc. (“Chart”), a wholly-owned subsidiary of Baker Hughes Company (“Baker Hughes”), for the supply of equipment for Pulsar's proposed Rare Gas Hub in Minnesota (the “Transaction”).

The Proposal provides for the supply of equipment for (i) a helium purification and liquefaction plant with capacity of 861 litres per hour, equivalent to approximately 7.5 million litres of liquid helium (approximately 200 million standard cubic feet of gaseous helium) annually at continuous nameplate operation (the “Helium Plant”); and (ii) a CO2 plant with 300-tonne-per-day capture capacity, expected to produce over 100,000 tonnes of liquid CO2 annually (the “CO2 Plant” and, together with the Helium Plant, the “Plant”).

Certain additional components relating to the CO2 Plant, including CO2 storage and loading and site-support services, are outside the current equipment-supply scope and will be addressed separately. Equipment manufacture is scheduled to take place over an approximate two-year period following receipt of the Milestone 2 (as defined below) payment. Certain equipment included in the Proposal and relating specifically to the helium liquefaction system has already been manufactured.

The aggregate equipment-supply price is US$85.5 million, payable entirely in cash in stages on achievement of milestones. The price is not the total installed cost of the Plant and excludes taxes, duties and tariffs, installation and commissioning, site infrastructure and interconnections, and certain other owner and third-party costs.

Following receipt of TSXV final acceptance on November 3, 2026, the Company has paid to Chart US$5,025,000 under the Proposal from existing cash resources (the “First Payment”). The First Payment comprised the 5% initial milestone of US$4,275,000 (“Milestone 1”) and the US$750,000 milestone payment under the existing Limited Notice To Proceed (“LNTP”). All LNTP amounts (totalling US$1,000,000, including the US$250,000 deposit previously paid) are credited dollar-for-dollar against amounts payable under the Proposal.

A payment of US$8.55 million is scheduled for January 31, 2027, and will authorize procurement of long-lead items (“Milestone 2”). If it is not paid by that date, the project automatically enters a suspension period of up to 180 days, during which the reserved helium liquefaction equipment remains protected, Pulsar has no obligation to pay Milestone 2, and no cancellation charge arises solely from the suspension. At the end of the suspension period, the parties will seek to agree whether to proceed, amend the commercial arrangements or terminate the project. The Company currently intends to fund this payment out of existing cash resources.

The remaining milestones, which together with the above comprise the full US$85.5 million, are tied to engineering, procurement, manufacture and delivery-readiness activities, including issuance of piping and instrumentation diagrams (“P&IDs”) for hazard and operability review and for manufacturing, ordering of pre-treatment and column major materials, confirmation that all major equipment is ready for shipment, and Chart's submission of final documentation. The Company continues to advance financing alternatives for the remaining payments.

Cancellation Provisions

If Pulsar terminates for convenience, cancellation payments depend on the stage of work completed, ranging from 0% at project award to a maximum of 70% of the total contract value after Chart delivers final project documentation, and no cancellation payment arises for a milestone unless its payment had become due and been paid.

No finder's fee is payable in connection with the Transaction. Chart is an arm's length party to the Company.

On behalf of Pulsar Helium Inc.

“Cliff Cain”

Chief Executive Officer

Pulsar Helium Inc.

+ 1 (218) 203-5301 (USA/Canada)

+44 (0)2033 55 9889 (United Kingdom)

Strand Hanson Limited

(Nominated & Financial Adviser)

Ritchie Balmer / Rob Patrick

Canaccord Genuity Limited

(Sole Broker)

Henry Fitzgerald-O'Connor / Charlie Hammond

Velocity Public Affairs

(Public Relations)

Stephanie Moncada / Mike Zipko

+ 1 (218) 203-5301

Yellow Jersey PR Limited

(Financial Public Relations)

Charles Goodwin

About Pulsar Helium Inc.

Pulsar Helium Inc. is a publicly traded company quoted on the AIM market of the London Stock Exchange (United Kingdom) and listed on the TSX Venture Exchange with the ticker PLSR (Canada), as well as on the OTCQB with the ticker PSRHF (United States of America). Pulsar’s exploration and development portfolio comprises its flagship Topaz helium project in Minnesota, the Falcon project in Michigan (both in the USA), and the Tunu helium project in Greenland. Pulsar is the first mover in these project locations, with primary helium occurrences not associated with the production of hydrocarbons identified at each. Separately, the Company is advancing its proposed Rare Gas Hub in Minnesota.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note