Pulsar Upcoming Down-Hole Testing Jetstream Wells

In brief · summary, not quotable

Down-hole testing of Jetstream appraisal wells scheduled to commence February 24th, with flow testing planned for March.

  • Jetstream #1 total depth 5,100 feet (1,555 meters)
  • Jetstream #2 total depth 5,638 feet (1,718 meters)
  • Jetstream #1 helium-bearing interval 3,350 feet (1,021 meters)
  • Jetstream #2 helium-bearing interval 3,178 feet (969 meters)
  • Helium concentration observed up to 14.5%
  • CO2 concentration exceeded 70%
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your PLSR notes

NEWS RELEASEFEBRUARY 20, 2025CASCAIS, PORTUGAL

PULSAR HELIUM ANNOUNCES UPCOMING DOWN-HOLE TESTING OF THE JETSTREAM APPRAISAL WELLS, TOPAZ PROJECT, MINNESOTA, USA

Pulsar Helium Inc. (AIM: PLSR, TSXV: PLSR, OTCQB: PSRHF) ("Pulsar" or the "Company"), a leading helium project development company, is pleased to announce that down-hole testing equipment is scheduled to mobilise to site on Monday, February 24th. The tools consist of an optical televiewer and LithoScanner, both of which will be run on both the Jetstream #1 and #2 appraisal wells.

Summary

  • Down-Hole Testing: Involving optical televiewer and LithoScanner tools, is scheduled to commence on Monday, February 24th. The data collection process, expected to take approximately two days, will provide valuable insights into reservoir characteristics. Jetstream #1 was deepened to a total depth (TD) of 5,100 feet (1,555 meters), while Jetstream #2 reached a TD of 5,638 feet (1,718 meters).
  • Next Steps: Flow rate and bottom-hole pressure testing will occur in March 2025 once well head pressures are anticipated to have stabilised. The flow testing will be conducted over a period of up to two weeks for each well. All data will then be sent to an independent resource estimator for a resource update, and to Chart Industries for production scenario assessment and conceptual processing facility design.

Expanded Reservoir Potential

Elevated helium values were observed in both Jetstream #1 and #2 over a gross vertical thickness of 3,350 and 3,178 feet (1,021 and 969 meters), respectively. This consistency between wells suggests that the interpreted geophysical data accurately indicates that the helium-bearing zone extends beyond 2,200 feet (671 meters), which was the total depth of Jetstream #1 before deepening. The increased gross helium-bearing interval has the potential to enhance the project's resource potential, highlighting the significance of the Topaz Project.

Strategic Significance

The Jetstream #1 appraisal well reached a TD of 2,200 feet (671 meters) on February 27, 2024. This identified top-tier helium concentrations of up to 14.5%, significantly exceeding the widely accepted economic threshold of 0.3%. Moreover, CO2 concentrations exceeded 70%, which is expected to further enhance the project's economics. The recent deepening of Jetstream #1 and the completion of Jetstream #2 are crucial steps in advancing Pulsar's strategy to meet the growing global demand for helium as the Company progresses toward its production objective.

On behalf Pulsar Helium Inc.

"Thomas Abraham-James"

President, CEO and Director

Pulsar Helium Inc.

+ 1 (218) 203-5301 (USA/Canada)

+44 (0) 2033 55 9889 (United Kingdom)

Strand Hanson Limited

(Nominated & Financial Adviser, and Joint Broker)

Ritchie Balmer / Rob Patrick / Richard Johnson

OAK Securities*

(Joint Broker)

BlytheRay Ltd

(Financial PR)

Megan Ray / Said Izagaren

About Pulsar Helium Inc.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note