CatalystWireBeta

Preliminary Economic Assessment for Bibemi Project

In brief · summary, not quotable

Oriole Resources PLC has submitted an amended technical report for its 50% owned Bibemi Gold Project in Cameroon, including a Preliminary Economic Assessment (PEA) supporting the Exploitation Licence Application. The PEA outlines an open pit mine scenario targeting approximately 89,000 ounces of in-situ gold grading 2.20g/t Au, largely within the 100,000oz Indicated Resource at Bakassi Zone 1. Based on a US$3,200 per ounce gold price, the project projects a seven-year mine life with total gold production of 72,000oz, average annual production of 10,000oz, an all-in sustaining cost of US$1,243/oz, and initial capital expenditure of US$60.4 million, with an estimated payback period of four years. The company anticipates receiving an Exploitation Licence in the first half of 2026, with significant upside potential from further resource conversion.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your ORR notes

Preliminary Economic Assessment for the Bibemi Gold Project, Cameroon to support Exploitation Licence Application Process

Oriole Resources PLC (AIM: ORR), the AIM quoted gold exploration company focused on West and Central Africa, is pleased to provide an update on its 50% owned Bibemi potential open pit gold mine project ('Bibemi' or the 'Project') in Cameroon, including results from its internal Preliminary Economic Assessment ('PEA').

Highlights

  • Amended detailed technical report (the 'Report') submitted to the Cameroon Ministry of Mines, Industry, and Technological Development ('Ministry of Mines') to expedite the Exploitation Licence Application ('ELA') process and which incorporates comprehensive technical progress achieved by the Company during 2024/25.
  • The Report includes an internal PEA that focuses on an optimised open pit mine scenario for exploiting approximately 89,000oz in situ contained gold grading 2.20g/t Au, largely centred within the 100,000oz contained Indicated Resource at the Bakassi Zone 1 ('BZ1') MRE deposit, published in May 2025.
  • Summary base case parameters using a US$3,200 per ounce gold price (unless otherwise stated), 85% treatment plant recovery and costs to scoping study levels of confidence, are tabulated below (see 'Further Details' section for expanded table):

Bibemi Gold Project Preliminary Economic Assessment Base Case Summary 1

Production

Life of Mine ('LoM')7 years
Total gold production72,000oz
Average annual gold production10,000oz
Average all-in sustaining cost ('AISC') over LoMUS$1,243/oz
Initial capital expenditure ('CAPEX')US$60.4m
Gold price usedUS$3,200/oz
Estimated pay-back period4 years
NPV @ 8% after tax @ US$3,200/ozUS$12.8m
Equity Internal Rate of Return ('IRR') after tax19% 3
Total after tax free cash flow @ US$3,200/ozUS$39.8m
NPV @ 8% after tax @ US$4,000/ozUS$34.9m 2
Total after tax free cash flow @ US$4,000/ozUS$72.7m 2

1 Costs to scoping study levels of confidence (+/-30%) and all figures are rounded

2Does not include any price-based increase in Resources.

3 Subject to final agreement on taxation and utilities pricing during the negotiation period.

  • Productive meetings took place in Cameroon's capital Yaoundé last week between the Company and the relevant government authorities responsible for the ELA negotiations.
  • Following the negotiation period to finalise the Cameroon Government's tax and customs regime for the potential open pit mine, the Company hopes to receive an Exploitation Licence in the first half of 2026.
  • Future production expansion and mine life extension potential through the conversion of the wider JORC Mineral Resources (additional 371,000oz Au contained) and Exploration Target (range of 3 to 5Mt at 1.50 to 2.50g/t Au for 145,000oz to 400,000oz contained gold, covering Bakassi Zone 1 and three further prospects) offers significant upside to the overall Project economics. The Exploration Target is conceptual in nature and additional exploration work will be required to determine whether it can be converted to a Mineral Resource.

Chief Executive Officer of Oriole Resources, Martin Rosser, said: "We are pleased to have submitted the amended detailed technical report to the Cameroon Ministry of Mines, which is an important milestone as the Company seeks to be granted an Exploitation Licence for the Bibemi Project.

"The Preliminary Economic Assessment for the selected Bibemi gold project mine scenario, which formed part of the technical report, shows that, based on the work completed to date, the Project has mine development potential.

"The mine plan has focused on extracting the bulk of the gold contained in the Indicated Resource using an expandable modular skid-mounted treatment plant design which would offer future operational flexibility, and potential for treatment plant capital intensity economies of scale. This flexibility to expand potential production is supported by the fact that less than 20% of the Project's total contained gold resources are incorporated into the PEA. Accordingly, there is encouraging scope for upgrading the existing Inferred Mineral Resources and Exploration Targets for all prospects, including those within and in close vicinity to the main BZ1-MRE zone.

"We look forward to the results from further technical studies, including more detailed metallurgical test work, to determine more accurate PEA parameters."

The Company has submitted an updated Report to the Ministry of Mines, to support the ELA process. The Report has incorporated the updated JORC Resource and Exploration Target, published in May 2025, mineral processing studies, all of the mine planning work and other technical studies that the Company has completed since the initial submission, and a PEA model.

The PEA focuses on an optimised open pit mine scenario with approximately 89,000oz contained in situ gold grading 2.20g/t Au, which is largely centred within the 100,000oz Indicated Resource published earlier this year (see announcement dated 15 May 2025).

Using a US$3,200 gold price, 85% treatment plant recovery and costs to scoping study levels of confidence (+/-30%), the PEA has estimated a seven-year LoM producing, on average, 10,000oz Au per annum. The initial CAPEX of US$60.4m is expected to be paid back in four years, with the selected optimised pit to 150m depth generating an NPV at 8% of US$12.8m and an equity IRR of 19%, subject to final agreement on taxation and utilities pricing during the negotiation period. The LoM average AISC is estimated at US$1,243/oz. A higher gold price of US$4,000 gives a marked increase in the NPV8% to US$34.9m.

Bibemi Gold Project Preliminary Economic Assessment Base Case Summary 1

Production

LoM7 years
Treatment plant design throughput190,800tpa
Head grade2.09g/t
Processing plant recovery85%
Total gold production72,000oz
Average annual gold production10,000oz
Total run of mine material ('RoM') to plant1.3Mt
Total waste mined16.8Mt
Total rock mined18.1Mt
Average waste : mineralised material strip ratio13.3
Operating costs
Mineralised and waste mining costsUS$2.4/t
Processing cost per tonne treatedUS$30.1/t
G&A costUS$5.0/t
Total cost per tonne processedUS$69.6/t
Total cash cost per gold ounce soldUS$1,218/oz
Average AISC over LoMUS$1,243/oz
Capital expenditure
Treatment plantUS$35.8m
All others Capex including 10% contingency and pre-stripUS$24.6m
Initial CAPEXUS$60.4m
Sustaining CapexUS$1.8m
Mine closure costsUS$3m
Total LoM CapexUS$65.2m
Base case economics
Gold price usedUS$3,200/oz
Pay-back period4 years (est.)
NPV @ 8% after taxUS$12.8m 2
Equity IRR after tax19% 3
Total after tax free cash flowUS$39.8m 2

1 Costs to scoping study levels of confidence (+/-30%) and all figures are rounded

2Using a US$4,000 gold price gives an NPV8% of US$34.9m and a total after tax free cash flow of US$72.7m, not including any price-based increase in Resources.

3 Subject to final agreement on taxation and utilities pricing during the negotiation period.

Note that the Equity IRR is after SONAMINES', the Cameroon state mining company, 10% free-carried interest, but has been calculated using certain assumptions around the treatment of other taxes and utilities costs. These taxes and costs will be finalised during the negotiation period.

The technical work completed to date is considered to be of a scoping study level in terms of mining industry standards. All metrics are therefore provisional in nature and are considered to be within +/-30% accuracy and subject to revision as a result of additional studies and modelling.

Negotiations to secure the Exploitation Licence, and agree the commercial terms are ongoing, with a targeted completion date of Q2-2026.

JORC Code2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
kmKilometre
km 2Square kilometre
LoMLife of Mine
MbeMbe orogenic gold project
mMetres
MREMineral Resource Estimate
MtMillion tonnes
Oriole ResourcesOriole Resources PLC
ozTroy ounce of gold
PEAPreliminary Economic Assessment
RoMRun of Mine
tpaTonnes per annum
t/m 3Tonnes per cubic metre

At the 177km2 Bibemi orogenic gold project in the North region of Cameroon, the Company's exploration to date has identified shear-hosted gold mineralisation at four main prospects - Bakassi Zone 1, Bakassi Zone 2, Lawa West and Lawa East - within an approximately 12km long mineralised hydrothermal system at surface.

Between 2021 and 2022, the Company completed four phases of diamond drilling at the Project for a total of 6,685.40m in 54 holes, with the majority of that drilling focused on an approximately 1km long section at the BZ1-MRE zone. Following a maiden MRE published in 2022, and an updated MRE published in 2024 (using Phase 1-4 data), the Company completed a Phase 5 diamond drilling programme in February 2025. This programme targeted the Bakassi Zone 1 to further test the BZ1-MRE zone, and two along-strike targets, BZ1-NE and BZ1-SW, for 6,915.40m in 56 holes.

These additional Phase 5 drill results enabled independent consultant Forge International to deliver an updated MRE for the BZ1-MRE zone of 460,000oz contained gold at over 2g/t Au, based on a 0.40g/t Au lower cut-off grade and within a US$2,750/oz gold price open pit shell. In addition to this being an approximate 23% increase on the 2024 MRE, the confidence level of the MRE was improved, with 100,000oz Au falling into the JORC Indicated category and the remaining in the Inferred category. The Indicated Resources occur as a unified block in the centre of the deposit and could provide a suitable location for a starter pit if mined. An additional JORC Exploration Target range of 3 to 5 million tonnes at 1.50 to 2.50g/t Au for 145,000oz to 400,000oz contained Au has been estimated for the Bakassi Zone 1, Bakassi Zone 2, Lawa East and Lawa West prospects, highlighting the significant upside potential of the wider licence area.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note