Neo Energy Metals plc has provided an update on its conditional acquisition of the Beisa Uranium and Gold Project from Sibanye-Stillwater, which includes current SAMREC-compliant resources of 1.2 million ounces of gold and 26.9 million pounds of uranium. The company has initiated an Implementation Assessment to guide the recommencement of gold and uranium production within 18 to 24 months, with a phased approach planned over four stages, targeting first uranium sales in H1 2027. Regulatory approvals from South Africa and the UK are anticipated in Q1 2026, following which the company will issue share consideration and finalize cash consideration payments. Neo Energy has secured a ZAR1.2 billion (£50.4 million) loan facility for working capital and is proceeding with a Rule 9 waiver for Sibanye-Stillwater's potential 40% shareholding.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your NEO notes

Neo Energy, the near-term, low-cost uranium developer, is pleased to provide a comprehensive update on the ongoing regulatory processes, project integration workstreams and key milestones associated with the conditional acquisition of the Beisa Uranium and Gold Project, including Beatrix 4 shaft complex, and associated infrastructure (the "Beisa Mine") through its majority owned subsidiary, Neo Uranium Resources Beisa Mine (Pty) Limited ("NURB"), from Sibanye Gold Proprietary Limited ("SGL"), a wholly owned subsidiary of Sibanye-Stillwater Limited ('Sibanye-Stillwater').

The Beisa Mine, which has current SAMREC-compliant measured and indicated resources of 1.2 million ounces of gold and 26.9 million pounds of uranium, is located in the Witwatersrand Basin, in the Free State Province of South Africa. Operations commenced at the Beisa Mine in the early 1980s and both uranium and gold were produced from the Beatrix 4 Shaft Complex and adjoining processing facilities up until it was placed on care and maintenance in late 2023.

The Company's executive management has now commenced a comprehensive Implementation Assessment to define operational readiness and the roadmap for production of gold and uranium from the Beisa Mine to commence within the next 18 to 24 months. The Implementation Assessment addresses all matters associated with mining gold and uranium, including the operational environment, regulatory issues with respect to underground mining, requisite licences for the handling of naturally occurring radioactive materials, tailings deposition facilities, and security. Various comprehensive studies on the re-commencement of mining and processing of uranium and gold at the Beisa Mine completed previously by Sibanye-Stillwater are under review and form part of this Implementation Assessment.

To support the increased activities in South Africa, an expansion to the executive management team is well advanced and senior financial as well as technical appointments will commence in early 2026 with the implementation of systems and controls to support the proposed operational rollout.

Under the Implementation Aseessment, it is currently proposed that the re-commencement of mining and processing activities at the Beisa Mine will proceed in four phases:

  • Phase 1A (months 0-3) covering site re-establishment, shaft refurbishment initiation, workforce recruitment engagement, and financing package finalisation;
  • Phase 1B (months 3-9) for shaft equipment upgrades, underground development, gold plant recommissioning, and uranium circuit design finalisation;
  • Phase 1C (months 9-15) for uranium plant construction, processing circuit integration, safety systems upgrade, and regulatory inspections; and
  • Phase 1D (months 18-24) for production ramp-up with first ore production, processing commissioning, ramp to nameplate capacity, and first uranium sales targeted in H1 2027.

Regulatory matters with respect to uranium mining and processing are being addressed and the risk contractors, retained by the Company, are compiling the Risk Register, with a view to taking operational control of the mine site. Mining and metallurgical consultants have been identified and will be retained with a view to the long-term operational success of the Beisa Mine.

The acquisition of the Beisa Mine, remains subject to regulatory approvals in South Africa and the United Kingdom and settlement of the cash and share based consideration to Sibanye-Stillwater. Applications for regulatory approval from the South African Department of Mineral Resources and Energy ("DMRE") were submitted by Sibanye-Stillwater in May 2025. These applications cover approvals required under Section 11 and Section 102 of the Mineral and Petroleum Resources Development Act ("MPRDA"), enabling, transfer of ownership of the Beisa Uranium project to NURB. The Company continues to work closely with Sibanye-Stillwater, the SSC Group and legal advisors in order to advance these approvals to completion, and which are currently outstanding.

The Company has already received approval from the South African Reserve Bank ("SARB") for a foreign inter-company shareholder loan facility of ZAR1.2 billion (approximately £50.4 million) for working capital purposes between the Company and Neo Uranium Resources South Africa (Pty) Ltd ("NURSA"), enabling efficient inflow of funds into South Africa subject to compliance with SARB reporting and exchange control requirements.

In the United Kingdom, the Company has already appointed Rule 3 adviser in connection with the Rule 9 waiver ("Waiver") required under the City Code on Takeovers and Mergers ("Takeover Code") that is required. The Waiver relates to the conditional issue of new shares to Sibanye-Stillwater as part of the transaction under which it is expected to become the Company's largest shareholder with up to an approximate 40% holding.

The Company anticipates that it will obtain all the necessary outstanding regulatory approvals in South Africa and in the United Kingdom in Q1 2026. With this received the Company will then be able to issue the share based consideration due to Sibanye-Stillwater under the conditional acquisition agreement to acquire the Beisa Mine, and then finalise its funding arrangements with its corporate advisors and corporate brokers to settle the cash consideration also due to Sibanye-Stillwater.

The Company will continue to provide further updates on its progress with the regulatory approval and its funding arrangements.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note