Total Resource increased to 31.9 Mt at 1.06% Li2O

Kodal Minerals, the mineral exploration and development company focused on lithium and gold assets in West Africa, announces a new JORC Mineral Resource estimate (MRE) for the Bougouni Lithium Project located in southern Mali ("Bougouni") of 31.9 million tonnes (Mt) at 1.06% Lithium Oxide (Li2O), an increase of over 40% from the previous Mineral Resource completed in 2019. The significant increase is specific to the Ngoualana and Boumou deposits following the drilling programmes completed in early 2023.

The updated Mineral Resource estimate has been prepared as part of the development plans for Bougouni. As previously announced, the Company plans for a two stage development strategy: Stage 1 through processing ore from the Ngoualana deposit through a dense media separation ("DMS") process plant; and Stage 2 through processing ore from the Boumou and Sogola-Baoulé deposits through a flotation plant.

Highlights

  • The 40% increase in Bougouni's spodumene resource adds 10.6Mt to bring the overall MRE to 31.9Mt at 1.06% Li2O following 3,230 metres of RC/diamond drilling during 2023.
  • New JORC Mineral Resource estimates have been prepared for the Boumou and Ngoualana prospects:

o Boumou: 13.1Mt at 1.04% Li2O, an increase of 236% from the 2019 estimate

(Boumou Resource reported using a 0.75% Li2O lower cut-off, no top cut-off)

o Ngoualana: 6.7Mt at 1.00% Li2O, an increase of 9% from the 2019 estimate

(Ngoualana MRE reported using 0.5% Li2O lower cut-off, no top cut applied)

The MRE update also improves Kodal management's confidence in the previously defined resource at the Ngoualana prospect ahead of the proposed DMS mining development.

  • Sogola-Baoulé prospect has a resource of 12.2Mt at 1.1% Li2O, which is unchanged from the 2019 resource estimate, and the next phase of drilling will include additional metres with potential to expand Sogola-Baoulé.
  • Boumou prospect remains open along strike and drilling is planned to commence in late November 2023 to target an additional 750m strike length.
  • Ngoualana resource is undergoing open pit optimisation and the mine design is being updated to capture the increased resources, and to support the final planning of the Ngoualana prospect's DMS development.
  • The next drilling campaign will commence imminently, focussing on further resource definition, infill and exploration drilling at Boumou and Sogola-Baoule prospects, as well as those not included in the MRE to date including Kola and Bougouni South, all within the current Bougouni mining licence.

Commenting on the 40% increase in Bougouni's MRE, Bernard Aylward, CEO of Kodal Minerals, stated: "The significant increase in Bougouni's lithium endowment is a further step towards becoming a West African spodumene producer of substance and scale. With the results from the latest drilling campaign delivering over 10Mt of resource, we are looking forward to bringing Bougouni into production at the end of 2024, as well as ramping up the drilling programme to include infill and extension definition drilling, and uncovering additional discoveries within our extensive mining licence.

"The drilling campaign completed by Kodal between January and May this year was the first programme conducted at the Bougouni Lithium Project since 2019. The results of the drilling programme confirm our positive view of the prospectivity within our project area, while the updated MRE highlights the potential for further resource growth at the project through continued drilling of our priority targets. The Boumou prospect has been significantly expanded by this recent drilling programme, and we will be returning in November 2023 to seek to extend the resource area further as well as undertaking infill and definition drilling to support future mine planning.

"The Ngoualana prospect resource has confirmed and expanded the 2019 resource estimate, and the new model has been prepared with a focus on the bulk commodity mining opportunity. This new model seeks to maximise the recovery of the pegmatite mineralisation during the mining process rather than attempting to selectively mine higher grade ore that may result in leaving mineralisation behind.

"We are currently planning the next phases of extension and definition drilling at the Bougouni Lithium Project with the Boumou prospect being a clear priority. However, the Sogola-Baoulé prospect is also a key expansion target as we look to build a major resource base to support the development of the phase 2 flotation plant. The aim of the programme is to demonstrate the potential to bring forward the development of the flotation plant as soon as possible after the DMS plant has been fully commissioned and maximise the opportunity we have at the Bougouni Lithium project."

This updated MRE has been completed by independent consultants ERM (formerly CSA Global). Kodal supplied a geological database and verified the geological interpretation that was used to define the lithium mineralised pegmatite bodies.

Resource updates were completed for the Ngoualana and Boumou prospects following additional reverse circulation ("RC") and diamond drilling. The updated JORC compliant Mineral Resource estimate for the Bougouni Lithium project, including the Sogola-Baoulé, Ngoualana and Boumou prospects is tabulated below:

ProspectIndicatedInferredTotal
Tonnes (Mt)Li 2 O% GradeContained Li 2 O (kt)Tonnes (Mt)Li 2 O% GradeContained Li 2 O (kt)Tonnes (Mt)Li 2 O% GradeContained Li 2 O (kt)
Sogola-Baoulé8.41.0991.93.81.1342.812.21.10134.8
Ngoualana3.21.1938.03.50.8228.56.71.0066.7
Boumou13.11.04135.813.11.04135.8
TOTAL11.61.12129.920.31.02207.131.91.06337.2

Notes: Sogola-Baoulé resource estimate unchanged from 2019. A 0.5% Li2O lower cut-off applied, and resource wireframe defined by a 0.3% Li2O selected boundary. Estimate completed utilising Surpac software.

Ngoualana resource estimate reported utilising a 0.5% Li2O lower cut-off. All pegmatite mineralisation modelled including zones of internal waste material for a fully diluted model. The geological model of the mineralisation is completed using Leapfrog modelling software. The Mineral Resource estimation is completed using Surpac software with grades estimated by Ordinary Kriging.

Boumou resource reported using a 0.75% Li2O lower cut-off. All pegmatite mineralisation modelled including zones of internal waste material for a fully diluted model. The geological model of the mineralisation is completed using Leapfrog modelling software. The Mineral Resource estimation is completed using Surpac software with grades estimated by Ordinary Kriging.

Figures in table may not sum due to rounding. The contained metal is determined by the estimate tonnage and grade.

The JORC code Table 1 with details of the resource estimate parameters is available to view on the Company's website at www.kodalminerals.com

Exploration and Development Programme

At the Ngoualana prospect, the Company is continuing with the rapid development of the Bougouni Lithium Project with a focus on the development of the proposed DMS plant to process the coarse grained mineralisation identified within this prospect. The updated mineral resource estimate for the Ngoualana prospect is currently undergoing an update to the open pit optimisation to finalise the open pit design and results are expected later this year.

Kodal is currently finalising an extension and definition drilling programme for the Boumou prospect where this new resource has highlighted a major increase in the previous estimate and in particular has confirmed the potential for further significant additional mineralisation along strike and at depth. The drilling programme will consist of:

o RC drilling to continue to target strike extensions over an additional 750m to the west, as well as new targets identified to the east of the prospect

o Diamond drilling to provide geological and structural control features of the pegmatite veins which in turn will enhance success of ongoing targeting

o Diamond drilling to provide metallurgical samples for testing to confirm the recoveries and possible material to supplement the proposed DMS plant and/or future flotation plant, which in both cases will support increased life of mine potential

o Diamond drilling to provide geotechnical information for future open-pit mining.

The Company anticipates that the Boumou and Sogola-Baoulé region will continue to demonstrate the potential for the development of the proposed 2Mtpa flotation plant (Phase 2) outlined in the Company's Feasibility Study (refer to Kodal's announcement of 27 January 2020).

In addition to the detailed programme at the Boumou prospect, the Company intends to undertake further drilling at the Kola, Bougouni South and Sogola-Baoulé prospects. Both Kola and Bougouni South do not currently figure in the Mineral Resource estimate and provide further potential for resource increase.

"cut off"the lowest grade value that is included in a resource statement. It must comply with JORC requirement 19: "reasonable prospects for eventual economic extraction" the lowest grade, or quality, of mineralised material that qualifies as economically mineable and available in a given deposit. It may be defined on the basis of economic evaluation, or on physical or chemical attributes that define an acceptable product specification
"Inferred" or "Inferred Resource"that part of a Mineral Resource for which tonnage, grade and mineral content can be estimated with a low level of confidence. It is inferred from geological evidence and assumed but not verified geological and/or grade continuity. It is based on information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes which may be limited or of uncertain quality and reliability
"Indicated" or "Indicated Resource"that part of a Mineral Resource for which tonnage, densities, shape, physical characteristics, grade and mineral content can be estimated with a reasonable level of confidence. It is based on exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes. The locations are too widely or inappropriately spaced to confirm geological and/or grade continuity but are spaced closely enough for continuity to be assumed
"JORC"The Australasian Joint Ore Reserves Committee Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves 2012 (the "JORC Code" or "the Code"). The Code sets out minimum standards, recommendations and guidelines for Public Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves
"MRE" "Mt"Mineral Resource estimate million tonnes
"Kt"thousand tonnes
"Reserve"the economically mineable part of a Measured and/or Indicated Mineral Resource
"t"tonne (= 1 million grams)

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note