Azteca Refurbishment Complete

In brief · summary, not quotable

Cadence Minerals plc has achieved mechanical completion of the Azteca processing plant refurbishment at the Amapá Iron Ore Project, with commissioning scheduled to commence next week. The company reported no safety incidents during the refurbishment period, which saw the plant progress from approximately 48% completion on July 2, 2026, to full mechanical completion on September 4, 2026. Commercial operations and shipments are contingent upon successful commissioning and the receipt of the operating licence. Cadence's total investment in the Amapá Project as of May 31, 2026, was approximately US$16.1 million, holding a 36.2% equity interest in the project owner.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your KDNC notes

Cadence Minerals plc (AIM: KDNC) announces that refurbishment of the Azteca processing plant at the Amapá Iron Ore Project is complete, with mechanical completion achieved today. The plant now moves into commissioning. Commercial operations and shipments remain subject to successful commissioning and receipt of the operating licence (Licença de Operação) for Azteca (the "Operating Licence").

Highlights

  • Mechanical completion achieved: Refurbishment finished today. All eight plant systems are complete.
  • Execution delivered: Azteca advanced from approximately 48% completion on 2 July 2026 to mechanical completion on 4 September 2026.
  • Commissioning next: Cold commissioning is scheduled to start next week. Wet commissioning will follow, with hot commissioning subject to completion of the applicable regulatory requirements.
  • Safe delivery: No safety incidents were recorded during the reporting period.
  • Remaining gates clear: Commercial operations and shipments remain subject to successful commissioning and grant of the Operating Licence.

Kiran Morzaria, Chief Executive Officer, commented:

"Mechanical completion closes the refurbishment phase. The next job is to prove the plant through commissioning.

We will progress sequentially through cold, wet and hot commissioning, identifying and resolving issues as they arise. Commercial operations and shipments remain dependent on successful commissioning and grant of the Operating Licence.

Azteca is intended to establish the first production and cash-flow platform at Amapá. Successful delivery would move the project from refurbishment into operations and support the wider redevelopment strategy."

Execution Update

All eight plant systems are complete: the hopper/feed system, transfer conveyor, screen, process tank, magnetic-separation circuit, piping, spiral concentrator and electrical system. The Company recorded no safety incidents during the reporting period.

Regulatory Position

The previously granted installation licence (Licença de Instalação) (the "Installation Licence") authorised the refurbishment and installation works now completed at Azteca. DEV has submitted its application for the Operating Licence to SEMA/AP.

DEV is permitted to undertake cold and wet commissioning. Hot commissioning remains subject to completion of the applicable regulatory requirements.

Grant of the Operating Licence remains required before commercial operations and shipments can commence.

Next Steps

Cold commissioning is scheduled to start next week. The completed equipment, electrical distribution and control systems will be tested without ore. Completion of this stage will allow the programme to move into wet commissioning.

Wet commissioning will introduce process water and trial material through the wet circuit. Following completion of this stage, hot commissioning will commence once the applicable regulatory requirements have been completed.

Hot commissioning will involve limited processing of run-of-mine material to tune plant grade and recovery. Any concentrate produced during this stage will be stockpiled. Commercial operations and shipments will remain subject to successful completion of commissioning and grant of the Operating Licence.

Cadence Ownership

As of 31 May 2026, Cadence's total investment in the Amapá Project was approximately US$16.1 million. Cadence holds a 36.2% equity interest in Pedra Branca Alliance Pte Ltd ("PBA"), which owns 100% of DEV Mineração S.A. ("DEV"), the owner and operator of the Amapá Project.

About the Amapá Project

The Amapá DR Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, Azteca is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to successful commissioning, completion of related regulatory workstreams and receipt of the Operating Licence.

For further information, contact;

Cadence Minerals plc+44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker)+44 (0) 20 3829 5000
James Joyce
Darshan Patel Matthew Diaz-Rainey
Fortified Securities - Joint Broker+44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations - Brand Communications+44 (0) 7976 431608

Alan Green

Qualified Person

Cautionary and Forward-Looking Statements

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note