CatalystWireBeta

Vietnam Gas Sales Agreement Signed

In brief · summary, not quotable

Jadestone Energy PLC has signed a Gas Sales and Purchase Agreement for gas from the Nam Du/U Minh discoveries offshore Vietnam, with production targeted for late-2028. The agreement with PV Gas includes a daily contract quantity of 80 MMscf/d, approximately 13,000 boe/d gross, with a take-or-pay clause of 90% of the DCQ, equating to around 26 Bscf annually during the plateau period. The fields hold audited gross 2P reserves of 32 MMboe and an estimated 1.5 trillion cubic feet of gross unrisked gas in place, with potential for further upside. The company is focused on progressing towards project execution, with bid evaluations for the FPSO and field infrastructure planned for the second half of the year.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your JSE notes

20 April 2026 - Singapore: Jadestone Energy plc (AIM:JSE) (the "Company" and together with its subsidiaries, "Jadestone" or the "Group"), an independent upstream production and development company focused on the Asia-Pacific region, is pleased to announce the signing of the Gas Sales and Purchase Agreement ("GSPA") for the supply of gas from the Nam Du / U Minh discoveries offshore Vietnam.

"The execution of this agreement is a pivotal moment for Jadestone. After years of dedicated effort, we are now in a position to deliver the Nam Du/U Minh development, which will materially strengthen our portfolio while supporting our growth ambitions. With all key commercial and technical approvals now in place, and recent key hires into the Jadestone Vietnam project delivery team, we are now focused on rapidly progressing towards the project execution phase. Our near-term priorities are to conclude the bid evaluation for the FPSO and field infrastructure, and award their respective contracts during the second half of this year.

We thank all of our stakeholders in Vietnam for supporting the recent progress on Nam Du/U Minh, and we look forward to working with them to deliver the development safely and efficiently. Over the project life, we expect that the development and production phases will generate significant local employment opportunities, material contract awards to local Vietnam companies, and hundreds of millions of dollars in government revenues. The Nam Du/U Minh project also supports Vietnam's strategic plan and net zero ambitions, prioritizing sovereign resources to enhance Vietnam's energy security and economic growth alongside the transition to lower emitting sources of fuel."

Nam Du/U Minh GSPA

The Nam Du/U Minh discoveries are located offshore southwest Vietnam in shallow waters, with production targeted to commence in late-2028, as per the approved field development plan previously announced on 18 March 2026.

The finalized GSPA sets out the terms on which gas will be supplied from the Nam Du/U Minh fields offshore Vietnam to PV Gas, a subsidiary of Petrovietnam, the state-owned national energy industry group of Vietnam. Key elements of the GSPA include:

  • A daily contract quantity ("DCQ") of 80 MMscf/d, or ~13,000 boe/d (gross).
  • Maximum DCQ set at 110% of DCQ.
  • Take-or-pay is set at 90% of DCQ, equivalent to approximately 26 Bscf per year during the plateau period.
  • The wellhead gas price is comparable to historical Vietnam gas imports and subject to fixed annual escalation.

Combined, the Nam Du/U Minh fields contain independently audited gross 2P reserves of 32 MMboe. Jadestone estimates up to 1.5 trillion cubic feet of gross unrisked gas in place from seismically supported prospects within the existing licenses, much of which lies in close proximity to Nam Du/U Minh, representing low risk upside potential which could extend and/or increase plateau production from the initial development.

Glossary

2P ReservesProved and Probable Reserves. Those additional reserves which analysis of geoscience and engineering data indicate are less likely to be recovered than Proved Reserves but more certain to be recovered than Possible Reserves. It is equally likely that actual remaining quantities recovered will be greater than or less than the sum of the estimated Proved plus 2P. In this context, when probabilistic methods are used, there should be at least a 50% probability that the actual quantities recovered will equal or exceed the 2P estimate
boe/dbarrels of oil equivalent per day
Bscfbillion standard cubic feet
MMboemillion barrels of oil equivalent
MMscf/dmillion standard cubic feet per day

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.