Homase Gold Mine Update
No summary for this filing – the full text is below.
Select text to share a quote on X · sign in to keep highlights & notes in your GRL notes
Goldstone Resources Limited (AIM: GRL) is pleased to provide an update on the progress of operations in respect of the Homase Mine and heap leach operation in south-western Ghana ("Homase").
- Mining continues in Pit 2 which is expected to be completed late January 2025, with preparation work starting in Pit 1 to commence production in Q1 2025.
- Earthworks continue for the extension to Cell 5 and to Cells 6 and 7 and preparations for Cell 4 have begun to prepare for a second lift.
- To date the Company has poured c.1,920 troy ounces gold in 2024, compared to 1,257 troy ounces during 2023.
- Remain on schedule to meet the Company's target of 1,000 ounces gold production per month from January 2025, from 48,000 tonnes of stacked agglomerated ore per month.
Emma Priestley, Chief Executive Officer, commented:
"We remain on track to deliver our stated objective of producing 1,000oz pcm from January 2025, with our production profile at Homase improving week on week, and month on month. This improvement has been delivered throughout the rainy season, which has continued well into October this year. The dry season is now just around the corner and this will support our expansion plans throughout the current quarter and into the new year. I am delighted with our progress over recent months and I look forward to sharing further updates throughout Q4 2024."
Homase Mine, Pit 2, with Pit 1 in background Stacking of agglomerated ore continues on Cell 5