Hussar EP513 Equipment Procurement

In brief · summary, not quotable

Georgina Energy orders casing, tubing and cementing equipment for Hussar EP513 well drilling in Western Australia.

  • Hussar well planned depth approximately 3,200 metres
  • Casing and tubing approximately 3,200 metres
  • Planned drilling duration approximately 50 days
  • Seismic fieldwork approximately 30 days
  • Hussar unrisked prospective helium resources 283 BCF
  • Hussar unrisked prospective hydrogen resources 315 BCF
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your GEX notes

Georgina Energy Plc, (LSE: GEX.L), a helium, hydrogen and natural gas exploration and development company with strategic permits in Australia, announces the procurement of key casing, tubing, cementing and float equipment required to drill the Hussar EP513 well in Western Australia.

Together with the wellhead equipment ordered from Cactus Wellhead, announced on 6 November 2026, these orders are key elements required to drill Hussar. With Ensign notified to mobilise the contracted Ensign 970 rig, the key remaining step before drilling is moving the rig to Hussar and rigging up on site.

Highlights

 Long-lead procurement complete: with these orders and the wellhead, [all long-lead equipment for the Hussar well is now on order].

 Casing and tubing: approximately 3,200 metres of surface, intermediate and production casing, together with production tubing, ordered for the Hussar well.

 Float, cementing and liner equipment: liner hanger system, float shoe, float and landing collars, cement plugs, centralisers and stop collars ordered.

 Drilling programme: the Hussar well is planned at approximately 50 days of drilling to a planned depth of approximately 3,200 metres.

 Site works completed: All civil engineering and site preparation works at Hussar EP513 have been completed to support the Hussar Drilling program

 Seismic programme: Formal applications have been submitted to the Department of Mines, Petroleum and Exploration (“DMPE”) with regulatory and Traditional Owner approvals pending and the programme budget being finalised for proposed funding by Harlequin Energy.

The Ensign 970 at its current location in Western Australia, ahead of mobilisation to Hussar.

Drilling Equipment

The Company has placed orders for the casing, tubing, cementing and float equipment required for the Hussar well. These include approximately 3,200 metres of surface, intermediate and production casing, together with production tubing and a VersaFlex expandable liner hanger system, to be run and cemented in stages as the well is drilled.

The associated float, cementing and centralisation equipment ensures each casing string is correctly positioned and cemented, providing well integrity throughout the drilling programme.

These items, together with the Cactus Wellhead equipment, are prerequisites for drilling. Procuring them ahead of the rig’s arrival allows delivery to be coordinated with the mobilisation of the Ensign 970, so drilling can commence once the rig is rigged up on site.

Anthony Hamilton, Chief Executive Officer of Georgina Energy, commented:

“The ordering of the casing, cementing and float equipment, following the wellhead, and preparations for mobilisation of the Ensign 970 rig represent an important milestone as we progress towards drilling. We continue to work closely with our contractors to progress the safe mobilisation of the Ensign 970 rig. Drilling Hussar and evaluating its significant helium, hydrogen and natural gas potential remains our priority, and we look forward to providing further updates as mobilisation arrangements progress."

Rig Mobilisation and Site Access

As previously announced, work continues the access road works with improvements to the Eagle Highway route from the Mangkili turn-off on the Gunbarrel Highway to the Hussar wellsite.

The Company is working closely with its contractors and advisers to address weather-related road restrictions and facilitate the safe mobilisation of the Ensign 970 drilling rig, with the safety of personnel and equipment remaining the priority.

Further updates on mobilisation arrangements and the revised spud date will be provided in due course along with additional site photos which can be viewed by shareholders on the Georgina website.

Seismic Programme

In parallel with preparations for drilling, the Company has submitted formal applications for the proposed Hussar seismic programme to the Western Australian Department of Mines, Petroleum and Exploration (DMPE).

The seismic program does not require heavy vehicle access and will use modern lightweight seismic techniques and equipment designed to minimise environmental disturbance.

The proposed survey will involve approximately 30 days of fieldwork, subject to the receipt of the necessary Western Australian DMPE and Traditional Owner cultural heritage approvals expected to be issued shortly.

The Company is also finalising the programme budget, which is intended to be funded by Harlequin Energy.

Hussar Resource Potential

The Hussar prospect is supported by an Independent Geological Report dated 1st February 2026, prepared by Competent Person Mr Maki Petkovski, which estimates unrisked SPE PRMS (the Society of Petroleum Engineers and Petroleum Resource Management Systems) net attributable 2U Prospective Resources of 283 BCF helium, 315 BCF hydrogen and 2.93 TCF of hydrocarbon gas.

Based on the pricing of Helium US$450/MCFG and Hydrogen US$2.65/kg and US$8/MCF for hydrocarbon gas, these volumes would equate to a total potential combined net attributable unrisked potential in-situ value of c.US$152 billion. These are estimates in-situ values from the AER (Australian Energy Regulator) and HNT (Helium Price Index) developed by the Company based on unrisked prospective resources; they exclude production, separation and transport-to-market costs, and there is no certainty that any part of these resources will be commercially recovered.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note