Results reading: Half-year Results
The interim report adds little on Hussar operations, but it shows how the project is being funded: the share price paid in placings rose from 2.7p to 12.5p, going concern is still a material uncertainty, and a Riverfort convertible loan was repriced from 8p to 2.7p. Against the May promise of Q3 2026 drilling, Hussar has not spudded and the 28 October update puts spud at least 8-10 weeks after rig mobilisation is ordered, which the interim chairman's statement does not mention.
What changed against what was known
-
Worse
Hussar drilling has slipped past the Q3 2026 target given in May: the rig is not on site and only the water-well works are under way. The interim statement does not mention the delay or the extra mobilisation costs disclosed on 28 October.
Then · 29 May 2026 · Audited Final Results for Year Ended 31 Jan 2026“Re-entry drilling of Hussar scheduled for Q3 2026” -
New
The Hussar funding wording has moved on from a non-binding $25m Harlequin offtake facility to an 'arrangement' with an unnamed offtake finance provider. It is now said to remove the need to raise production funding, but no amount or terms are given.
Then · 29 May 2026 · Audited Final Results for Year Ended 31 Jan 2026“Structured off-take funding facility of $25 million with Harlequin Energy for the drilling of Hussar” -
New
Placing prices rose steeply: about 37.0m shares at 2.7p in May and 20.0m at 5p in June, then about 22.3m at 9p in August and 20.0m at 12.5p in late August and early September. The post-period placings raised roughly £4.5m, a lot against the £0.27m cash held at 31 January 2026, but no cash balance at 31 July is given in the material.
“On 27 August 2026 the Company issued 10.0m new ordinary shares at a price of 12.5 pence per share in a private placing to new equity investors.” -
Worse
The Riverfort convertible's conversion price reset from 8p to 2.7p after the May placing at 2.7p. The £0.8m drawn could convert into roughly three times as many shares (about 30m instead of 10m, before any repayment).
“The conversion terms of the loan include fixed conversion at 8 pence per share, however included in the conversion terms is a conversion price reset clause which is triggered if the Company raises equity funding within the term of the loan at a price lower...” -
Better
Mt Winter moved forward: the Aboriginal Land Rights Agreement terms were agreed with the Central Land Council in June 2026, up from a draft under review in the May report. Traditional Owner signature and the Minister's grant of the permit are still needed before the acquisition completes.
Then · 29 May 2026 · Audited Final Results for Year Ended 31 Jan 2026“Received draft of the Aboriginal Land Rights Act Agreement from Central Land Council in February 2026, currently under review, following which 100% acquisition will be approved”
What the notes say – not in the headline numbers
The group is still a going concern with a material uncertainty. The directors rely on equity raises, convertible notes, debtholder deferrals and the offtake finance arrangement, with no certainty any of these will be secured.
Funding still depends on the market, and the Hussar drilling delay probably pushes costs higher.
“However, as there may be no certainty over the securing of additional funding over this period, there exists a material uncertainty which may cast significant doubt on the group’s ability to continue as a going concern.”Current borrowings include £409,369 owed to Riverfort under a £1m convertible facility, with £0.8m drawn (£300,000 in November 2025 and £500,000 in January 2026). The conversion price reset to 2.7p, and warrants were issued with each drawdown.
The reset and the warrants mean more dilution for existing shareholders than the original 8p terms implied.
“The loan was drawn by £300,000 in November 2025 and by a further £500,000 in January 2026.”The VAT provision owed to HMRC within other payables rose to £938,731 from £874,693 at 31 January 2026.
A growing tax liability for a pre-revenue company competes with drilling spend for cash.
“Included in other payables is a provision for £938,731 for VAT repayable to HMRC (31 January 2026: £874,693).”A convertible loan to WMC, a company controlled by Mark Wallace and Anthony Hamilton, totals £1,199,440 and has a carrying value of £905,694. WMC also received £48,652 of interest in the period (nil a year earlier) and paid about £0.3m of group costs on the group's behalf.
Related parties, including the CEO, are lenders and cash providers, so their terms and any repayment deserve scrutiny.
“During the six months ended 31 July 2026, £48,652 in interest payments were made to WMC (6m to 31 July 2025: nil) in service of a convertible loan payable to WMC totalling £1,199,440 and with a carrying value as at the reporting date of £905,694 (31...”The interim report's Hussar update (April entry) gives a prognosed total depth of about 2,800m, while the October announcements say about 3,200m, possibly extended.
A deeper well is likely to cost more and take longer, on top of the mobilisation cost increases already flagged.
“note the prognosed TD of the Hussar well is c.2,800m”Promises management made Track record →
-
On track
Complete the 100% acquisition of Mt Winter and begin re-entry drilling by mid 2027
ALRA terms agreed June 2026, but acquisition not completed and the permit is not yet granted. Deadline is June 2027, so there is time, though Hussar is the immediate priority.
“Georgina will complete the settlement with Mosman Oil & Gas including the payment of A$300,000 (from current working capital) on granting by the Minister of the permit.”
No longer mentioned
Inorganic growth / acquisitions (Central Petroleum)
Last said · 29 May 2026 · Audited Final Results for Year Ended 31 Jan 2026“While it was agreed to not proceed the Central Petroleum acquisition, it remains my driving ambition to seek value accretive organic and inorganic opportunities for the business and our shareholders where possible, and we will continuously assess how best...”Extension of Hussar resource area / additional well targets
Last said · 29 May 2026 · Audited Final Results for Year Ended 31 Jan 2026“Extension of resource area may provide additional future well target sites”
Not in this report at all – which can mean nothing, or a plan quietly dropped.
Watch at the next report
- Formal notice to Ensign to mobilise, and the revised Hussar spud date and final mobilisation costs.
- Grant of EP155 by the Minister, the A$300,000 payment to Mosman and the start of Mt Winter drilling approvals.
- Cash balance, drawdowns under the offtake finance arrangement, and further dilution from Riverfort conversions or new placings.
Read 29 Oct 2026 against the last statement, the previous results and the open promises. Quotes are the company's words; the rest is our reading. Not investment advice.