Market Update
Montepuez Ruby Mine's second processing plant is 95% complete, first rubies expected August 2025, final completion delayed to September.
- MRM PP2 construction completion 95%
- MRM ore processing capacity expansion 200tph to 600tph
- Expected first ruby production from PP2 August 2025
- Supply trucks delivered to MRM 287 out of approximately 300
Select text to share a quote on X · sign in to keep highlights & notes in your GEM notes
Share code on JSE:GML (General Segment of JSE Main Board) / AIM:GEM
("Gemfields" or the "Group" or the "Company")
Market Update
LONDON, 20 JUNE 2025
Gemfields hereby provides a market update regarding its three principal subsidiaries.
Montepuez Ruby Mine ("MRM")
Construction of MRM's second processing plant (or "PP2"), designed to triple MRM's ore processing capacity from 200tph to 600tph, is 95% complete and materially on budget.
PP2 is now expected to produce its first rubies during August 2025 courtesy of the plant's core components. Final completion of PP2, including the tailings belt conveyor and decanter centrifuge, is now expected to occur during September 2025.
Final completion has been delayed as a result of, inter alia:
- difficulties in obtaining the requisite work permits, particularly in relation to specialist electrical component installation, including the SCADA controls necessary to operate PP2;
- transport difficulties, including in relation to a key transformer which was damaged this month during transit (some 287 trucks related to the construction - out of an estimated 300 - have successfully completed their deliveries to MRM); and
- security and operational issues arising from, inter alia, high levels of illegal miner incursions.
The Group wishes to commend the sterling efforts of both the MRM team and the principal contractor, Consulmet (Africa) Limited, in positively navigating the very challenging circumstances experienced in the north of Mozambique during the 22 months since the project was first announced.
Kagem Emerald Mine ("Kagem")
As announced on 8 May 2025, Kagem has recommenced focused mining by re-opening two production points in the Chama pit with minimal waste mining. A measured further expansion of mining operations is expected from July 2025 and will be further shaped according to developing market conditions. A return to full-scale mining is not presently expected for some months.
Fabergé
The Group continues to explore strategic options in respect of Fabergé, the iconic and wholly-owned luxury-brand, following the completion of the rights issue which required the process to be paused.
GEMFIELDS
| GEMFIELDS.COM | INVESTORS | FOUNDATION | ||
| X | YOUTUBE | |||
| FABERGÉ | ||||
| FABERGÉ.COM | X | YOUTUBE | ||
KAGEM MINING LIMITED LINKEDIN
MONTEPUEZ RUBY MINING LINKEDIN
Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.