Firering Strategic Minerals plc is reporting significant operational progress at its Limeco asset in Zambia, with Kiln 2 achieving discharge rates exceeding 60 tonnes per day, and work commencing to bring Kilns 3 and 4 online in Q3 and Q4 respectively. The hydrated lime circuit has expanded to four operating units with a fifth under construction, and the limestone milling circuit is nearing completion with commissioning targeted for Q3. These developments are expected to support planned production expansion and meet increasing demand from mining, agricultural, and industrial markets.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your FRG notes

Firering Strategic Minerals plc (AIM: FRG), an emerging producer of high quality quick- and hydrated lime with a portfolio of critical minerals projects, is pleased to provide an update on operational progress at its producing lime asset in Zambia, Limeco Resources Limited ("Limeco").

HIGHLIGHTS

  • Kiln 2 performance continues to improve, with discharge rates of over 60 tonnes per day ("tpd") being achieved.
  • Work has commenced bringing Kilns 3 and 4 online, with commissioning expected in Q3 and Q4, respectively.
  • Hydrated lime circuit expanded to four operating units, with a fifth under construction.
  • Limestone milling circuit installation progressing, with commissioning targeted for Q3.
  • Commercial engagement increasing across mining, agricultural and industrial markets.

Youval Rasin, Chairman and Interim Chief Executive Officer of Firering, commented: "We are pleased with the continued operational progress at Limeco, with Kiln 2 performing in line with expectations as ramp-up advances towards its targeted output. At the same time, bringing Kilns 3 and 4 online has commenced as part of our planned capacity expansion. These developments position Limeco to increase production to meet the growing demand for our lime products."

DETAILS

Limeco

Limeco, the Company's vertically integrated quicklime and hydrated lime operation in Zambia, continues to progress operations, increasing its lime product range and capacity expansion across its business.

Performance at Kiln 2 continues to improve as process optimisation and ramp-up are advancing and discharge rates of over 60 tpd now being achieved, surpassing those of Kiln 1 and supporting the internal modifications made to this kiln.

Work to bring Kilns 3 and 4 online has commenced, with fabrication of piping connecting these kilns to the gasifier underway on site. Additional work includes fabrication of the hopper for the feed system to these kilns and modification of the burner system. Kiln 3 is expected to come online in Q3, with Kiln 4 scheduled for Q4 this year.

The manual hydrating circuit now comprises four units constructed in-house, with a fifth under construction. Each unit produces approximately eight tonnes of hydrated lime per shift. Automation of this process is planned once all four kilns are operational.

Serviceable components of the limestone powder milling circuit stored on site have been serviced and their integrity checked ahead of erection and installation. Preparations for additional civil works are being finalised, with commissioning of the milling circuit expected in Q3 this year.

Commercial activity continues to build, with increased sales engagement across mining, agricultural and industrial customers in the region. Newly branded lime bags are expected to support direct customer enquiries and improve brand visibility in regional markets.

Firering Strategic Minerals plc (AIM: FRG) is an Africa-focused producer and developer of industrial and critical minerals. The Company's near-term focus is the ramp-up of production at the Limeco project in Zambia, where Firering holds a 36.2% interest with an option to increase this to 45%. Once fully optimised, Limeco is expected to be among the largest lime operations in the region, supplying a range of mining, agricultural and industrial customers. Firering's portfolio also includes the highly prospective Atex Lithium-Tantalum Project in northern Côte d'Ivoire.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note